Permit Information
Permit NumberBLD01-00622
StatusFinaled
Name GARRIK CONSTRUCTION N.W.
Site Address 5996 S PIERRE WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is to build a new 2287s.f. 2-story single family dwelling with 1015s.f. on the main level and 1172s.f. on the upper level, there is an attached 692s.f. 3-car garage and 330s.f. of covered porch/patio. R-1C setbacks ok per rhj all per the approved plans and attached conditions. PC#179 pep
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection10/22/200110/22/200110/22/2001 PASS
DetailsSteven Webb
c. of c. was issued on 6/20/01 10/22/2001 8:38:42 AM
DOC - Permit Finaled10/22/200110/22/200110/22/2001APASS
DetailsSteven Webb
Finaled by inspector at 10/22/2001 8:38:44 AM
BLD-Aging Inspection8/20/20018/20/20018/20/2001 PART
DetailsSteven Webb
wip 8/20/2001 7:55:29 AM
BLD-Final6/20/20016/20/20016/20/2001PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 06/20/2001 at 09:18:18. Contact: ###-####. C. of C. #20437 issued. 6/20/2001 3:07:24 PM
BLD-Final6/19/20016/19/20016/19/2001PFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 06/19/2001 at 08:29:48. Contact: ###-####. c/n posted on window in garage. 6/19/2001 2:56:06 PM
BLD-Framing/Rough-in5/3/20015/4/20015/4/2001APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 05/03/2001 at 17:59:10. Contact: ###-####.
BLD-Energy code compliance5/3/20015/4/20015/4/2001APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 05/03/2001 at 17:59:52. Contact: ###-####. Ok to cover 5/4/2001 9:20:43 AM
BLD-Framing/Rough-in5/2/20015/3/20015/3/2001AFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 05/02/2001 at 09:05:26. Contact: ###-####. c/n on site need eng on headers and mec inspection ok to insulate after mec rough in 5/3/2001 10:58:11 AM
BLD-Framing/Rough-in4/19/20014/20/20014/20/2001PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/19/2001 at 15:37:05. Contact: ###-####. Shear--ok to side. 4/20/2001 3:20:09 PM
BLD-Foundation3/28/20013/28/20013/28/2001PPART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 03/28/2001 at 05:31:27. Contact: ###-####. wip 3/28/2001 4:16:12 PM
BLD-Footing3/27/20013/27/20013/27/2001APART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 03/27/2001 at 06:48:27. Contact: ###-####. wip 3/27/2001 11:16:41 AM
Inspection Record Card- Bld  3/22/2001 DONE
CHANGE STATUS TO (R)  3/22/2001 DONE
Telephone call  3/22/2001 DONE
called left message w/dave gave dollar amount
PLANS/APPL TAKEN TO FRONT DESK  3/22/2001 DONE
Issue PAID IN FULL permit  3/22/2001 DONE
(F) Reprint permit  3/22/2001 DONE
Inspector's copy Bld permit  3/19/2001 DONE
Plan Review Report  3/19/2001 DONE
Telephone call  3/19/2001 DONE
call to the designer stating the the stair intermediate landing does not comply. pep
Plan Reviewer's activity  3/19/2001  
recieved correspondence from the designer stating that the landing is not such as it is not required. This was taken to djo, and sam and we con fir that the drawings do not constitute a winder stair.
Plan assigned to (PEP)3/15/20013/15/20013/15/2001 DONE
DetailsPerry Paine
Pending Assignment by DJO3/12/2001 3/15/2001 DONE
DetailsDan Overy
3/15/2001 14:22:46 PEP - activity updated through activity BLDA176 from case BLD01-00622.
Routing - PUBLIC WORKS3/12/20013/12/20013/13/2001 PASS
Routing - PLANNING3/12/20013/12/20013/12/2001 PASS
Application received  3/12/2001  
Routing - PLAN CHECK3/13/20013/13/2001  PEND