Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD01-01316
StatusFinaled
Name PETRA INC
Site Address 3795 S DEVELOPMENT AVE
Project NameSYRINGA/PMT BLDG
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A NEW 10,000 SQUARE FOOT, ONE STORY OFFICE SHELL BUILDING WITH A 110 SQUARE FOOT, FIRE RISER/ELECTRICAL ROOM. THIS BUILDING IS CONSTRUCTED OF CONCRETE TILT-UP EXTERIOR WALLS WITH STEEL INTERIOR STRUCTURAL FRAME AND STEEL ROOF JOIST WITH METAL ROOF DECK AND SINGLE PLY ROOFING SYSTEM. THIS BUILDING IS FULLY FIRE SPRINKLED. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THIS IS A SHELL PERMIT ONLY. NO OCCUPANCY IS ALLOWED UNDER THIS PERMIT. SEPARATE TENANT IMPROVEMENT PERMITS WILL BE REQUIRED TO FINISH THIS BUILDING FOR OCCUPANCY. DRH01-00089/PC#0422-01/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/18/20024/18/20024/18/2002 DONE
Final/ok for L.C. for the shell
Letter of compliance  4/18/2002 DONE
Letter of Compliance #22339 issued 4-18-02.
BLD-Final3/14/20023/14/20023/14/2002PNR
DetailsJim Storey
###-#### HAROLD need mech permit sign off. 3/15/2002 1:51:47 PM
FIRE-Final Inspection3/14/20023/14/20023/14/2002PPASS
DetailsRick Jackson
Added by Inspector: 409 On 3/14/2002 4:43:42 PM
Case Summary (BLD)  2/25/2002 DONE
Fee Review-notes5/17/20015/17/20011/14/2002 DONE
FIRE-Final Inspection1/4/20021/7/20021/7/2002APART
DetailsRick Jackson
###-#### per Dave Miller temp occ approved pending resolution of alarm system 1/7/2002 9:32:54 AM
BLD-Final1/4/20021/7/20021/7/2002PPART
DetailsJim Storey
###-#### temp ok with agrement w/d.miller 1/7/2002 1:57:25 PM
BLD-Final1/4/20021/7/20021/7/2002PPART
DetailsJim Storey
###-#### temp ok with agrement w/d.miller 1/7/2002 1:57:25 PM
Temporary occupancy  1/7/2002 PART
Temp. Occ. Cert. #4699 issued 1-7-02 to Syringa/PMT core and shell.
Code Occupancy Approval  12/17/2001 PASS
BLD-Conference10/23/200110/23/200110/23/2001AFAIL
DetailsBill VanDegrift
Added by Inspector: 330 On 10/23/2001 8:56:19 AM need test on exterior rain water piping
BLD-Foundation9/19/20019/20/20019/20/2001APASS
DetailsJim Storey
###-#### west ft and pannel rebar ok pending special insp report/ resubmital need archived at next insp. w/harold. 9/20/2001 8:09:20 AM
BLD-Footing8/13/20018/14/20018/14/2001PPART
DetailsDave Hannah
###-#### harold spec inspection on site will check panels and ftg 8/14/2001 3:04:55 PM
FIRE-Sprinkler Rough-in8/13/20018/13/20018/13/2001APART
DetailsRick Jackson
###-#### brad okay to cover supply line see FIR01-00442 for proper permit of underground 8/13/2001 10:09:35 AM
(F) Reprint permit  7/30/2001 DONE
Issue PAID IN FULL permit  7/27/2001 DONE
Inspection Record Card- Bld  7/12/2001 DONE
Print Occupancy Form  7/12/2001 DONE
Telephone call  7/12/2001 DONE
called and left a message for Cornel Larson at ###-####
Routing - PLAN CHECK6/11/2001 7/11/2001 PASS
Plan assigned to (JCM)5/18/2001 7/11/2001 PASS
DetailsJohn Menard
7/11/01 15:38:27 JCM - activity updated through activity BLDA022 from case BLD01-01316.
PLANS/APPL TAKEN TO FRONT DESK  7/11/2001 PASS
Plan resubmittals received  6/18/2001 DONE
Received three sets of plan resubmittals from Cornel Larson Architects, plus small documents, forwarded same to John Menard. 6/18/01 DAR
Routing - FIRE6/7/2001 6/11/2001 PASS
Routing Off Site - STRUCTURAL5/18/2001 6/11/2001 FAIL
Sent plans to consultanting structural engineer via PDQ. 5/18/01 dar Received a mailed copy of the comment list from the consulting engineer requesting revisions. JCM
Plan resubmittals requested  6/11/2001  
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Plan Review Completed(1st rev)  6/11/2001 FAIL
Plan resubmittals requested  6/7/2001 FAIL
Mailed the architect of record a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK6/1/2001 6/7/2001  
Routing - PLUMBING5/30/2001 5/31/2001 PASS
per plans and 97 upc
Routing - PUBLIC WORKS5/18/2001 5/29/2001 PASS
Routing - PLANNING5/29/2001 5/29/2001 PASS
Approved per DRH01-00089
Plans ACCEPTED BY PLAN TECH  5/18/2001  
Application received  5/17/2001  
Recd Pcfee & Taken To Pln CK  5/17/2001 DONE
Routing Off Site - STRUCTURAL7/9/2001    
resubmittals 6/18/2001/ sent to outside eng. by pdq. pe