Case Summary (BLD) | | | 7/26/2004 | | DONE |
|
|
|
|
Fee Review-notes | 7/8/2003 | 7/8/2003 | 7/8/2003 | | DONE |
|
|
|
Additional value from subcontractor.
No fire review fees were charged.
|
Fee Review-notes | 4/26/2001 | 4/26/2001 | 1/29/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/23/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8797 issued 8-23-01 to Cole Elementary School for a portable classroom bldg.
|
Permanent Occupancy | | 8/22/2001 | 8/22/2001 | | DONE |
|
|
|
|
BLD-Final | 8/22/2001 | 8/22/2001 | 8/22/2001 | P | PASS |
Russ Owen
|
|
|
jack ###-####ok perm oc. 8/22/2001 1:36:26 PM
|
Code Occupancy Approval | | | 8/22/2001 | | PASS |
|
|
|
Meets compliance
|
FIRE-Final Inspection | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PASS |
Joe Tawney
|
|
|
Reinsp OK for permanant occupancy 8/20/2001 8:10:54 AM
|
BLD-Final | 8/16/2001 | 8/17/2001 | 8/17/2001 | A | NR |
Tom Arcoraci
|
|
|
Jack Young ###-####
|
Reopen Permit (ISS) | | | 8/16/2001 | | DONE |
|
|
|
reopen as per bob a.
|
FIRE-Final Inspection | 8/2/2001 | 8/3/2001 | 8/3/2001 | A | PASS |
Joe Tawney
|
|
|
Final Alarms tested OK 8/3/2001 10:37:30 AM
|
FIRE-Final Inspection | 8/2/2001 | 8/3/2001 | 8/3/2001 | A | PART |
Joe Tawney
|
|
|
Ok on alarm test 8/6/2001 7:57:11 AM
|
DOC - Permit Finaled | 8/3/2001 | 8/3/2001 | 8/3/2001 | A | PASS |
Joe Tawney
|
|
|
Finaled by inspector at 8/3/2001 10:37:40 AM
|
Issue PAID IN FULL permit | | | 6/29/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/19/2001 | | 6/25/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/25/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/25/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/25/2001 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 4/30/2001 | | 6/25/2001 | | PASS |
Mike Otto
|
|
|
6/25/2001 09:15:51 MLO - activity updated through activity BLDA022 from case BLD01-01081.
|
Routing - FIRE | 6/19/2001 | 6/19/2001 | 6/19/2001 | | PASS |
Bill Alexander
|
|
|
Provided letter of agreement for hydrant addition (on file).
|
Routing - FIRE | 5/31/2001 | 5/31/2001 | 5/31/2001 | | FAIL |
Bill Alexander
|
|
|
Architect provided letter of access and load acceptance for FD apperatus. Asked for acceptable location of hydrant and gave them 2 options. Need acceptable hydrant location plan submitted. Refaxed action/response review notes.
|
Additional plans submitted | | | 5/31/2001 | | DONE |
|
|
|
Received small documents from Hutchison Smith Architects, forwarded same to Mike Otto. 5/31/01 DAR
|
Routing - FIRE | 5/24/2001 | | 5/30/2001 | | FAIL |
|
|
|
inadequate access, excessive hydrant distance, and water flow info.
|
Routing - PLAN CHECK | 5/24/2001 | | 5/24/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/23/2001 | | DONE |
|
|
|
received two copies of revised sheets A1.0, A1.1, A3.0, one copy of HSA responses to plan review comments, and one copy of Briggs eng. struct. calcs. Routed to Mike O. KMM
|
Routing - PLAN CHECK | 5/17/2001 | | 5/17/2001 | | FAIL |
|
|
|
engineering as requested not provided, site plan is only partial.
|
Plan resubmittals requested | | | 5/17/2001 | | FAIL |
|
|
|
UBC corrections
|
Plan resubmittals received | | | 5/16/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals HSA Architects, two sets of sheets A1 and A2 plus small documents. Forwarded same to Mike Otto. 5/16/01 DAR
|
Routing - FIRE | 5/9/2001 | 5/14/2001 | 5/14/2001 | | FAIL |
Bill Alexander
|
|
|
Need access requirements, hydrant location, minimum fire flows.
|
Plan Review Completed(1st rev) | | | 5/14/2001 | | FAIL |
|
|
|
plans returned to plan review
|
Routing - PLAN CHECK | 5/2/2001 | | 5/9/2001 | | FAIL |
|
|
|
corrections faxed and mailed to architect
|
Plan resubmittals requested | | | 5/9/2001 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLANNING | 5/1/2001 | | 5/2/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 4/30/2001 | | 5/1/2001 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/30/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/30/2001 | | PEND |
|
|
|
Requires ID State tag number.
|
Received Certificate of Value | | | 4/27/2001 | | DONE |
|
|
|
|
Application received | | | 4/26/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/26/2001 | | |
|
|
|
|