Case Summary (BLD) | | | 6/17/2016 | | DONE |
|
|
|
|
Letter of compliance | | | 5/28/2002 | | DONE |
|
|
|
Letter of Compliance #22503 issued 5-28-02.
|
BLD-Final | 5/22/2002 | 5/23/2002 | 5/23/2002 | A | PASS |
Tom Arcoraci
|
|
|
JOHN ###-#### ok for perm occ 5/23/2002 11:01:04 AM
|
Fee Review-notes | 4/12/2001 | 4/12/2001 | 5/23/2002 | | DONE |
|
|
|
|
BLD-Final | 5/2/2002 | 5/3/2002 | 5/3/2002 | A | FAIL |
Carl Dependahl
|
|
|
john 8673334c/n, eng's & MTI affidavits needed....add rails deleted at stair as redlined ( 36" stair...both sides???) need all signatures. ok for t/o pend P&Z. 5/3/2002 3:41:42 PM
|
Print Occupancy Form | | | 5/3/2002 | | |
|
|
|
|
Print Occupancy Form | | | 5/3/2002 | | |
|
|
|
|
Temporary occupancy | | | 5/3/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4802 issued 5-3-02 to the Fulton Street Annex (shell only).
|
BLD-Final | 5/2/2002 | 5/2/2002 | 5/2/2002 | P | NR |
Carl Dependahl
|
|
|
###-#### john
|
FIRE-Final Inspection | 2/11/2002 | 2/12/2002 | 2/12/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 2/11/2002 2:06:56 PM
|
FIRE-Final Inspection | 2/8/2002 | 2/11/2002 | 2/11/2002 | A | NR |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 2/8/2002 11:17:36 AM
|
FIRE-Final Inspection | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | FAIL |
Rick Jackson
|
|
|
###-#### need knox box; sprinkler riser obstructed; need alarm and sprinkler permits passed 2/8/2002 10:25:57 AM
|
FIRE-Final Inspection | 2/8/2002 | 2/8/2002 | 2/8/2002 | A | CANC |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 2/8/2002 10:29:36 AM
|
BLD-Conference | 2/1/2002 | 2/4/2002 | 2/4/2002 | A | CANC |
Rick Jackson
|
|
|
###-#### JOHN see FIRE conference notes for same date 2/4/2002 9:01:53 AM
|
FIRE-Conference | 2/4/2002 | 2/4/2002 | 2/4/2002 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 2/4/2002 9:01:28 AM with John about sprinkler heads in stairs; won't be obstructed by clouds at top of stairs
|
BLD-Aging Inspection | 1/14/2002 | 1/14/2002 | 1/16/2002 | | NR |
Carl Dependahl
|
|
|
wip 1/16/2002 9:08:52 AM
|
BLD-Conference | 1/15/2002 | 1/15/2002 | 1/15/2002 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/15/2002 5:17:43 PM w/ John re address...must be 4", posted for final
|
BLD-Framing/Rough-in | 11/14/2001 | 11/14/2001 | 11/14/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### JOHN extend drywall membrane to seal above beam at stair "enclosure". ok to continue . 11/14/2001 3:15:37 PM
|
BLD-Framing/Rough-in | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### JOHN need spec insp reports...ok to 1side at stair enclosure, need backing between joists t lids 11/5/2001 5:20:31 PM s 11/5/2001 5:28:58 PM 11/5/2001 5:34:57 PM
|
BLD-Aging Inspection | 10/29/2001 | 10/29/2001 | 11/5/2001 | | NR |
Carl Dependahl
|
|
|
wip 11/5/2001 10:27:13 AM
|
BLD-Framing/Rough-in | 8/28/2001 | 8/29/2001 | 8/29/2001 | A | PART |
Carl Dependahl
|
|
|
###-####; joisting at ramp ok; 1: 20 slope 8/29/2001 11:49:57 AM 8/29/2001 11:50:16 AM
|
BLD-Framing/Rough-in | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### john; int framing at stairs, joisting at landing ok 8/21/2001 2:58:42 PM
|
BLD-Framing/Rough-in | 7/12/2001 | 7/13/2001 | 7/13/2001 | P | PART |
Carl Dependahl
|
|
|
###-####; roof diaphragm & overlay nailed off ok, wall ties and straps at roof to follow...MTI may inspect strap nailing at roof 7/13/2001 4:26:56 PM
|
Issue PAID IN FULL permit | | | 6/19/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/16/2001 | | 6/15/2001 | | PASS |
Carl Westfall
|
|
|
6/15/01 08:57:28 CJW - activity updated through activity BLDA022 from case BLD01-00921.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/15/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/15/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/16/2001 | | 6/14/2001 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Routing Off Site - STRUCTURAL | 5/30/2001 | | 6/7/2001 | | PASS |
|
|
|
Sent resubsmittals to consulting engineer via PDQ. 5/30/01 DAR
|
Plan resubmittals received | | | 5/24/2001 | | DONE |
|
|
|
Received 3 sets of plan resubmittals from Margie Kennedy, Armstrong Architects, sheets A2.0, S2.0, S2.1 and S3.0 plus small documents forwarded same to Carl Westfall. 5/24/01 DAR
|
Routing - PUBLIC WORKS | 5/15/2001 | | 5/16/2001 | | PASS |
|
|
|
Assigned address re-evaluated.
|
Routing - FIRE | 5/14/2001 | | 5/15/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 4/24/2001 | | 5/14/2001 | | |
|
|
|
Failed first UBC review.
|
Plan Reviewer's activity | | | 5/7/2001 | | |
|
|
|
Failed first UBC review. UBC plan review started May 7, 2001 and finished May 11, 2001. A response from the architect was required. See the conditions list.
|
Routing - PLANNING | 4/20/2001 | | 4/23/2001 | | PASS |
|
|
|
Historic Preservation
|
Routing - PUBLIC WORKS | 4/17/2001 | | 4/20/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 4/20/2001 | | 4/20/2001 | | PASS |
|
|
|
Pending Historic Preservation approval.
|
Pending Assignment by MYS | 4/12/2001 | | 4/16/2001 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/13/2001 | | DONE |
|
|
|
|
Application received | | | 4/12/2001 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/18/2001 | | | | |
|
|
|
Failed first structural review. Contacted pdq to take plans to outside eng. KMM
|