BLD-Final | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 15:22:40. Contact: ###-####. c.c # 20979 issued 11/21/2001 10:24:13 AM
|
DOC - Permit Finaled | 11/21/2001 | 11/21/2001 | 11/21/2001 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 11/21/2001 10:27:43 AM
|
BLD-Final | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 09:23:11. Contact: ###-####.
|
BLD-Final | 11/19/2001 | 11/19/2001 | 11/19/2001 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/19/2001 at 10:47:18. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/12/2001 | 10/12/2001 | 10/12/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/12/2001 at 06:45:46. Contact: ###-####. insulation ok all c/n items completed ok cover 10/12/2001 9:30:15 AM
|
BLD-Energy code compliance | 10/11/2001 | 10/11/2001 | 10/11/2001 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/11/2001 at 06:29:36. Contact: ###-####. c/n items not completed 10/11/2001 10:11:03 AM
|
BLD-Framing/Rough-in | 10/10/2001 | 10/10/2001 | 10/10/2001 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/10/2001 at 00:38:36. Contact: ###-####. c/n on site ok to insulate 10/10/2001 11:10:26 AM
|
BLD-Framing/Rough-in | 10/10/2001 | 10/10/2001 | 10/10/2001 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/10/2001 at 00:41:29. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/9/2001 | 10/9/2001 | 10/9/2001 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 06:08:24. Contact: ###-####. needs plumbing rough in and city appr plans on site 10/9/2001 10:20:44 AM
|
BLD-Wall cover | 9/27/2001 | 9/27/2001 | 9/27/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/27/2001 at 07:33:10. Contact: ###-####.
|
BLD-Foundation | 8/13/2001 | 8/13/2001 | 8/13/2001 | P | PART |
Dave Hannah
|
|
|
###-#### mana wall work in progress 8/13/2001 2:23:42 PM
|
BLD-Footing | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/09/2001 at 14:57:52. Contact: ###-####.
|
BLD-Footing | 8/9/2001 | 8/9/2001 | 8/9/2001 | P | NR |
Dave Hannah
|
|
|
###-#### crew having problems old concrete slab conflicting with ftg and drain ditch dumping water in excavation 8/9/2001 3:20:18 PM
|
Issue PAID IN FULL permit | | | 6/14/2001 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 6/5/2001 | 6/5/2001 | 6/12/2001 | | PASS |
Steve Munroe
|
|
|
6/12/2001 08:04:50 SAM - activity updated through activity BLDA022 from case BLD01-01226.
|
Print Pending Permit.LaserJet4 | | | 6/12/2001 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/12/2001 | | DONE |
|
|
|
talked to kim to verify plans are ready
|
Plan Review Report | | | 6/11/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/11/2001 | | PEND |
|
|
|
6/11/01 Plan review is done. Waiting for appeal period to be over with.
|
Plan Reviewer's activity | | | 6/8/2001 | | PEND |
|
|
|
6/8/01 Called and left a message for the builder to call me back. I have questions on spacing of pier pads and if house is engineered. Brace panels are not 4 feet in length.
|
Routing - PUBLIC WORKS | 5/9/2001 | 5/9/2001 | 6/5/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 5/9/2001 | 5/9/2001 | 6/4/2001 | | PASS |
|
|
|
Per CAA01-0129.
|
Application received | | | 5/9/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 6/5/2001 | 6/5/2001 | | | PEND |
|
|
|
|