Routing - PUBLIC WORKS | 7/11/2001 | | 7/13/2011 | | FAIL |
Beverly Mountain
|
|
|
Requires drainage plan revision. 7/13/01 DAR
|
BLD-Aging Inspection | 12/8/2003 | 12/8/2003 | 12/8/2003 | | PASS |
Tom Arcoraci
|
|
|
needs to obtain co 12/8/2003 3:00:18 PM
|
DOC - Permit Expired | 12/8/2003 | 12/8/2003 | 12/8/2003 | P | PASS |
Tom Arcoraci
|
|
|
Expired by inspector at 12/8/2003 3:01:34 PM
|
Fee Review-notes | 7/7/2003 | 7/7/2003 | 7/7/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/19/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9358 issued 9-19-02 to the Bethel Street Apts.
|
PubWorks Occupancy Approval | 9/5/2002 | 9/5/2002 | 9/5/2002 | | DONE |
|
|
|
Drainage project complete, signed off 9/4/02. R.Cummings
|
BLD-Final | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | PASS |
Tom Arcoraci
|
|
|
MICK ###-#### ok for perm when others sign perm 6/13/2002 11:29:34 AM
|
Permanent Occupancy | | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
|
Temporary occupancy | | | 6/13/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4826 issued 6-13-02 to the Bethel Street Apts.
|
FIRE-Final Inspection | 6/11/2002 | 6/12/2002 | 6/12/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 6/12/2002 2:27:18 PM
|
BLD-Energy code compliance | 4/11/2002 | 4/12/2002 | 4/12/2002 | P | PASS |
Dave Hannah
|
|
|
###-#### ok to cover 4/12/2002 10:14:40 AM
|
BLD-Framing/Rough-in | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PART |
Russ Owen
|
|
|
nick- ###-#### r/i c/n exterior post connections tro beams. 4/9/2002 3:31:22 PM
|
BLD-Framing/Rough-in | 4/5/2002 | 4/8/2002 | 4/8/2002 | A | PART |
Tom Arcoraci
|
|
|
shear wall nick ###-#### ok to side 4/8/2002 10:31:16 AM
|
BLD-Foundation | 3/7/2002 | 3/7/2002 | 3/7/2002 | P | PASS |
Tom Arcoraci
|
|
|
found- nick ###-####
|
BLD-Footing | 3/5/2002 | 3/5/2002 | 3/5/2002 | P | PART |
Tom Arcoraci
|
|
|
per tom for ft - wip 3/5/2002 4:14:27 PM
|
Issue PAID IN FULL permit | | | 3/5/2002 | | |
|
|
|
|
Print Occupancy Form | | | 11/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/6/2001 | | DONE |
|
|
|
|
Telephone call | | | 11/6/2001 | | DONE |
|
|
|
permit ready
|
Routing - PUBLIC WORKS | 11/2/2001 | | 11/2/2001 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 10/30/2001 | | 11/2/2001 | | PASS |
|
|
|
New parcel #'s will need to be entered from subdivision. Routed to Public Works.
|
Plan Reviewer's activity | | | 11/2/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/2/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/2/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/6/2001 | | 11/2/2001 | | PASS |
Mike Phillips
|
|
|
11/2/2001 15:15:13 M_P - activity updated through activity BLDA022 from case BLD01-00863.
|
Override - Parcel Holds | | | 10/30/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 10/30/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 10/5/2001 | | 10/30/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 10/2/2001 | | 10/5/2001 | | |
|
|
|
|
Routing - PLUMBING | 10/5/2001 | | 10/5/2001 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/1/2001 | | 10/2/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 9/28/2001 | | 10/1/2001 | | PEND |
|
|
|
Waiting for other to approve prior to issuing permit.
|
Routing - FIRE | 9/25/2001 | | 9/26/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/25/2001 | | DONE |
|
|
|
Received one copy or revised sheets T-1, SITE, GRD, ST-P, S-1, S-2, DT-1, and one copy of water plan, by United Water Idaho. routed to mike p. kmm
|
Routing - PLUMBING | 9/25/2001 | | 9/25/2001 | | FAIL |
|
|
|
submit a civil plan showing water service size and location and 1% min. grade on sewer mains.
|
Routing - PUBLIC WORKS | 9/24/2001 | | 9/24/2001 | | FAIL |
|
|
|
Subdivision not recorded yet.
|
Routing - PLAN CHECK | 9/13/2001 | | 9/24/2001 | | |
|
|
|
|
Plan resubmittals received | | | 9/19/2001 | | DONE |
|
|
|
Received two copies of sheets A.1.0, A1.1, A2.0, A2.1, A3.0, A7.1, M1.0, two copies of struct. calcs and one copy of cover letter. Routed to Mike P. KMM
|
Routing - PLANNING | 9/12/2001 | | 9/13/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/7/2001 | | 9/12/2001 | | HOLD |
|
|
|
FAILED IN ALL DIVISIONS. Subdivision in process. Hold waiting for resubmittals.
|
Routing - PLUMBING | 9/6/2001 | | 9/7/2001 | | FAIL |
|
|
|
PROVIDE A PLAN SHOWING WATER SERVICE SIZING AND LOCATIONS, PROVIDE A PLAN SHOWING MIN. 1% GRADE ON ALL SEWER MAINS.
|
Plan resubmittals received | | | 9/6/2001 | | DONE |
|
|
|
Received two copies of revised sheets P1.0, P1.1, P2.0. Put with plans and routed to Plumbing. kmm
|
Routing - PLANNING | 9/4/2001 | | 9/6/2001 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 9/6/2001 | | DONE |
|
|
|
received 4 sheets of revised site plan and routed to Sev Jones
|
Routing - PLAN CHECK | 7/25/2001 | | 8/31/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/31/2001 | | 8/31/2001 | | FAIL |
|
|
|
Subdivision has not been recorded per Addressing.
|
Routing - FIRE | 7/23/2001 | | 7/25/2001 | | FAIL |
|
|
|
hydrant locations for entire complex
|
Routing - PLAN CHECK | 6/1/2001 | | 7/23/2001 | | FAIL |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 7/23/2001 | | FAIL |
|
|
|
Additional information required for a further review prior to issuing permit.
|
Plan resubmittals received | | | 6/29/2001 | | DONE |
|
|
|
Received plan resubmittals from Tamura and associates, 3 sets of plans and two sets of structural caculations. Forwarded same to Mike Phillips. 6/29/01 DAR
|
Plan Reviewer's activity | | | 6/14/2001 | | FAIL |
|
|
|
Waiting for structural calculations.
|
Routing - PLUMBING | 5/23/2001 | | 5/31/2001 | | FAIL |
|
|
|
provide a plan showing water services, size and location. detail 4 page P2.0 shows 1"service piping, too small, provide a plan showing min. 1% grade on all sewer mains, min. 1" supply for each unit, 2 units 1 1/4", 3 units 1 1/4", 4 units 1 1/2" if services are 150' or less.
|
Routing - PLANNING | 4/25/2001 | | 5/22/2001 | | FAIL |
|
|
|
Conditions of approval for CUP01-00010 are not satisfied.
|
Routing - PUBLIC WORKS | 4/12/2001 | | 4/26/2001 | | FAIL |
|
|
|
Requires drainage plan revision per Brian Murphy. 4/26/01 DAR
|
Plan routing begun/NEW & ADDTN | | | 4/12/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 4/11/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 4/6/2001 | | |
|
|
|
|
Application received | | | 4/6/2001 | | |
|
|
|
|