BLD-Final | 11/2/2001 | 11/5/2001 | 11/5/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/02/2001 at 15:36:27. Contact: ###-####. c. of c. #20629 issued. 11/5/2001 11:45:07 AM
|
DOC - Permit Finaled | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 11/5/2001 11:45:18 AM
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | PART |
Steven Webb
|
|
|
wip 10/8/2001 10:10:22 AM
|
BLD-Energy code compliance | 8/4/2001 | 8/6/2001 | 8/6/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/04/2001 at 21:55:59. Contact: ###-####. Engineering was submitted as requested on prior c/n--T.Young--ok to cover 8/6/2001 9:50:29 AM
|
BLD-Framing/Rough-in | 8/3/2001 | 8/3/2001 | 8/3/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/03/2001 at 07:27:03. Contact: ###-####. Engineering needed on changes to beam sizes which are marked on plans, to be verifed at energy inspection. 8/3/2001 9:00:17 AM
|
BLD-Framing/Rough-in | 8/1/2001 | 8/2/2001 | 8/2/2001 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 23:29:16. Contact: ###-####. c/n on site ok to insulate after pluming inspection 8/2/2001 10:19:55 AM
|
BLD-Other | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/17/2001 at 14:54:32. Contact: ###-####.
|
BLD-Foundation | 6/12/2001 | 6/12/2001 | 6/12/2001 | P | PART |
Steven Webb
|
|
|
###-#### wip 6/12/2001 2:18:48 PM
|
BLD-Footing | 6/12/2001 | 6/12/2001 | 6/12/2001 | P | PART |
Steven Webb
|
|
|
###-#### Already poured-appears ok 6/12/2001 2:18:34 PM
|
BLD-Footing | 6/11/2001 | 6/11/2001 | 6/11/2001 | A | NR |
Steven Webb
|
|
|
###-####
|
BLD-Footing | 5/17/2001 | 5/18/2001 | 5/18/2001 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 17:18:37. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 5/15/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 5/14/2001 | 5/14/2001 | 5/14/2001 | | PASS |
Dan Overy
|
|
|
5/14/2001 15:29:39 DJO - activity updated through activity BLDA022 from case BLD01-01133.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/14/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 5/14/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/14/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/14/2001 | | DONE |
|
|
|
called Tahoe Construction permit ready for pickup
|
Plans ACCEPTED BY PLAN CHECK | | | 5/14/2001 | | |
|
|
|
|
Routing - PLANNING | 5/2/2001 | 5/2/2001 | 5/2/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2001 | 5/2/2001 | 5/2/2001 | | PASS |
|
|
|
|
Application received | | | 5/2/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 5/2/2001 | 5/2/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 5/2/2001 | | | | PEND |
Dan Overy
|
|
|
|