Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD01-01043
StatusFinaled
Name CYNTHIA MANN ELEMENTARY SCHOOL
Site Address 5401 W CASTLE DR
Project NameSCHOOL * CYNTHIA MANN
Customer Number 
ePlanReviewNo
Description
Cynthia Mann * Work constists of grading, new concrete construction, and landscaping for the Cynthia Mann Outdoor Classroom. PC#345-01
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes4/24/20014/24/20011/29/2002 DONE
BLD-Final9/10/20019/11/20019/10/2001APASS
DetailsTony Young
call first ###-#### or ###-#### Boyd
DOC - Permit Finaled9/10/20019/10/20019/10/2001PPASS
DetailsTony Young
Finaled by inspector at 9/10/2001 3:38:38 PM
BLD-Aging Inspection9/3/20019/3/20019/3/2001 PART
DetailsTony Young
wip 9/4/2001 9:42:58 AM
BLD-Framing/Rough-in7/2/20017/2/20017/2/2001PPART
DetailsTony Young
###-####
concrete bleachers and steps, no plans on site, appears ok 7/2/2001 3:42:07 PM
BLD-Foundation6/21/20016/22/20016/22/2001APART
DetailsTony Young
wip,, verbal warnings 6/22/2001 10:06:53 AM
BLD-Footing6/21/20016/21/20016/21/2001PPASS
DetailsTony Young
Added by Inspector: 415 On 6/21/2001 3:46:49 PM
Routing - PLAN CHECK6/20/2001 6/21/2001 PASS
Second Set
Plan assigned to (MLO)4/25/2001 6/21/2001 PASS
DetailsMike Otto
6/21/2001 13:07:40 MLO - activity updated through activity BLDA022 from case BLD01-01043.
PLANS/APPL TAKEN TO FRONT DESK  6/21/2001 DONE
Inspection Record Card- Bld  6/21/2001 DONE
Telephone call  6/21/2001 DONE
left mess for don hutchison that permit is ready
Issue PAID IN FULL permit  6/21/2001 DONE
Routing - PLANNING6/18/2001 6/20/2001 DONE
Second set
Case Summary (BLD)  6/18/2001  
Routing - PUBLIC WORKS6/18/2001 6/18/2001 PASS
Second Set
Additional plans submitted  6/18/2001 DONE
Kathy advised me that plans could not be found. I looked around places she hadn"t and could not find them . Therefore to get the review process back on track I called Don Hutchison and requested two more sets. Received the two sets and sent them to PW and then to P& Z.. I found the original plans the next day in with Roger Jones. 6/20/01 DAR
Routing - PLAN CHECK5/2/2001 5/3/2001 PEND
Routing - PUBLIC WORKS4/27/2001 5/2/2001 FAIL
Requires drainage plan revision per Brian Murphy. 5/2/01 DAR
Plans ACCEPTED BY PLAN TECH  4/27/2001 DONE
Received extra civil sheets.
Plan routing begun/NEW & ADDTN  4/27/2001  
Plans ACCEPTED BY PLAN TECH  4/25/2001 HOLD
Requires 1. Three extra civil sheets.
2. CUP
Plans in my hold box.
Received Certificate of Value  4/24/2001 DONE
Application received  4/24/2001  
Recd Pcfee & Taken To Pln CK  4/24/2001 DONE
Routing - PLANNING5/3/2001    
Picked up first set of plans from Roger Jones on 6/18/01 who had been holding them since Scott sent them to him on 5/3/01. 6/20/01 DAR