Permit Information
Permit NumberBLD01-01169
StatusFinaled
Name HEWLETT-PACKARD
Site Address 11311 W CHINDEN BLVD
Project NameHP-CHEMICAL SERVICE BLDG
Customer Number 
ePlanReviewNo
Description
(H-P CHEMICAL SERVICE BUILDING,PART OF HEWLETT-PACKARD BUILDING 6-WEST) To remodel within a 9,072 sq. ft. portion of the 45,913 sq. ft. 1st & 2nd stories (41,718 main / 4195 2nd levels) with 9600 sq. ft. basement of H.P. Building #6-West, to create rooms & areas for use as storage and distribution of hazardous materials to serve the "H-6" occupancy, fabrication area located in H.P. #6-East. To construct or upgrade the existing firewalls between "H" to "H" occupancies and and "H" to "B/S1" occupancies"; to provide mechanical, electrical, drainage, fire supression sprinkler system, alarm notification systems and distribution systems to conform with current adopted City of Boise codes and ordinances. All per approved plans, notes and attached plan review conditions of all City Agencies, all as part of the approved plans. NOTE: The entire HP Building #6 (East - West 1st & 2nd floors & basement) is listed as being currently sprinklered. Hazardous Materials Inventory Statement provided by Winslow Partnership is used to establish UBC & UFC requirements. A"Certificate of Occupancy" for the entire HP#6- E/W Occupancy is required at the final approval of the Chem Storage & Nickel Plating / Fabrication expansion project. PC#01-378/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  10/24/2002 DONE
Perm. Occ. Cert. #9420 issued 10-24-02 to HP Chemical Service Bldg.
Fee Review-notes5/4/20015/4/20013/22/2002 DONE
Letter of compliance  1/11/2002 DONE
Letter of Compliance #22119 issued 1-11-02.
Permanent Occupancy 12/27/200112/27/2001 DONE
Details
FIRE-Final Inspection12/19/200112/19/200112/19/2001PPASS
DetailsTroy Cobbley
Added by Inspector: 430 On 12/19/2001 4:32:26 PM Fire life/safety finaled
Issue PAID IN FULL permit  9/20/2001 DONE
Telephone call  9/19/2001 DONE
Telephone call  9/19/2001 DONE
tony
Routing - FIRE9/12/20019/12/20019/17/2001 PASS
Routing - PLAN CHECK9/17/2001 9/17/2001 PASS
Approved as noted on plans to include attached plan review comments / condiotions from plan review agencies.
PLANS/APPL TAKEN TO FRONT DESK  9/17/2001 PASS
To permit desk for processing to issue building permit.
Inspection Record Card- Bld  9/17/2001 DONE
Print Occupancy Form  9/17/2001 DONE
Plan assigned to (DRS)5/8/2001 9/17/2001 PASS
DetailsDan Stuart
9/17/2001 15:54:36 DRS - activity updated through activity BLDA022 from case BLD01-01169.
Routing - PLAN CHECK9/12/20019/12/20019/12/2001 PEND
Routing resubmittals to building & fire code reviews to fire code analyst for re-review to verify compliance.
Plan resubmittals received  9/12/2001 DONE
Received two copies of revised sheetsA2.1, M2.1, E2.1P, E2.1L, two copies of response letter, two copies of AHJ letter and one copy of fire response. Routed to Dan S. Two copies of rsponse to fire comments also routed to Dan S. KMM
Plan resubmittals received  9/12/2001 PEND
Inserted plans resubmittals & response to fire code analysis into original plans. Routing to fire code analyst for review of response to determine further need for additional information before permit could be issued.
Routing - PLAN CHECK8/29/2001 8/30/2001 FAIL
Received resubmittal sheets and response from architect. Items required by fire code plan review concerning the breakdown of the hazardous products as to: size of containers; method of storage (pallet, pile or rack, etc.) in each room or area; arrangment of storage; stored in approved cabinets or exhaust enclosure's, etc.; and arrangement of aisles, were not presented as part of the resubmittals so the plan cannot be circulated back to fire analyst for review. A "SPILL CONTAINMENT AND SECONDARY CONTAINMENT SYSTEM" will most likely be required for some if not all of the haz-mat rooms. This is determined based on the chemical storage container size - information not yet submitted - of one vessel grater than 55 gallons or aggregate capacity of multiple vessels exceeding 1000 gallons. This determination is made by the fire code analyst based on submittals and then the design is based on UBC section 307.2.3. Until fire code items responded to and the design data & analysis for the spill & secondary control presented to show compliance with required storage area volumes per fire code /UBC, we are still at a standstill.
For some reason the mixed occupancy analysis for the entire 6-West was modified to show only the chemical building portion, 8,900 s.f. of the 45,000 sq. ft total to show code compliance. This will need to be corrected. I have sent comments to architect to let him know ball is in his park.
NOTE: Once all the data is in or the fire and building code review of the basics, the same data will need to be presented to Bill Alexander for a separate sprinkler permit and to Sam Rogers for a separate Alarm permit per Boise City ordinance / policy. If the sprinkler system design is required ot be modified from the design values used with standard review, the size requirements for the containment areas may need to be enlarged.
Plan resubmittals received  8/29/2001 DONE
Revised sheets AO, A2.1, A3.1, M1.0, M1.1, E2.1P, E3.1. Two copies of each. Routed to Dan Stuart
Routing - FIRE8/13/2001 8/17/2001 FAIL
Comments reviewed and faxed to Tony Ray, ###-#### by SLR on 8/17/01
Plan resubmittals requested  8/13/2001 FAIL
PLANS INCOMPLETE AND INCORRECT. HAVE NOT RECEIVED ANY RESPONSE TO VERBAL (PHONE) CONVERSATION WITH BOB BOWEN ON 7/31/01 CONCERNING THE DESIGNATION OF ROOM 63, 64 & 65 AND DIFERENCES BETWEEN PLANS AND THE HAZ MAT SPECIALIST.
Routing - PLAN CHECK5/31/2001 8/13/2001 FAIL
Routing to fire code analyst for review and comment to verify the "H" occupancy hazardous materials report for confirmation of design requirements per section 307 UBC & applicable UFC. CORRECTIONS LIST TO ARCHITECT. FAXED AND MAILED.
Telephone call  7/31/2001 DONE
Called Tony Ray & Bob Bowen of HDR Architects, Inc. to see if the latest plans & hazardous materials reports had been presented to the city plan check diviosion for review. The plans indicate and "H7" occupancy use for rooms 64 & 65 (combined into one room on plans by new opening in wall) and the hazardhous materials report from Will Winslow classify's rooms 63, 64 & 65 as "S1" storage units. Bob Bowen stated the plans were correct. I told him an update of the hazardous materials report from Mr. Winslow is required to allow proper evaluation of the facility room uses which should match the report. Bob said he would start the process as the report person was hired through HP and they would have to make the request.
Routing - PLANNING5/18/2001 5/31/2001 PASS
Approved per building permit plans.
Routing - PLANNING5/30/2001 5/31/2001 PASS
Routing - PLUMBING5/14/2001 5/18/2001 PASS
per plans and 97 upc
Routing - PUBLIC WORKS5/8/2001 5/14/2001 PASS
Plans ACCEPTED BY PLAN TECH  5/4/2001  
Application received  5/4/2001  
Recd Pcfee & Taken To Pln CK  5/4/2001 DONE