Fee Review-notes | 5/18/2001 | 5/18/2001 | 3/22/2004 | | DONE |
|
|
|
|
First Notice | | 5/28/2003 | 5/28/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/28/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9660 issued 5-28-03 to St. Luke's Hospital - Human Resources IS Bldg.
|
Permanent Occupancy | | 4/9/2003 | 4/9/2003 | | DONE |
|
|
|
|
BLD-Final | 4/9/2003 | 4/9/2003 | 4/9/2003 | P | DONE |
Dave Hannah
|
|
|
DAN; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Final | 4/4/2003 | 4/4/2003 | 4/4/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/4/2003 at 7:22:27 AM. Contact: ###-####.ok for perm occ 4/4/2003 1:11:19 PM
|
BLD-Final | 3/4/2003 | 3/5/2003 | 3/5/2003 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 3/4/2003 at 2:00:48 PM. Contact: ###-####...need verify gas storage final as per permit req's 3/5/2003 4:05:41 PM
|
BLD-Aging Inspection | 3/3/2003 | 3/3/2003 | 3/3/2003 | | PASS |
Dave Hannah
|
|
|
called construction office they will schedule final 3/4/2003 11:26:07 AM
|
BLD-Conference | 12/17/2002 | 12/19/2002 | 12/19/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/17/2002 at 15:48:28. Contact: ###-####.
|
BLD-Aging Inspection | 12/12/2002 | 12/12/2002 | 12/17/2002 | | PASS |
Carl Dependahl
|
|
|
called Stan Brown, proj mgr, will advise re final status 12/17/2002 11:23:39 AM
|
BLD-Final | 8/22/2002 | 8/22/2002 | 8/22/2002 | A | FAIL |
Jim Storey
|
|
|
###-#### need exit signage/ 8/22/2002 2:27:58 PM
|
FIRE-Final Inspection | 12/19/2001 | 12/20/2001 | 12/20/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/19/2001 at 13:00:36. Contact: ###-####.
|
BLD-Final | 12/19/2001 | 12/20/2001 | 12/20/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/19/2001 at 13:02:12. Contact: ###-####. Ok for temp oc pending conditions on permit for a perm co. 12/20/2001 2:23:01 PM
|
FIRE-Final Inspection | 12/13/2001 | 12/13/2001 | 12/13/2001 | P | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/13/2001 4:44:31 PM sprinklers in concealed combustible spaces or cover; c/n issued
|
BLD-Framing/Rough-in | 11/15/2001 | 11/15/2001 | 11/15/2001 | P | PART |
Carl Dependahl
|
|
|
celing ###-#### dan, c/n re grid clg. ok to continue 11/15/2001 4:32:45 PM
|
BLD-Framing/Rough-in | 10/30/2001 | 10/31/2001 | 10/31/2001 | A | FAIL |
Tony Young
|
|
|
###-#### DAN CEILING
c/n posted, need trades, seismic pods 10/31/2001 10:59:00 AM
|
BLD-Framing/Rough-in | 9/24/2001 | 9/24/2001 | 9/24/2001 | P | PART |
Steven Webb
|
|
|
fr ###-####- phil Southwest portion of building--floor--pending mechanical approval. 9/24/2001 2:28:46 PM
|
BLD-Framing/Rough-in | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | PART |
Dave Hannah
|
|
|
fr insp- bill ###-#### ok to cover rooms #117-121,128-132,141-143,136,138,139 micro lame beams 3ok but 4 needs point load blocking floor to ftg 9/21/2001 12:45:01 PM
|
Issue & PRINT to be Invoiced | | | 9/4/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/28/2001 | | DONE |
|
|
|
Received two copies of revised sheet S2.1 and one copy of revised Structural Calculations. Routed to Dan S. KMM
|
Inspection Record Card- Bld | | | 8/28/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/28/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/22/2001 | | 8/28/2001 | | PASS |
|
|
|
APPROVED AS NOTED ON APPROVED PLANS, SPECIFIED CONDITIONS FOR FUTURE OCCUPANCY BY "HUMAN RESOURCES-IS" AND ATTACHED PLAN REVIEW CONDITIONS OF FIRE AND BUILDING PLAN REVIEW DIVISIONS.
|
(F) Reprint permit | | | 8/27/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/27/2001 | | |
|
|
|
FAXED COMMENT SHEET TO ARCHITECT AS NOTICE THAT DOOS TO ROOMS #115 (RECRUITER OFFICE) & #128 (BREAK ROOM) ARE TO BE UPGRADED FOR ACCESSIBILITY PER APPENDIX CHAPTER 11, 20% RULE, TO BE 3'-0" X 6'-8" MINIMUM. ARCHITECT ALSO TO PROVIDE FURTHER CLARIFICATION FOR CONNENCTIONS OF NEW STRUCTURAL MEMBERS TO EACH OTHER AND TO EXISTING STRUCTURE TO STRUCTURAL INSPECTOR BEFORE FRAMING INSPECTION.
|
Telephone call | | | 8/27/2001 | | DONE |
|
|
|
CALLED AND TALKED WITH JOHN PRICE. THE CONNECTION DETAILS FOR SUPPORT AND ATTACHMENT OF NEW STRUCTURAL BEAMS & COLUMNS TO EACH OTHER AND TO EXISTING STRUCTURE IS NOT SPECIFIED. THE NEW HEADERS NOTED ON PLANS WERE NOT PART OF THE STRUCTURAL RE-SUBMITTAL. THIS INFORMATION IS TO BE PROVIDED BEFORE A FRAMING INSPECTION CAN BE DONE TO THE STRUCTURAL INSPECTOR IN THE FIELD.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2001 | | PASS |
|
|
|
ROUTING TO PERMIT DESK FOR ISSUANCE OF PERMIT.
|
Plan assigned to (DRS) | 5/18/2001 | | 8/27/2001 | | PASS |
Dan Stuart
|
|
|
8/27/2001 17:35:26 DRS - activity updated through activity BLDA022 from case BLD01-01345.
|
Routing - FIRE | 8/20/2001 | | 8/22/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/22/2001 | | DONE |
|
|
|
Received three copies of revised sheetsA0.0, A1.0, A2.0, A2.1, A7.0, A9.0, S2.1, E2.0. One copy of response letter and struct. calcs. Routed to Dan S. KMM
|
Plan Review Completed(1st rev) | | | 8/22/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/22/2001 | | 8/20/2001 | | FAIL |
|
|
|
Condition requireing further clarification or detailed re-submittals were faxed and mailed to John Price. Routing to fire code analsyst for his review and comment.
|
Print Pending Permit.LaserJet4 | | | 8/20/2001 | | |
|
|
|
|
Routing - PLUMBING | 5/21/2001 | | 5/22/2001 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - PUBLIC WORKS | 5/18/2001 | | 5/21/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/18/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 5/18/2001 | | DONE |
|
|
|
|
Application received | | | 5/18/2001 | | |
|
|
|
|