Letter of compliance | | | 3/22/2002 | | DONE |
|
|
|
Letter of Compliance #22312 issued 3-22-02.
|
BLD-Final | 3/21/2002 | 3/21/2002 | 3/21/2002 | P | PASS |
Tony Young
|
|
|
###-#### RICH
needs to post bond, then office can give c of c 3/21/2002 2:49:06 PM
|
BLD-Grading Inspection | 3/21/2002 | 3/21/2002 | 3/21/2002 | | BOND |
Rita DeYoung
|
|
|
Grading is complete. Reveg is not. Engineer is recommending $400 bond for reveg. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Final | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | NR |
Tony Young
|
|
|
###-####
|
BLD-Final | 3/15/2002 | 3/15/2002 | 3/15/2002 | P | FAIL |
Tony Young
|
|
|
890----9730 call 1 st 3/15/2002 10:29:02 AM
|
BLD-Aging Inspection | 1/21/2002 | 1/21/2002 | 1/21/2002 | | PART |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 11/19/2001 | 11/20/2001 | 11/20/2001 | P | FAIL |
Tony Young
|
|
|
###-#### RICH
finish hd,s and put insulation back in place 11/20/2001 4:09:09 PM
|
BLD-Framing/Rough-in | 11/6/2001 | 11/8/2001 | 11/8/2001 | A | NR |
Carl Dependahl
|
|
|
###-####, complete hd's, recall 11/8/2001 9:55:16 AM
|
BLD-Framing/Rough-in | 11/8/2001 | 11/8/2001 | 11/8/2001 | P | FAIL |
Tony Young
|
|
|
###-####
still not ready 11/8/2001 1:49:03 PM
|
BLD-Framing/Rough-in | 11/1/2001 | 11/2/2001 | 11/2/2001 | A | FAIL |
Steven Webb
|
|
|
late am ###-#### c/n prior c/n items not completed. Complete all items and re-call. 11/2/2001 11:24:01 AM
|
BLD-Framing/Rough-in | 10/29/2001 | 10/30/2001 | 10/30/2001 | P | PART |
Tony Young
|
|
|
fr insp- rich ###-####
c/n posted, ok to insulate pending pressure test pass, and engineer approval letter 10/30/2001 3:26:48 PM
|
BLD-Framing/Rough-in | 9/26/2001 | 9/26/2001 | 9/26/2001 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### CN POSTED ENGINEER TO MAKE FIELD INSP AND OK ENGINEERED SYSTEMS 9/26/2001 2:50:28 PM
|
BLD-Conference | 8/14/2001 | 8/15/2001 | 8/15/2001 | A | PART |
Tony Young
|
|
|
###-#### rich please call before
winder stair issues,. will go back w/ handout 8/15/2001 10:20:29 AM
|
BLD-Conference | 8/15/2001 | 8/15/2001 | 8/15/2001 | P | PASS |
Tony Young
|
|
|
stair issues 8/15/2001 10:23:24 AM
gave papers on stairs, also talked about blocking trusses per architect, ok to change detail w/ arch. approval 8/15/2001 4:06:41 PM
|
BLD-Foundation | 7/2/2001 | 7/3/2001 | 7/3/2001 | A | PART |
Tony Young
|
|
|
###-####
pouring 7/3/2001 11:14:47 AM
|
BLD-Footing | 6/22/2001 | 6/25/2001 | 6/25/2001 | P | PART |
Tony Young
|
|
|
early pm Rich ###-####
c/n, ok to pour after fixes are done, verbal ok via phone 6/26/2001 10:50:10 AM
|
Issue PAID IN FULL permit | | | 6/15/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 5/16/2001 | 5/16/2001 | 5/31/2001 | | PASS |
Dan Overy
|
|
|
5/31/2001 11:28:52 DJO - activity updated through activity BLDA022 from case BLD01-01167.
|
Plan Reviewer's activity | | | 5/31/2001 | | DONE |
|
|
|
received revised engineered foundations. all other items red-lined
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/31/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 5/31/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/31/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/31/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/16/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 5/16/2001 | | PEND |
|
|
|
4:15 pm. started initial review. engineere foundation and construction drawings do not match. both will be identical showing all footing locations, steps and datums. as soon as contractors is contacted other items need to be addressed. appears to be overheight walls around stair core. engineering required. missing bearing at powder room wall. truss information needed. no electrical. no trellis plans.
|
Routing - PLANNING | 5/11/2001 | 5/11/2001 | 5/14/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/3/2001 | 5/3/2001 | 5/11/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 5/3/2001 | 5/3/2001 | 5/10/2001 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3
|
Application received | | | 5/3/2001 | | |
|
|
|
came in 5/2, got addressed 5/3 3:37 pe
|
Routing - PLAN CHECK | 5/14/2001 | 5/14/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 5/3/2001 | | | | PEND |
Dan Overy
|
|
|
|