Permit Information
Permit NumberBLD01-00621
StatusFinaled
Name L B INDUSTRIES
Site Address 1185 S VINNELL WAY
Project NameGSA
Customer Number 
ePlanReviewNo
Description
GSA: BOISE CUSTOMER SERVICE CENTER * TO CONSTRUCT A NEW 30,755 SQUARE FOOT, ONE STORY, OFFICE BUILDING WITH A VEHICLE SALLYPORT AND TEMPORARY HOLDING CELLS FOR IMMIGRATION PROCESSING. THIS BUILDING IS CONSTRUCTED OF CONCRETE SLAB FLOORS, MASONRY EXTERIOR WALLS, STEEL STRUCTURAL FRAME AND METAL ROOF DECK WITH SINGLE PLY ROOFING SYSTEM. THIS BUILDING IS FULLY FIRE SPRINKLED. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THE FOUNDATION IS BEING CONSTRUCTED AND COMPLETED UNDER BUILDING PERMIT BLD01-00620. DRH01-0008/CUP00-00157/PC#192-01/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/28/2010 DONE
Fee Review-notes7/7/20037/7/20037/7/2003 DONE
Fee Review-notes3/12/20013/12/20019/6/2002 DONE
waiting for final billing for elect. will fax cert when they get all. //have final cert from GC waiting for ele 6/28 lh
Permanent occupancy  4/1/2002 DONE
Perm. Occ. Cert. #9092 issued 4-1-02 to the Boise Customer Service Center.
Permanent Occupancy 3/29/20023/29/2002 DONE
Details
BLD-Final3/28/20023/29/20023/29/2002APASS
DetailsRuss Owen
fn mike ###-#### -re-insp . ok perm oc. 3/29/2002 2:19:00 PM
BLD-Final3/19/20023/20/20023/20/2002PPART
DetailsRuss Owen
mike- ###-#### fn occ . Need pillow pad installation requirements. 3/20/2002 4:37:37 PM 3/20/2002 4:38:06 PM
BLD-Final2/14/20022/15/20022/15/2002APART
DetailsRuss Owen
MIKE ###-#### Ok for a temp oc c/n posted. 2/15/2002 1:17:17 PM
Temporary occupancy  2/15/2002 DONE
Temp. Occ. Cert. #4729 issued 2-15-02 to Boise Customer Service Center by RAD
FIRE-Final Inspection2/13/20022/14/20022/14/2002APASS
DetailsTroy Cobbley
Fire life/safety finaled. Structural inspector to review door hardware 2/15/2002 8:30:14 AM
FIRE-Final Inspection2/7/20022/7/20022/7/2002PNR
DetailsTroy Cobbley
contractor was not ready for inspection 2/7/2002 5:21:21 PM
BLD-Framing/Rough-in2/5/20022/6/20022/6/2002APART
DetailsRuss Owen
above ceiling insp mike ###-#### Needs a few pods 2 holes at corridor wall contractor notifed no c/n. 2/6/2002 3:14:31 PM
BLD-Conference1/16/20021/16/20021/16/2002PNR
DetailsTroy Cobbley
spoke with contractor about rough-in spection for sprinklers, verified locations of duct detectors and in-duct detectors with dampers 1/16/2002 3:42:32 PM
BLD-Framing/Rough-in1/15/20021/15/20021/15/2002PPART
DetailsRuss Owen
ceiling\\###-#### mike. west area ok east still in process. Also recieved ok from Architect fr cell walls not to deck and ok for column fire proffing in place of sheetrocked protection,still waiting for 2 hour occupancy wll change at the rear area of restrooms, also still need to caulk mis penetrations through out at exit corid and 2 hr oc wall around holding cell.s 1/17/2002 1:16:38 PM
BLD-Framing/Rough-in12/4/200112/5/200112/5/2001APART
DetailsRuss Owen
MIKE ###-####. Still need ok for interior columns fire-proffing inst of sheetrock assembly, also need ok for walls of holding cells not constructed to roof deck, and 2 hr wall (east) around the holding cell does not jog in rear of restrooms wall is continous with corridor and will have (2) 90 min access doors to the service plumbing at rear walls of the restrooms. These items require documentation from architect for changes to the approved plans. contractor notified. This day. Note: walls can now be sheetrocked. Ceilings not in at this time also all penetration fire stops and dampers will need insp prior to ceiling cover. 12/5/2001 12:36:49 PM 12/5/2001 12:41:50 PM
BLD-Framing/Rough-in11/2/200111/5/200111/5/2001APART
DetailsRuss Owen
###-#### MIKE OR COLLIN. Only the right rear south area evidence and office ok to cover rest not ready, found a duct w-out fire damper at west side of 1 hr corridor,contractor notified also all interior columns have been fire profed with spray applied plan shows drywall listing need ok from architect. 11/6/2001 10:56:02 AM
BLD-Aging Inspection10/25/200110/25/200110/25/2001 PART
DetailsRuss Owen
no insp called for. 10/25/2001 5:01:28 PM
BLD-Aging Inspection8/16/20018/16/20018/16/2001 FAIL
DetailsRuss Owen
c/n posted. 8/23/2001 3:40:19 PM
(F) Reprint permit  5/18/2001 DONE
Override - Parcel Holds  5/17/2001  
Issue PAID IN FULL permit  5/17/2001 DONE
Routing - PLAN CHECK5/4/2001 5/10/2001 PASS
Plan Reviewer's activity  5/10/2001 PASS
Plan resubmittals reviewed and approved with attached comment list and redlined notations. JCM
PLANS/APPL TAKEN TO FRONT DESK  5/10/2001 PASS
Override - Parcel Holds  5/10/2001  
Inspection Record Card- Bld  5/10/2001 DONE
Print Occupancy Form  5/10/2001 DONE
Telephone call  5/10/2001 DONE
rus
Plan assigned to (JCM)3/13/2001 5/10/2001 PASS
DetailsJohn Menard
5/10/01 10:50:32 JCM - activity updated through activity BLDA022 from case BLD01-00621.
Received Certificate of Value  5/9/2001 DONE
Received revised cert. of value. Routed to John M. KMM
Plan Reviewer's activity  5/7/2001 DONE
Density Reduction Survey recorded on 4/6/01 which combined Lots 30 and 31. Instrument #101032024/ROS 5344 by Briggs Engineering.
Plan resubmittals received  5/7/2001 DONE
Received plan resubmittals from erstad thorton architects, with small documents. Forwarded same to John Menard. 5/7/01 DAR
Routing - FIRE5/1/2001 5/4/2001 PASS
Routing - PLAN CHECK4/24/2001 5/1/2001 FAIL
Plan resubmittals requested  5/1/2001 FAIL
Mailed the architect of record a copy of the comment list requesting revisions. JCM
Routing Off Site - STRUCTURAL4/20/2001 5/1/2001 PASS
Received comment letter from consulting engineer approving resubmitted plans and calculations. JCM
Routing - PUBLIC WORKS4/19/2001 4/24/2001 PASS
Plan resubmittals received  4/20/2001 DONE
Received plan resubmittals from Richard Honsinger, Erstad Thorton Architects, two sets of sheets S1.1, S2.1, S3.1 and , S3.2, plus small documents forwarded same to John Menard. 4/20/01 DAR
Routing - PLAN CHECK3/22/2001 4/19/2001  
Please route to PW when your review is complete. KMM
Plan resubmittals requested  3/26/2001  
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting revisions and additional calculations. JCM
Routing Off Site - STRUCTURAL3/13/2001 3/23/2001 FAIL
Contacted PDQ to take plans to outside eng. KMM Received copy of comment list from consulting structural engineer requesting revisions. JCM
Routing - PLUMBING3/20/2001 3/22/2001 PASS
per plans and 97 upc
Routing - PLANNING3/16/2001 3/20/2001 PASS
Approved per DRH01-8 and CUP00-157 by TKW and SAR.
Routing - PUBLIC WORKS3/13/2001 3/16/2001 FAIL
Requires street light plan per Bill Colson. KMM
Plan routing begun/NEW & ADDTN  3/13/2001 DONE
Plans ACCEPTED BY PLAN TECH  3/13/2001 DONE
Received Certificate of Value  3/12/2001 DONE
Application received  3/12/2001  
Override - Parcel Holds  3/12/2001  
Recd Pcfee & Taken To Pln CK  3/12/2001 DONE