Case Summary (BLD) | | | 10/15/2015 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/18/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9259 issued 7-18-02 to the Park Apts. II.
|
Permanent Occupancy | | 7/17/2002 | 7/17/2002 | | DONE |
|
|
|
|
BLD-Final | 7/17/2002 | 7/17/2002 | 7/17/2002 | P | PASS |
Carl Dependahl
|
|
|
dave; Phone #: ###-#### 7/17/2002 2:41:55 PM
|
Fee Review-notes | 3/14/2001 | 3/14/2001 | 5/23/2002 | | DONE |
|
|
|
|
BLD-Final | 4/26/2002 | 4/26/2002 | 4/26/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/26/2002 at 08:12:13. Contact: ###-####. c/n rails, plbg, ok t/o 4/26/2002 5:05:52 PM
|
Temporary occupancy | | | 4/26/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4801 issued 4-26-02 to the Park Apts.
|
BLD-Final | 4/24/2002 | 4/25/2002 | 4/25/2002 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/24/2002 at 17:04:02. Contact: ###-####. cn issued not ready 4/25/2002 2:58:14 PM
|
FIRE-Final Inspection | 4/23/2002 | 4/24/2002 | 4/24/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 04/23/2002 at 15:38:38. Contact: ###-####.
|
BLD-Final | 4/23/2002 | 4/24/2002 | 4/24/2002 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/23/2002 at 15:39:31. Contact: ###-####.
|
Code Occupancy Approval | | | 4/11/2002 | | PASS |
|
|
|
SIGNED FINAL AS WE ARE HOLDING LARGE BOND FOR LANDSCAPE.
|
Case Summary (BLD) | | | 4/5/2002 | | |
|
|
|
|
BLD-Wall cover | 1/31/2002 | 2/1/2002 | 2/1/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/31/2002 at 18:04:32. Contact: .
2/1/2002 9:26:38 AM
|
BLD-Framing/Rough-in | 1/29/2002 | 1/30/2002 | 1/30/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/29/2002 at 17:35:32. Contact: ., c/n air seal stairs, stud shoes, etc 1/30/2002 5:33:41 PM
|
BLD-Aging Inspection | 12/24/2001 | 12/24/2001 | 12/27/2001 | | NR |
Carl Dependahl
|
|
|
apts,wip 12/27/2001 8:56:55 AM
|
Case Summary (BLD) | | | 12/6/2001 | | |
|
|
|
|
Case Summary (BLD) | | | 12/6/2001 | | |
|
|
|
|
BLD-Conference | 10/23/2001 | 10/23/2001 | 10/23/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/23/2001 9:00:25 AM w/ Otis L. at site re 1st fl shear walls...add'l eng'g req'd.
|
Plan resubmittals received | | | 10/10/2001 | | DONE |
|
|
|
Recieved one copy of cover letter and information from Structural Eng. Routed to Carl D. kmm
|
Print Pending Permit.LaserJet4 | | | 10/5/2001 | | |
|
|
|
|
BLD-Framing/Rough-in | 9/24/2001 | 9/25/2001 | 9/25/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/24/2001 at 17:11:29. Contact: ###-####. upper floor shear wall nailing ok 9/25/2001 10:28:04 AM
|
BLD-Framing/Rough-in | 9/19/2001 | 9/19/2001 | 9/19/2001 | P | PART |
Carl Dependahl
|
|
|
fr insp -dave shear 1st fl shear nailing ok. 9/20/2001 10:14:03 AM Still need eng's report re sheathing not to sill plates. 9/20/2001 10:21:48 AM
|
BLD-Framing/Rough-in | 9/10/2001 | 9/10/2001 | 9/10/2001 | P | PART |
Carl Dependahl
|
|
|
FR JIM ###-#### shear wall straps 1st to 2nd fl 9/10/2001 4:49:10 PM
|
BLD-Framing/Rough-in | 9/7/2001 | 9/7/2001 | 9/7/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### remainder 1st fl shear ok 9/7/2001 3:27:50 PM
|
BLD-Framing/Rough-in | 9/5/2001 | 9/5/2001 | 9/5/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### jim 1st fl shear ok 9/5/2001 3:44:15 PM
|
BLD-Foundation | 8/8/2001 | 8/8/2001 | 8/8/2001 | A | PART |
Carl Dependahl
|
|
|
###-####; slab ok 8/8/2001 3:32:09 PM
|
BLD-Foundation | 7/26/2001 | 7/26/2001 | 7/26/2001 | P | PASS |
Jim Storey
|
|
|
stem wall rebar ok 7/26/2001 9:26:01 AM
|
BLD-Footing | 7/5/2001 | 7/5/2001 | 7/5/2001 | P | PASS |
Jim Storey
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/4/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/11/2001 | | 5/25/2001 | | DONE |
|
|
|
TOOK TO MIKE P
|
Plan Reviewer's activity | | | 5/25/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/25/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/25/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/25/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2001 | | DONE |
|
|
|
called permit ready for pickup
|
Plan assigned to (M_P) | 3/12/2001 | | 5/25/2001 | | PASS |
Mike Phillips
|
|
|
5/25/2001 09:43:46 M_P - activity updated through activity BLDA022 from case BLD01-00600.
|
Routing - FIRE | 5/8/2001 | | 5/11/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/10/2001 | | DONE |
|
|
|
Received one copy of revised sheet C1.2. Contacted Chad Heimbigner requesting four additional copies. kmm
|
Plan resubmittals received | | | 5/1/2001 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS A1.6, S1.1, S1.2, A6.1, A6.2. TWO COPIES OF REVISED SHEETS A2.1, A2.2, A2.3, A2.4, A2.5, A3.1, A3.2, A3.3, A5.1, A6.1, A6.2, P-1. FOUR COPIES OF RESPONSE LETTER. ROUTED TO MIKE P. KMM
|
Plan Reviewer's activity | | | 4/11/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing - PLAN CHECK | 4/4/2001 | | 4/11/2001 | | FAIL |
|
|
|
Routing to fire.
|
Routing - PLUMBING | 3/30/2001 | | 4/4/2001 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/15/2001 | | 4/3/2001 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. KMM
Additional information required for further review.
|
Routing - PARKS DEPARTME | 3/28/2001 | | 3/30/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 3/20/2001 | | 3/28/2001 | | PASS |
|
|
|
Approved by SAR and TKW (DRH00-00239)
|
Routing - PUBLIC WORKS | 3/15/2001 | | 3/20/2001 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/15/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/2001 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2001 | | DONE |
|
|
|
|
Application received | | | 3/12/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/12/2001 | | |
|
|
|
|
Received Certificate of Value | | | 3/12/2001 | | DONE |
|
|
|
|