Permanent occupancy | | | 10/24/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9420 issued 10-24-02 to HP Chemical Service Bldg.
|
Fee Review-notes | 5/4/2001 | 5/4/2001 | 3/22/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 1/11/2002 | | DONE |
|
|
|
Letter of Compliance #22119 issued 1-11-02.
|
Permanent Occupancy | | 12/27/2001 | 12/27/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/19/2001 | 12/19/2001 | 12/19/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/19/2001 4:32:26 PM Fire life/safety finaled
|
Issue PAID IN FULL permit | | | 9/20/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2001 | | DONE |
|
|
|
tony
|
Routing - FIRE | 9/12/2001 | 9/12/2001 | 9/17/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/17/2001 | | 9/17/2001 | | PASS |
|
|
|
Approved as noted on plans to include attached plan review comments / condiotions from plan review agencies.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2001 | | PASS |
|
|
|
To permit desk for processing to issue building permit.
|
Inspection Record Card- Bld | | | 9/17/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/17/2001 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 5/8/2001 | | 9/17/2001 | | PASS |
Dan Stuart
|
|
|
9/17/2001 15:54:36 DRS - activity updated through activity BLDA022 from case BLD01-01169.
|
Routing - PLAN CHECK | 9/12/2001 | 9/12/2001 | 9/12/2001 | | PEND |
|
|
|
Routing resubmittals to building & fire code reviews to fire code analyst for re-review to verify compliance.
|
Plan resubmittals received | | | 9/12/2001 | | DONE |
|
|
|
Received two copies of revised sheetsA2.1, M2.1, E2.1P, E2.1L, two copies of response letter, two copies of AHJ letter and one copy of fire response. Routed to Dan S. Two copies of rsponse to fire comments also routed to Dan S. KMM
|
Plan resubmittals received | | | 9/12/2001 | | PEND |
|
|
|
Inserted plans resubmittals & response to fire code analysis into original plans. Routing to fire code analyst for review of response to determine further need for additional information before permit could be issued.
|
Routing - PLAN CHECK | 8/29/2001 | | 8/30/2001 | | FAIL |
|
|
|
Received resubmittal sheets and response from architect. Items required by fire code plan review concerning the breakdown of the hazardous products as to: size of containers; method of storage (pallet, pile or rack, etc.) in each room or area; arrangment of storage; stored in approved cabinets or exhaust enclosure's, etc.; and arrangement of aisles, were not presented as part of the resubmittals so the plan cannot be circulated back to fire analyst for review. A "SPILL CONTAINMENT AND SECONDARY CONTAINMENT SYSTEM" will most likely be required for some if not all of the haz-mat rooms. This is determined based on the chemical storage container size - information not yet submitted - of one vessel grater than 55 gallons or aggregate capacity of multiple vessels exceeding 1000 gallons. This determination is made by the fire code analyst based on submittals and then the design is based on UBC section 307.2.3. Until fire code items responded to and the design data & analysis for the spill & secondary control presented to show compliance with required storage area volumes per fire code /UBC, we are still at a standstill.
For some reason the mixed occupancy analysis for the entire 6-West was modified to show only the chemical building portion, 8,900 s.f. of the 45,000 sq. ft total to show code compliance. This will need to be corrected. I have sent comments to architect to let him know ball is in his park.
NOTE: Once all the data is in or the fire and building code review of the basics, the same data will need to be presented to Bill Alexander for a separate sprinkler permit and to Sam Rogers for a separate Alarm permit per Boise City ordinance / policy. If the sprinkler system design is required ot be modified from the design values used with standard review, the size requirements for the containment areas may need to be enlarged.
|
Plan resubmittals received | | | 8/29/2001 | | DONE |
|
|
|
Revised sheets AO, A2.1, A3.1, M1.0, M1.1, E2.1P, E3.1. Two copies of each. Routed to Dan Stuart
|
Routing - FIRE | 8/13/2001 | | 8/17/2001 | | FAIL |
|
|
|
Comments reviewed and faxed to Tony Ray, ###-#### by SLR on 8/17/01
|
Plan resubmittals requested | | | 8/13/2001 | | FAIL |
|
|
|
PLANS INCOMPLETE AND INCORRECT. HAVE NOT RECEIVED ANY RESPONSE TO VERBAL (PHONE) CONVERSATION WITH BOB BOWEN ON 7/31/01 CONCERNING THE DESIGNATION OF ROOM 63, 64 & 65 AND DIFERENCES BETWEEN PLANS AND THE HAZ MAT SPECIALIST.
|
Routing - PLAN CHECK | 5/31/2001 | | 8/13/2001 | | FAIL |
|
|
|
Routing to fire code analyst for review and comment to verify the "H" occupancy hazardous materials report for confirmation of design requirements per section 307 UBC & applicable UFC. CORRECTIONS LIST TO ARCHITECT. FAXED AND MAILED.
|
Telephone call | | | 7/31/2001 | | DONE |
|
|
|
Called Tony Ray & Bob Bowen of HDR Architects, Inc. to see if the latest plans & hazardous materials reports had been presented to the city plan check diviosion for review. The plans indicate and "H7" occupancy use for rooms 64 & 65 (combined into one room on plans by new opening in wall) and the hazardhous materials report from Will Winslow classify's rooms 63, 64 & 65 as "S1" storage units. Bob Bowen stated the plans were correct. I told him an update of the hazardous materials report from Mr. Winslow is required to allow proper evaluation of the facility room uses which should match the report. Bob said he would start the process as the report person was hired through HP and they would have to make the request.
|
Routing - PLANNING | 5/18/2001 | | 5/31/2001 | | PASS |
|
|
|
Approved per building permit plans.
|
Routing - PLANNING | 5/30/2001 | | 5/31/2001 | | PASS |
|
|
|
|
Routing - PLUMBING | 5/14/2001 | | 5/18/2001 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - PUBLIC WORKS | 5/8/2001 | | 5/14/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/4/2001 | | |
|
|
|
|
Application received | | | 5/4/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/4/2001 | | DONE |
|
|
|
|