BLD-Final | 8/16/2002 | 8/16/2002 | 8/16/2002 | | DONE |
|
|
|
Final ok - approved by Russ Owen
|
Fee Review-notes | 3/23/2001 | 3/23/2001 | 8/16/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/16/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9299 issued 8-16-02 to the Hilton Garden Inn section 2 of 3.
|
Permanent Occupancy | | 8/15/2002 | 8/15/2002 | | DONE |
|
|
|
|
BLD-Final | 8/15/2002 | 8/15/2002 | 8/15/2002 | P | PART |
Russ Owen
|
|
|
|
BLD-Final | 8/12/2002 | 8/13/2002 | 8/13/2002 | A | PART |
Russ Owen
|
|
|
###-#### CLAY need the handrails in the stair tower repaired and 20 min doors at the lower rear exit,pool,area. rest room hc unit, contractor on site other items ok. 8/13/2002 12:52:08 PM
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
BLD-Conference | 7/31/2002 | 7/31/2002 | 7/31/2002 | P | CANC |
Russ Owen
|
|
|
|
Case Summary (BLD) | | | 7/31/2002 | | DONE |
|
|
|
|
BLD-Final | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | PART |
Russ Owen
|
|
|
###-#### CLAY . Needs fire/life safety for a temporary oc, also has pending corrections for a permanent. 6/18/2002 5:06:35 PM
|
FIRE-Final Inspection | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | PART |
Troy Cobbley
|
|
|
Fire alarm and fire life/safety finaled. Fire sprinkler given a temp for the window sprinklers per Dave Miller 6/18/2002 4:34:46 PM
|
Temporary occupancy | | | 6/18/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4829 issued 6-18-02 to the Hilton Garden Inn, middle section.
|
FIRE-Final Inspection | 6/14/2002 | 6/17/2002 | 6/17/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide "area of refuge signs", provide and test firemans phone system, provide emergency lights in conference room, repair emergency lights in small conference room, repair emergency light in 1st floor elev. lobby, repair emergency lights in central corridor on 1st floor, provide a fire extinguisher in main lobby, install occupancy load signs in assembly areas 6/17/2002 3:00:02 PM
|
BLD-Final | 6/14/2002 | 6/17/2002 | 6/17/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
| | | 6/17/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
| | | 6/17/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
| | | 6/17/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
| | | 6/17/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/14/2002 10:29:36 AM c/n posted. 6/14/2002 4:42:06 PM
|
| | | 6/14/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
| | | 6/14/2002 | | DONE |
Rita DeYoung
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
BLD-Framing/Rough-in | 6/3/2002 | 6/3/2002 | 6/3/2002 | P | CANC |
Russ Owen
|
|
|
CLAY ###-####
|
| | | 6/3/2002 | | DONE |
Darla L Downs
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
BLD-Framing/Rough-in | 4/18/2002 | 4/18/2002 | 4/18/2002 | P | PART |
Russ Owen
|
|
|
CLAY ###-####laundry ceiling. 4/18/2002 4:35:54 PM
|
BLD-Framing/Rough-in | 3/28/2002 | 3/29/2002 | 3/29/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/28/2002 3:54:45 PM .pool area ok to sheetrock., Also talked with engineer about kitchen beam with holes , ok as is will be sending letter soon. 3/29/2002 12:02:52 PM
|
BLD-Framing/Rough-in | 3/27/2002 | 3/27/2002 | 3/27/2002 | P | PART |
Russ Owen
|
|
|
###-####
|
BLD-Wall cover | 3/21/2002 | 3/22/2002 | 3/22/2002 | A | PART |
Russ Owen
|
|
|
CLAY ###-#### need addl work in laundry and kitchen areas as per prior c/n.. 3/22/2002 5:11:08 PM
|
BLD-Framing/Rough-in | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PART |
Russ Owen
|
|
|
CLAY ###-#### Still need beam in kitchen with holes approved. also top of wall connection at lower floor 2 locations done. 3/19/2002 9:58:59 AM
|
BLD-Framing/Rough-in | 3/14/2002 | 3/14/2002 | 3/14/2002 | P | FAIL |
Russ Owen
|
|
|
###-#### c/n posted. 3/14/2002 5:10:33 PM
|
BLD-Framing/Rough-in | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | PART |
Russ Owen
|
|
|
fr insp ###-####-clay Ok to complete sheetrock at 2nd floor. 3/6/2002 4:17:28 PM
|
BLD-Framing/Rough-in | 3/4/2002 | 3/5/2002 | 3/5/2002 | A | PART |
Russ Owen
|
|
|
clay ###-#### ok to cover 2nd floor rest room ceiling from the east wall to elevator. 3/5/2002 3:35:34 PM
|
BLD-Framing/Rough-in | 2/27/2002 | 2/28/2002 | 2/28/2002 | A | PART |
Russ Owen
|
|
|
CLAY ###-####
|
BLD-Framing/Rough-in | 2/22/2002 | 2/22/2002 | 2/22/2002 | P | PART |
Russ Owen
|
|
|
###-#### ok to sheetrock ceiling in restrooms. in 3rd floor 2nd floor shear now complete. 2/22/2002 4:41:28 PM
|
BLD-Framing/Rough-in | 2/20/2002 | 2/20/2002 | 2/20/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/20/2002 3:21:33 PM ok to complete insulation at 2nd floor. 2/20/2002 3:25:39 PM
|
BLD-Framing/Rough-in | 2/19/2002 | 2/19/2002 | 2/19/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/19/2002 2:41:10 PM
|
BLD-Framing/Rough-in | 2/15/2002 | 2/15/2002 | 2/15/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/15/2002 11:26:33 AM Need to complete all fire stoping east of first 2hr wall. 2/15/2002 11:31:27 AM
|
BLD-Framing/Rough-in | 2/14/2002 | 2/14/2002 | 2/14/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/14/2002 4:54:14 PM
|
BLD-Framing/Rough-in | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/13/2002 3:49:21 PM
|
BLD-Framing/Rough-in | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/12/2002 12:13:38 PM Need to complete shaer nailing in the last 6 rooms at far west end, Second floor shear is ok up to the first 2 hr wall from the east end. Note the 2 hr wall is not complete Ie fire stoping. A c/n is posted for areas that are approved for cover. 2/12/2002 4:21:12 PM
|
BLD-Framing/Rough-in | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PART |
Russ Owen
|
|
|
CLAY ###-#### 2nd floor shear ok up from east side up to the second area separation wall,need to complete the rest from this wall west exterior wall. 2/8/2002 4:13:41 PM
|
BLD-Framing/Rough-in | 2/6/2002 | 2/7/2002 | 2/7/2002 | A | PART |
Russ Owen
|
|
|
###-#### Fourth floor is good to sheetrock and about a 3/4 of east end of 3rd floor, is approved for cover, rest is ok to insulate and complete shear nailing and recall, note the electrical rooms are not approved for cover on the 3rd or 4th floors, also the pvc direct vent pipes at these floor lines will all be relocated. and will be exposed and inspection will be required prior to cover,also note a stairway will be added later at the east wall. 2/7/2002 4:55:40 PM . 2/7/2002 4:56:34 PM 2/7/2002 4:59:25 PM
|
BLD-Framing/Rough-in | 2/5/2002 | 2/5/2002 | 2/5/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/5/2002 4:28:26 PM see bld01-00729 2/5/2002 4:31:43 PM
|
BLD-Conference | 2/4/2002 | 2/4/2002 | 2/4/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/4/2002 12:10:53 PM Meet with Architect and Mec engineer for fire damper locations in lower floor. Also meet with Project manager Clay to go over posted c/ns , Note inspections to date for rooms has only been select areas, as work and other inspections for plumbing had not completed and or approved select inspections have been done as to insulate and add shear oand or drywall at places nessecart mostley exterior and bettween rooms out of plumbing walls. The MBR hold down sytem may be inspected by project engineer Clay will address prior c/n items and call back as required prior to covering , not some ares will need dry wall removed at 2 hr walls. 2/4/2002 1:00:56 PM
|
BLD-Conference | 1/18/2002 | 1/18/2002 | 1/18/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/18/2002 5:25:27 PM
|
BLD-Framing/Rough-in | 1/14/2002 | 1/15/2002 | 1/15/2002 | A | PART |
Russ Owen
|
|
|
###-####. Went out to review area separation walls, as architect would like to revise configuration of wall at the area of mechanical chases for restroom exhaust duct. Needs suppervisor approval possible plan check modification . 1/15/2002 4:46:31 PM
|
BLD-Framing/Rough-in | 12/20/2001 | 12/21/2001 | 12/21/2001 | A | PART |
Russ Owen
|
|
|
###-####. Added 2nd layer drywall to ceiling in front porte cochere. as was cover with out approval with finish coat exterior efis system with out 2 layers as required, also c/n for shear wall top bolcking requires 2 blocks over all int shear walls. 12/21/2001 4:42:47 PM 12/21/2001 4:44:56 PM
|
BLD-Conference | 12/19/2001 | 12/19/2001 | 12/19/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 12/19/2001 9:30:19 AM c/n posted. 12/20/2001 4:56:37 PM
|
Plan Reviewer's activity | | | 11/7/2001 | | |
|
|
|
Architect replaced. New architect is Russell Colburn
|
BLD-Aging Inspection | 10/17/2001 | 10/17/2001 | 10/17/2001 | | PART |
Russ Owen
|
|
|
wip. 10/22/2001 2:57:04 PM
|
Case Summary (BLD) | | | 9/25/2001 | | |
|
|
|
|
BLD-Concrete | 8/16/2001 | 8/17/2001 | 8/17/2001 | A | CANC |
Dave Hannah
|
|
|
###-#### rich
|
BLD-Concrete | 8/14/2001 | 8/15/2001 | 8/15/2001 | A | PART |
Dave Hannah
|
|
|
###-#### clay ..... russ owen requested that david hannah look at this talked with mason and spec insp about high left grouting 8/15/2001 1:06:00 PM
|
BLD-Conference | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PART |
Dave Hannah
|
|
|
Added by Inspector: 425 On 8/14/2001 4:38:23 PM masonry high lift grouting and speceal inspection
|
BLD-Footing | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PART |
Russ Owen
|
|
|
ft insp- rich ###-#### pending s-i report. 8/10/2001 10:30:11 AM
|
BLD-Foundation | 7/26/2001 | 7/26/2001 | 7/26/2001 | P | PART |
Russ Owen
|
|
|
rich ###-####subject to s-i. 7/26/2001 1:56:07 PM
|
BLD-Footing | 7/24/2001 | 7/24/2001 | 7/24/2001 | P | PART |
Russ Owen
|
|
|
###-#### ok pending s-i. 7/24/2001 3:21:00 PM
|
BLD-Footing | 7/16/2001 | 7/16/2001 | 7/16/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/16/2001 at 10:06:27. Contact: .
|
BLD-Footing | 7/13/2001 | 7/13/2001 | 7/13/2001 | P | PART |
Russ Owen
|
|
|
###-####subject to s-i. 7/13/2001 3:47:23 PM
|
BLD-Footing | 7/11/2001 | 7/11/2001 | 7/11/2001 | P | PART |
Russ Owen
|
|
|
Rich ###-####. subject to s-i . 7/11/2001 4:23:50 PM
|
BLD-Footing | 7/9/2001 | 7/9/2001 | 7/9/2001 | P | PART |
Russ Owen
|
|
|
Rich ###-#### s-i pending. 7/10/2001 12:00:01 PM
|
BLD-Foundation | 7/3/2001 | 7/3/2001 | 7/3/2001 | P | PART |
Russ Owen
|
|
|
###-####ok pending s-i report 7/3/2001 3:30:46 PM
|
BLD-Footing | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PART |
Russ Owen
|
|
|
###-#### ok pending s-i report. 7/3/2001 2:55:15 PM
|
BLD-Footing | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PART |
Russ Owen
|
|
|
pouring at 10:00 clay ###-#### s-i required insp poured at this time. 6/29/2001 11:16:58 AM
|
BLD-Foundation | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PART |
Russ Owen
|
|
|
pouring at 10:00 clay s-i required insp. poured at this time.. 6/29/2001 11:16:40 AM
|
(F) Reprint permit | | | 6/26/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/22/2001 | | 6/25/2001 | | DONE |
|
|
|
Preparing for issuance. KMM
|
Print Occupancy Form | | | 6/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/25/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/25/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/25/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/25/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/25/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/23/2001 | | 6/25/2001 | | PASS |
Mike Phillips
|
|
|
6/25/2001 08:54:50 M_P - activity updated through activity BLDA022 from case BLD01-00736.
|
Routing - PUBLIC WORKS | 6/21/2001 | | 6/22/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/18/2001 | | 6/21/2001 | | DONE |
|
|
|
contacted pdq to take revised plans to outside eng.
|
Routing - PLAN CHECK | 5/18/2001 | | 6/21/2001 | | PEND |
|
|
|
Routing to P.W> and Plumbing.
|
Plan Reviewer's activity | | | 6/21/2001 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Routing - PLANNING | 6/1/2001 | | 6/5/2001 | | PASS |
|
|
|
Approved per DRH01-17.
|
Routing - PLUMBING | 5/25/2001 | | 5/25/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2001 | | 5/18/2001 | | FAIL |
|
|
|
Same as before
|
Routing - PLAN CHECK | 5/11/2001 | | 5/18/2001 | | |
|
|
|
|
Routing - FIRE | 5/11/2001 | | 5/11/2001 | | PASS |
|
|
|
|
Routing - FIRE | 4/23/2001 | | 4/25/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/23/2001 | | 4/23/2001 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside eng.
|
Plan Reviewer's activity | | | 4/23/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Print Pending Permit.LaserJet4 | | | 4/23/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/23/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 4/16/2001 | | 4/23/2001 | | FAIL |
|
|
|
Routing to fire.
|
Routing - PLUMBING | 4/12/2001 | | 4/16/2001 | | FAIL |
|
|
|
|
Routing - PLANNING | 4/9/2001 | | 4/9/2001 | | PEND |
|
|
|
Ok for conditional use per Susan Riggs. Design Review conditions have not been met.
|
Routing - PUBLIC WORKS | 3/23/2001 | | 4/4/2001 | | FAIL |
|
|
|
Requires proof of legal land division per Jim Rich. 4/4/01 DAR
|
Plan routing begun/NEW & ADDTN | | | 3/23/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/23/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 3/23/2001 | | DONE |
|
|
|
|
Application received | | | 3/23/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/23/2001 | | DONE |
|
|
|
|