Fee Review-notes | 4/24/2001 | 4/24/2001 | 12/16/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 11/5/2002 | | DONE |
|
|
|
Letter of Compliance #22760 issued 11-1-02.
|
BLD-Final | 10/31/2002 | 10/31/2002 | 10/31/2002 | P | PASS |
Carl Dependahl
|
|
|
###-####...ok for final. 10/31/2002 1:51:25 PM
|
FIRE-Final Inspection | 10/28/2002 | 10/29/2002 | 10/29/2002 | P | PASS |
Rick Jackson
|
|
|
###-####
|
FIRE-Final Inspection | 8/27/2002 | 8/28/2002 | 8/28/2002 | A | FAIL |
Rick Jackson
|
|
|
Phone #: ###-#### need alarm plans submitted; verify through agreement with city (Dan Stuart has original agreement with FD and ATT) 8/28/2002 10:28:13 AM
|
FIRE-Final Inspection | 8/1/2002 | 8/1/2002 | 8/1/2002 | P | FAIL |
Rick Jackson
|
|
|
Joe, ###-####
need alarm plans submitted; all other items completed; will need to test alarms for damper release 8/1/2002 4:24:35 PM
|
FIRE-Final Inspection | 4/17/2002 | 4/18/2002 | 4/18/2002 | A | FAIL |
Rick Jackson
|
|
|
dick- ###-#### per rick at 8:30 labels on rated doors; access doors for smoke dampers; fire alarm plans needed; overhead door traps occupants inside when door is released by fusible links; need to test alarms; exit sign needed; penetrations in rated walls 4/18/2002 10:39:33 AM
|
BLD-Final | 4/17/2002 | 4/18/2002 | 4/18/2002 | A | NR |
Tom Arcoraci
|
|
|
fn occ dick ###-####
|
BLD-Framing/Rough-in | 3/21/2002 | 3/22/2002 | 3/22/2002 | A | PART |
Carl Dependahl
|
|
|
fr dick- ###-#### ; walls ok to cover 3/22/2002 12:13:07 PM
|
BLD-Aging Inspection | 1/7/2002 | 1/7/2002 | 1/7/2002 | | NR |
Carl Dependahl
|
|
|
qwest, wip. 1/7/2002 4:59:43 PM
|
BLD-Aging Inspection | 11/5/2001 | 11/5/2001 | 11/5/2001 | | NR |
Carl Dependahl
|
|
|
AT&T/ Qwest Bldg; wip. 11/5/2001 3:17:33 PM
|
BLD-Aging Inspection | 9/3/2001 | 9/3/2001 | 9/3/2001 | | NR |
Carl Dependahl
|
|
|
WIP per contractor 9/4/2001 11:04:41 AM
|
BLD-Framing/Rough-in | 6/29/2001 | 7/2/2001 | 7/2/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/29/2001 at 13:37:46. Contact: ###-####. ok to infill.wall....ele is on surface 7/2/2001 11:50:10 AM
|
Print Occupancy Form | | | 6/29/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2001 | | DONE |
|
|
|
called permit ready
|
Issue PAID IN FULL permit | | | 6/29/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/27/2001 | | 6/28/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2001 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 6/4/2001 | | 6/28/2001 | | PASS |
Jason Blais
|
|
|
6/28/2001 13:55:38 JCB - activity updated through activity BLDA022 from case BLD01-01044.
|
Routing - PLAN CHECK | 6/25/2001 | | 6/27/2001 | | FAIL |
|
|
|
One item still has not been adequately addressed from initial plan review report. Called architect and let him know. He said he would see what he could do.
|
Routing - FIRE | 6/26/2001 | 6/26/2001 | 6/26/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/26/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals from Hutchison Smith Architects, sheets M2.0, M3.0, A-3 AND A-5, FORWARDED SAME TO Jason Blais. 6/26/01 DAR
|
Routing - FIRE | 6/20/2001 | | 6/25/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/15/2001 | | 6/20/2001 | | FAIL |
|
|
|
Not all items were addressed or addressed adequately. Second plan review report sent and faxed to architect. Plan resubmittals and response required again. Plans routed to Fire Dept. again.
|
Plan resubmittals requested | | | 6/20/2001 | | |
|
|
|
Plan resubmittals required for review again.
|
Routing - FIRE | 6/13/2001 | | 6/15/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/2/2001 | | 6/13/2001 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 6/13/2001 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Plan assigned to (DRS) | 4/30/2001 | | 6/4/2001 | | DONE |
Dan Stuart
|
|
|
Reassigned to Jason Blais by M. Southard.
|
Routing - PUBLIC WORKS | 4/30/2001 | | 5/2/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/25/2001 | | DONE |
|
|
|
Requested Architect/Engineer of record form. 4/25/01 DAR
|
Application received | | | 4/24/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/24/2001 | | DONE |
|
|
|
|