BLD-Final | 6/27/2001 | 6/27/2001 | 6/27/2001 | P | PASS |
Jim Sly
|
|
|
chuck ###-#### C/C issued. 6/27/2001 3:18:21 PM
|
DOC - Permit Finaled | 6/27/2001 | 6/27/2001 | 6/27/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 6/27/2001 3:17:59 PM
|
BLD-Energy code compliance | 5/10/2001 | 5/10/2001 | 5/10/2001 | P | PASS |
Jim Sly
|
|
|
chuck ###-####
|
BLD-Framing/Rough-in | 5/10/2001 | 5/10/2001 | 5/10/2001 | P | PASS |
Jim Sly
|
|
|
chuck ###-#### reinspection
|
BLD-Energy code compliance | 5/10/2001 | 5/10/2001 | 5/10/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 5/10/2001 2:05:28 PM
|
BLD-Framing/Rough-in | 5/10/2001 | 5/10/2001 | 5/10/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 5/10/2001 2:08:26 PM
|
BLD-Framing/Rough-in | 5/9/2001 | 5/9/2001 | 5/9/2001 | P | FAIL |
Jim Sly
|
|
|
chuck ###-#### C/N issued. 5/9/2001 12:45:31 PM
|
BLD-Framing/Rough-in | 5/8/2001 | 5/8/2001 | 5/8/2001 | P | PASS |
Jim Sly
|
|
|
shear nail 941- 1103
|
BLD-Foundation | 4/24/2001 | 4/24/2001 | 4/24/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/24/2001 at 06:39:02. Contact: ###-####.
|
BLD-Footing | 4/23/2001 | 4/23/2001 | 4/23/2001 | P | PART |
Dave Hannah
|
|
|
dane ###-#### W.I.P 4/23/2001 1:28:41 PM
|
Issue PAID IN FULL permit | | | 4/17/2001 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 4/13/2001 | 4/13/2001 | 4/16/2001 | | PASS |
Perry Paine
|
|
|
4/16/2001 07:53:46 PEP - activity updated through activity BLDA022 from case BLD01-00936.
|
Inspector's copy Bld permit | | | 4/16/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/16/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 4/13/2001 | 4/13/2001 | 4/13/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/13/2001 | 4/13/2001 | 4/13/2001 | | PASS |
|
|
|
|
Application received | | | 4/13/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 4/13/2001 | 4/13/2001 | | | PEND |
|
|
|
|