Fee Review-notes | 5/2/2001 | 5/2/2001 | 5/15/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/19/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9043 issued 2-19-02 to Columbia Village Storage, Phase I, Bldg. #1.
|
Permanent Occupancy | | 2/13/2002 | 2/13/2002 | | DONE |
|
|
|
|
BLD-Final | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | PASS |
Steven Webb
|
|
|
fn insp ed -###-####
|
FIRE-Final Inspection | 2/6/2002 | 2/7/2002 | 2/7/2002 | A | PASS |
Rick Jackson
|
|
|
###-####
|
Code Occupancy Approval | | | 2/5/2002 | | PASS |
|
|
|
|
BLD-Framing/Rough-in | 1/25/2002 | 1/28/2002 | 1/28/2002 | A | PASS |
Steven Webb
|
|
|
###-#### ED Framing and 1-hr wall-- 1/28/2002 9:56:45 AM
|
BLD-Other | 1/22/2002 | 1/23/2002 | 1/23/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/22/2002 at 17:27:00. Contact: ###-####. Building #1--ext. 1-Hr not interior 1/23/2002 10:23:18 AM
|
BLD-Aging Inspection | 12/5/2001 | 12/5/2001 | 12/5/2001 | | PART |
Steven Webb
|
|
|
wip 12/5/2001 12:14:23 PM
|
Plan Reviewer's activity | | | 11/13/2001 | | PASS |
|
|
|
Parcel hold removed office must be completed prior to issuance of certificate of occupancy.
|
BLD-Concrete | 10/4/2001 | 10/4/2001 | 10/4/2001 | P | PART |
Steven Webb
|
|
|
###-####- ed concrete- ed has additional special insp on site
|
Override - Parcel Holds | | | 10/4/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 10/4/2001 | | |
|
|
|
|
BLD-Concrete | 10/1/2001 | 10/2/2001 | 10/2/2001 | A | PART |
Steven Webb
|
|
|
###-#### ed \\special insp
|
Override - Parcel Holds | | | 10/1/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 10/1/2001 | | |
|
|
|
|
BLD-Foundation | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | DONE |
Steven Webb
|
|
|
###-#### ED speical inspection 9/21/2001 12:11:34 PM
|
BLD-Footing | 8/30/2001 | 8/30/2001 | 8/30/2001 | P | PART |
Steven Webb
|
|
|
ed ###-#### ok to pour 75% of retaining wall. 8/30/2001 1:08:37 PM
|
Override - Parcel Holds | | | 8/17/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 8/17/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/17/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/16/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Override - Parcel Holds | | | 8/13/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 8/13/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/13/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/13/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/10/2001 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 8/10/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 8/10/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/10/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/10/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/23/2001 | | 8/10/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/3/2001 | | 8/10/2001 | | PASS |
Mike Phillips
|
|
|
8/10/2001 14:28:39 M_P - activity updated through activity BLDA022 from case BLD01-01152.
|
Routing - PUBLIC WORKS | 8/9/2001 | | 8/9/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/30/2001 | | 8/8/2001 | | PASS |
|
|
|
Sent plan resubmitals to consultanting engineer via PDQ. 7/30/011 DAR
|
Routing Off Site - STRUCTURAL | 8/1/2001 | | 8/8/2001 | | PASS |
|
|
|
Sent plan resubmittals to consultanting structural engineer via PDQ. 8/1/01 DAR
|
Routing - PUBLIC WORKS | 8/3/2001 | | 8/6/2001 | | FAIL |
|
|
|
Requires drainage plan revision per Brian Murphy. 8/6/01 DAR
|
Plan resubmittals received | | | 8/1/2001 | | DONE |
|
|
|
Received three sets of plan resubmittals from Glancy/Rockwell Architects, forwarded same to Mike Phillips. 8/1/01 DAR
|
Plan Reviewer's activity | | | 7/31/2001 | | FAIL |
|
|
|
Additional information required for further review and waiting for outside structural review report. Called and talked to architect about concerns. Put parcel hold on project until house plans have been approved.
|
Plan resubmittals received | | | 7/31/2001 | | DONE |
|
|
|
Received one set of plan resubmittals from Glancy/Rockwell Architects. Forwarded same to Mike Phillips. 7/31/01 DAR
|
Routing - PLANNING | 7/19/2001 | | 7/23/2001 | | PASS |
|
|
|
Approved per DRH01-00108.
|
Plan resubmittals received | | | 7/13/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals and two sets of pre-engineered buildings drawings plus small documents, forwarded same to Mike Phillips. 7/13/01 DARb b .
|
Plan Review Completed(1st rev) | | | 6/22/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 6/19/2001 | | 6/22/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/22/2001 | | 6/20/2001 | | FAIL |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 6/20/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Plan resubmittals received | | | 6/11/2001 | | DONE |
|
|
|
Two sets of plan resubmittals received plus small document, frim /Glancy/Rockwell Architects, forwarded same to Mike Phillips. 6/11/01 DAR
|
Routing Off Site - STRUCTURAL | 5/3/2001 | | 6/4/2001 | | FAIL |
|
|
|
contacted PDQ to take plans to outside eng. KMM
Additional information required for further review. MJP 6/4/01
|
Plan Reviewer's activity | | | 6/4/2001 | | FAIL |
|
|
|
Requested additional information about area separation walls, building layout and certificate of value for each building and each side of area separation walls. Waiting for additional information to be submitted prior to routing plans to fire department.
|
Routing - PLUMBING | 5/17/2001 | | 5/22/2001 | | PASS |
|
|
|
additional cross connection protection may be required
|
Routing - PLANNING | 5/15/2001 | | 5/17/2001 | | PASS |
|
|
|
Applicant needs to submit a modification to DRH00-00154. Have contacted the applicant. Approved per DRH01-00108.
|
Routing - PUBLIC WORKS | 5/3/2001 | | 5/15/2001 | | FAIL |
|
|
|
Requires Drainage Plan revision per Brian Murphy. And a street light plan per Bill Colson 5/15/01 DAR
|
Plan routing begun/NEW & ADDTN | | | 5/3/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 5/2/2001 | | DONE |
|
|
|
|
Application received | | | 5/2/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/2/2001 | | |
|
|
|
|