Description
Type "B-5" BUILDING * To construct a new two story, with basement and mezzanines 5,144 sq.ft. wood framed, 12 unit apartment building. The basement is 2,220 sq.ft and has two units @ 562 sq.ft and two units @ 548 sq.ft.each. The first floor is 2,220 sq.ft. and contains two units @ 562 sq.ft. and two units and 548 sq.ft. each. The second floor contains four units @ 615 sq.ft with a 116 sq.ft. mezzanine. All construction per the approved plans, attached comment list, CABO/ANSI A 117.1. DRH 00-00239 CUP 00-00136 MJP
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  10/15/2015 DONE
Permanent Occupancy 6/7/20026/7/2002 DONE
Details
BLD-Final6/7/20026/7/20026/7/2002PPASS
DetailsCarl Dependahl
ok for c/o 6/7/2002 3:36:28 PM
Permanent occupancy  6/7/2002 DONE
Perm. Occ. Cert. #9163 issued 6-7-02 to the Park Apartments II.
BLD-Final6/6/20026/6/20026/6/2002PNR
DetailsCarl Dependahl
Cathy has the card
BLD-Final6/3/20026/5/20026/5/2002PNR
DetailsTom Arcoraci
###-####
Fee Review-notes3/14/20013/14/20014/18/2002 DONE
BLD-Conference4/10/20024/10/20024/10/2002PPASS
DetailsCarl Dependahl
w/ rail fabricator re c/n...install extensions as req'd
Case Summary (BLD)  4/5/2002  
Temporary occupancy  4/4/2002 DONE
Temp. Occ. Cert. #4780 issued 4-4-02 to the Park Apts. II.
BLD-Final4/2/20024/3/20024/3/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/02/2002 at 17:20:49. Contact: ###-####. ok for t/o, see c/n w/ BLD01-00594 4/3/2002 5:11:16 PM
FIRE-Final Inspection4/2/20024/2/20024/2/2002PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 04/02/2002 at 09:27:24. Contact: ###-####.
BLD-Final4/2/20024/2/20024/2/2002PNR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/02/2002 at 09:27:58. Contact: ###-####.
BLD-Final3/29/20024/1/20024/1/2002ANR
DetailsCarl Dependahl
fn occ allen###-####
FIRE-Final Inspection3/29/20024/1/20024/1/2002AFAIL
DetailsRick Jackson
allen ###-#### fire fn doors not closing; handrails 4/1/2002 2:47:56 PM
FIRE-Final Inspection3/27/20023/28/20023/28/2002ANR
DetailsRick Jackson
dave ###-#### need handrails 3/28/2002 5:25:58 PM
BLD-Final3/27/20023/28/20023/28/2002PNR
DetailsCarl Dependahl
dave ###-####
BLD-Conference3/25/20023/25/20023/25/2002PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 3/25/2002 11:38:03 AM re handrails, install extensions, & add'l rails as needed 3/25/2002 3:25:02 PM
BLD-Final3/25/20023/25/20023/25/2002PPART
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 3/25/2002 11:38:31 AM keep c/n, ok for t/o. 3/25/2002 3:25:32 PM
BLD-Wall cover12/14/200112/14/200112/14/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/14/2001 at 09:12:07. Contact: ###-####....dicussed shear nailing at 1st fl w/ supt. need eng's clarification, ok to continue. 12/14/2001 3:37:07 PM
BLD-Framing/Rough-in12/12/200112/12/200112/12/2001PPART
DetailsCarl Dependahl
###-####, hvac ok'd ? ok to insul, keep c/n...need to see gyp shear at int. 12/13/2001 4:24:39 PM
BLD-Framing/Rough-in12/11/200112/11/200112/11/2001PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/11/2001 at 11:05:34. Contact: . c/n, see bld01-00594 12/11/2001 4:21:20 PM
Case Summary (BLD)  12/6/2001  
Case Summary (BLD)  12/6/2001  
BLD-Aging Inspection11/19/200111/19/200111/19/2001 NR
DetailsCarl Dependahl
apt....wip. 11/26/2001 8:59:54 AM 11/26/2001 9:19:32 AM
BLD-Aging Inspection11/19/200111/19/200111/19/2001 NR
DetailsCarl Dependahl
apt....wip. 11/26/2001 8:59:54 AM 11/26/2001 9:19:32 AM
Plan resubmittals received  10/10/2001 DONE
Recieved one copy of cover letter and information from Structural Eng. Routed to Carl D. kmm
Print Pending Permit.LaserJet4  10/5/2001  
BLD-Aging Inspection9/18/20019/18/20019/18/2001 PART
DetailsCarl Dependahl
wip 9/18/2001 10:24:34 AM
BLD-Foundation7/18/20017/19/20017/19/2001PPASS
DetailsJim Storey
Jim ###-####
BLD-Footing7/5/20017/5/20017/5/2001PPASS
DetailsJim Storey
BLD-Footing6/21/20016/25/20016/25/2001PPART
DetailsCarl Dependahl
late pm ###-#### pending mti report 6/26/2001 11:18:55 AM
BLD-Footing6/25/20016/25/20016/25/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 6/25/2001 5:31:29 PM perim ftg steel ok
Inspection Record Card- Bld  6/5/2001 DONE
Inspection Record Card- Bld  6/5/2001 DONE
Print Occupancy Form  6/5/2001 DONE
Issue PAID IN FULL permit  6/4/2001 DONE
Plan assigned to (M_P)3/12/2001 5/25/2001 PASS
DetailsMike Phillips
5/25/2001 10:47:54 M_P - activity updated through activity BLDA022 from case BLD01-00604.
Routing - PLAN CHECK5/11/2001 5/25/2001 DONE
TOOK TO MIKE P
Plan Reviewer's activity  5/25/2001 PASS
Print Pending Permit.LaserJet4  5/25/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/25/2001 DONE
Case Summary (BLD)  5/25/2001 DONE
Inspection Record Card- Bld  5/25/2001 DONE
Print Occupancy Form  5/25/2001 DONE
Telephone call  5/25/2001 DONE
called permit ready for pickup
Routing - FIRE5/8/2001 5/11/2001 PASS
Plan resubmittals received  5/10/2001 DONE
Received one copy of revised sheet C1.2. Contacted Chad Heimbigner requesting 4 additional copies. KMM
Plan resubmittals received  5/1/2001 DONE
RECEIVED THREE COPIES OF REVISED SHEETS A1.6, S1.1, S1.2, A6.1, A6.2. TWO COPIES OF REVISED SHEETS A2.1, A2.2, A2.3, A2.4, A2.5, A3.1, A3.2, A3.3, A5.1, A6.1, A6.2, P-1. FOUR COPIES OF RESPONSE LETTER. ROUTED TO MIKE P. KMM
Routing - PLUMBING3/30/2001 4/4/2001 FAIL
Routing - PARKS DEPARTME3/28/2001 3/30/2001 PASS
Routing - PLANNING3/20/2001 3/28/2001 PASS
Approved by SAR and TKW (DRH00-00239)
Routing - PUBLIC WORKS3/15/2001 3/20/2001 PASS
Plan routing begun/NEW & ADDTN  3/15/2001 DONE
Plans ACCEPTED BY PLAN TECH  3/15/2001 DONE
Recd Pcfee & Taken To Pln CK  3/14/2001 DONE
Application received  3/12/2001  
Print Pending Permit.LaserJet4  3/12/2001  
Received Certificate of Value  3/12/2001 DONE
Routing - PLAN CHECK4/4/2001    
Routing Off Site - STRUCTURAL3/15/2001    
contacted pdq to take to outside eng. KMM