(ST. AL'S REHABILITATION SERVICES - ELEVATOR ADDITION) This building is fire sprinklered. To remodel portions of an existing 12,250 square foot medical office and physical therapy building AND to construct a new elevator accessible to the disabled. Selective demolition, including removal of a wheelchair lift, is covered under this permit. The elevator shaft includes concrete footings, masonry foundations, masonry walls, wood truss roof, and metal roof covering. Work is to include modifying the basement toilet/shower rooms and the first floor reception area. A temporary ramp accessible to the disabled will also be constructed. All work shall comply with the approved drawings, engineering, and plan review conditions on file. The location of new fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. CZC01-00050 PC-0365-01 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  2/23/2007  
Fee Review-notes4/27/20014/27/200111/9/2001 DONE
Letter of compliance  11/1/2001 DONE
Letter of Compliance #22031 issued 11-1-01.
BLD-Final10/31/200110/31/200110/31/2001PPASS
DetailsTom Arcoraci
###-#### nick ok for perm 10/31/2001 2:15:02 PM
BLD-Final10/24/200110/25/200110/25/2001APART
DetailsTom Arcoraci
###-#### nick ok but needs spec insp and eng final letters and ok from code enfor 10/25/2001 2:04:39 PM
FIRE-Final Inspection10/23/200110/24/200110/24/2001APASS
DetailsTroy Cobbley
OK for perm occ. 10/25/2001 8:18:46 AM
BLD-Final10/23/200110/24/200110/24/2001PCANC
DetailsTom Arcoraci
###-#### NICK
FIRE-Final Inspection9/10/20019/11/20019/11/2001APART
DetailsJoe Tawney
Ok on location of three new heads at elevator shaft. Need head in bottom of shaft or info indicating non combustable hyd fluid 9/11/2001 1:19:44 PM
BLD-Framing/Rough-in8/13/20018/13/20018/13/2001PPART
DetailsTom Arcoraci
###-#### jerry tie in to elevator pit wip conf 8/13/2001 1:50:55 AM
BLD-Foundation7/18/20017/19/20017/19/2001PPART
DetailsTom Arcoraci
rebar nick -###-#### wip 7/19/2001 4:05:11 AM
BLD-Footing7/17/20017/17/20017/17/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 07/17/2001 at 08:12:05. Contact: ###-####. MTI ON SITE 7/17/2001 2:19:49 AM
BLD-Framing/Rough-in7/5/20017/5/20017/5/2001PPART
DetailsTom Arcoraci
for conf on temp ramp--- nick ###-#### 7/5/2001 2:49:47 AM building ramp per plan
7/5/2001 2:50:25 AM
Issue PAID IN FULL permit  7/5/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/3/2001 PASS
Inspection Record Card- Bld  7/3/2001 DONE
Print Occupancy Form  7/3/2001 DONE
Telephone call  7/3/2001 DONE
left mess that permit is ready
Plan assigned to (CJW)6/4/2001 7/3/2001 PASS
DetailsCarl Westfall
7/3/01 08:42:59 CJW - activity updated through activity BLDA022 from case BLD01-01085.
Routing - PLAN CHECK6/19/2001 7/3/2001 PASS
(6-25-01) Failed 2nd UBC review. Faxed report to architect. Asked for resubmitted Sheet SD-1. (7-3-01) Approved subject to "red lines" on the drawings and the structural inspector's judgement.
Plan resubmittals received  7/2/2001 DONE
Received two copies of revised sheet SD-1 and one copy of response letter. Routed to Carl W. KMM
Plan resubmittals received  6/22/2001  
2 copies stamped revised plans--1memo--1 letter from structural eng--1structural calc's---sd-1 a-1 a-2 a-4-- a-5

Plan Review Completed(1st rev)  6/19/2001  
Failed first UBC review.
Routing - FIRE6/14/2001 6/19/2001 PASS
Plan Reviewer's activity  6/14/2001  
Failed first UBC review. UBC plan review started June 7, 2001 and finished June 14, 2001. A response from the architect was required. See the conditions list. A plan review report was sent to the architect.
Routing - PLAN CHECK6/4/2001 6/14/2001  
Failed first UBC review.
Routing - PLAN CHECK5/10/2001 6/4/2001  
put in dan s bin 5/10/2001/pe
Plan assigned to (DRS)5/1/2001 6/4/2001 DONE
DetailsDan Stuart
Reassigned to Carl Wesfall by MYS.
Routing - PLANNING5/9/2001 5/10/2001 PASS
Paul Krommenhoek.
Routing - PLUMBING5/2/2001 5/8/2001 PASS
per plans and 97 upc
Routing - PUBLIC WORKS5/1/2001 5/2/2001 PASS
Plans ACCEPTED BY PLAN TECH  5/1/2001 PEND
Site plan not complete. 1.property lines not dimensioned
2. building not dimensioned
3. no distances to property lines from building
4. no fire hydrant placement/radieus of curves and corners of roads.
Floor plans not fully dimensioned.
No indication of codes and years under which this project is to be reviewed
Received Certificate of Value  4/27/2001 DONE
Application received  4/27/2001  