Case Summary (BLD) | | | 4/2/2003 | | |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 4/10/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9098 issued 4-10-02 to the River Quarry Apts., Bldg. #23.
|
Permanent Occupancy | | 4/5/2002 | 4/5/2002 | | DONE |
|
|
|
|
BLD-Final | 4/5/2002 | 4/5/2002 | 4/5/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 07:36:28. Contact: ###-####. c/n made ok c/o ok 4/5/2002 3:31:35 PM
|
BLD-Final | 4/3/2002 | 4/4/2002 | 4/4/2002 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/03/2002 at 15:17:52. Contact: ###-####. landings at 3rd floor exit max 3/4 elavation transition. 4/4/2002 11:58:14 AM
|
FIRE-Final Inspection | 3/26/2002 | 3/26/2002 | 3/26/2002 | P | PASS |
Rick Jackson
|
|
|
###-####
|
FIRE-Final Inspection | 3/14/2002 | 3/15/2002 | 3/15/2002 | P | FAIL |
Rick Jackson
|
|
|
###-#### need additional module on alarm panel to monitor spervisory signal; horn not installed in bedroom in one unit 3/15/2002 5:11:33 PM
|
BLD-Energy code compliance | 12/19/2001 | 12/19/2001 | 12/19/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/19/2001 at 09:31:09. Contact: ###-####. framing and insulation ok. 12/19/2001 3:38:32 PM
|
BLD-Energy code compliance | 12/17/2001 | 12/18/2001 | 12/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/17/2001 at 11:35:03. Contact: ###-####. 2nd and 3rd floors ok 12/19/2001 11:32:59 AM
|
BLD-Energy code compliance | 12/14/2001 | 12/14/2001 | 12/14/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/14/2001 at 11:08:05. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/12/2001 | 12/13/2001 | 12/13/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/12/2001 at 16:03:30. Contact: ###-####.
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | PASS |
Jim Storey
|
|
|
wip 10/8/2001 4:47:52 PM
|
BLD-Concrete | 8/6/2001 | 8/7/2001 | 8/7/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 08:43:27. Contact: ###-####.s-i on site. 8/7/2001 12:07:03 PM
|
BLD-Foundation | 7/18/2001 | 7/19/2001 | 7/19/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/18/2001 at 15:04:17. Contact: ###-####. strata on site to inspect and test concrete along with rebar 7/19/2001 11:12:28 AM
|
BLD-Footing | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/20/2001 at 09:20:24. Contact: ###-####.pouring when I got here, looks ok so far, special inspector on job, pending report. 6/21/2001 11:09:01 AM
|
Issue PAID IN FULL permit | | | 6/12/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/6/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/6/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/6/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/6/2001 | | DONE |
|
|
|
PERMIT READY
|
Plan assigned to (M_P) | 3/14/2001 | | 6/6/2001 | | PASS |
Mike Phillips
|
|
|
6/6/2001 09:50:57 M_P - activity updated through activity BLDA022 from case BLD01-00650.
|
Routing - FIRE | 5/14/2001 | 5/15/2001 | 5/15/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan Reviewer's activity | | | 5/14/2001 | | FAIL |
|
|
|
Additional information required for further review
|
Routing - PLAN CHECK | 4/11/2001 | | 5/14/2001 | | FAIL |
|
|
|
Routing to fire.
|
Routing - PLUMBING | 4/6/2001 | | 4/11/2001 | | PASS |
|
|
|
provide a cleanout at the base of each waste or soil stack, 12 unit water system isometric didn't show clothes washers on the 2nd or 3rd floors, note 16 page P4.0- use approved material for inside the building, install main water risers in warm wall, pipe water heater drip pan drains to exterior induvudually, water pipihng in exterior walls for kitchen sicnks must be protected from freezing.
|
Routing - PLANNING | 3/29/2001 | | 4/4/2001 | | FAIL |
|
|
|
|
Routing - PARKS DEPARTME | 3/22/2001 | | 3/28/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/20/2001 | | 3/22/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/20/2001 | | DONE |
|
|
|
|
Application received | | | 3/14/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/14/2001 | | |
|
|
|
|