Permit Information
Permit NumberBLD01-01347
StatusFinaled
Name ST LUKES STL200408
Site Address 190 E BANNOCK ST
Project NameST LUKES-4 NORTH / SOUTH
Customer NumberSTL200-408
ePlanReviewNo
Description
(ST LUKES - 4 SOUTH & 4 NORTH of 4TH FLOOR)(NURSE STATION CORE REMODEL) To remodel approximately 4,300 sq. ft. portion of the 4th floor, Central & North Wings. To perform selective demolision as per plans; to construct new non-bearing, non-combustible, fire-resistive walls to create new room layout & support use's as per approved plans; to separate the Storage, Soiled Linen & Clean Supply rooms from adjacent areas with 1-hour occupancy separation rooms per Table 3-C, UBC; to refurbish the interiors and add new cabinetry & millwork; provide accessibility compliance; upgrades to electrical, plumbing, mechanical, fire sprinklers and alarm systems to meet hospital needs and maintain compliance with current adopted codes per approved plans on file. NOTE: This building is fully sprinklered. A "LETTER OF COMPLETION / COMPLIANCE IS REQUIRED AS A CONDITION OF THIS PERMIT BEFORE THE REMODELED AREAS ARE APPROVED FOR OCCUPANCY & USE. (P.C.#0428-01) / drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes5/18/20015/18/20013/22/2004 DONE
BLD-Aging Inspection7/22/20037/22/20037/22/2003 DONE
DetailsCarl Dependahl
previously finalled, ok for l/c 7/22/2003 9:17:38 AM
DOC - Permit Finaled7/22/20037/22/20037/22/2003APASS
DetailsCarl Dependahl
Finaled by inspector at 7/22/2003 9:17:40 AM
BLD-Final5/21/20035/22/20035/22/2003APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:31 AM. Contact: ###-####. ok for c/o 5/22/2003 11:31:19 AM
BLD-Final5/21/20035/22/20035/22/2003APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:31 AM. Contact: ###-####. ok for c/o 5/22/2003 11:31:19 AM
FIRE-Final Inspection5/13/20035/13/20035/13/2003PPASS
DetailsRick Jackson
FIRE-Final Inspection4/7/20034/7/20034/7/2003AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 4/7/2003 at 6:48:05 AM. Contact: ###-####. need detectors at all smoke/fire dampers; all rated doors not installed as shown on plans; audible not loud enough; need to relocate detectors within 5 ft of door with hold opens 4/7/2003 4:33:16 PM
FIRE-Conference3/5/20033/7/20033/7/2003AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 3/5/2003 at 10:32:30 AM. met with Jason; reviewed plans and wlaked the project area; will need 60 minute doors on all storage/linen rooms as shown on plans; penetrations will need protection; will need to test alarms and review sprinkler plans 3/7/2003 10:31:57 AM
BLD-Conference3/6/20033/7/20033/7/2003PPASS
DetailsCarl Dependahl
w/fire...seal all penetrations a 3/7/2003 5:04:30 PM t rated assy's 3/7/2003 5:07:14 PM
BLD-Framing/Rough-in10/23/200210/24/200210/24/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 10/23/2002 at 08:54:58. Contact: ###-####....walls, firestops ok at storage areas, c/n re perimeter wires etc..ok to continue, chk at final.... 10/24/02 12:34:16 PM
BLD-Framing/Rough-in9/16/20029/17/20029/17/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/16/2002 at 14:18:03. Contact: ###-####. wip on 4 th floor store room 9/17/2002 11:30:21 AM
BLD-Framing/Rough-in9/13/20029/16/20029/16/2002ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 09/13/2002 at 13:06:11. Contact: ###-####. no answer on phone 9/16/2002 3:48:33 PM
BLD-Framing/Rough-in4/9/20024/9/20024/9/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/09/2002 at 10:19:07. Contact: ###-####. walls ok at lounge area, patch roof/clg, verify s/f dampers 4/9/2002 5:24:10 PM
BLD-Aging Inspection1/7/20021/7/20021/10/2002 NR
DetailsCarl Dependahl
st lukes, work may be postponed? 1/10/2002 12:03:56 PM
Issue & PRINT to be Invoiced  9/27/2001 DONE
Print Occupancy Form  9/25/2001 DONE
Inspection Record Card- Bld  9/25/2001  
Telephone call  9/25/2001 DONE
emailed curtis 9:18 am mps
Routing - PLAN CHECK8/28/2001 9/24/2001 PASS
Resubmittals inserted into plans. Approved as noted and attached to plans.
PLANS/APPL TAKEN TO FRONT DESK  9/24/2001 PASS
Routing to permit desk to issue.
Plan assigned to (DRS)5/18/2001 9/24/2001 PASS
DetailsDan Stuart
9/24/2001 16:29:27 DRS - activity updated through activity BLDA022 from case BLD01-01347.
Plan resubmittals received  9/19/2001 DONE
Received three copies of revised sheets A1.0, A2.1, A2.2, A3.1, A3.2, A3.3, A7.1, P0.1, P1.1, P2.1, P3.1, M1.1, M2.1, E2.0, E3.0, E4.0, E5.0, one copy of response letter to Dan and one to Art. Routed to Dan S. kmm
Routing - FIRE8/22/2001 8/27/2001 PASS
Plan Review Completed(1st rev)  8/27/2001 FAIL
Routing - PLAN CHECK5/24/2001 8/22/2001 FAIL
Plan re-submittals requested of Art Albanese, ZGA. Copy faxed and mailed to Art. Routing plans to fire code analyst for review.
Routing - PLUMBING5/22/2001 5/24/2001 PASS
additional cross connection protection may be required
Routing - PUBLIC WORKS5/18/2001 5/22/2001 PASS
Plans ACCEPTED BY PLAN TECH  5/18/2001 DONE
code data not on cover sheet
Received Certificate of Value  5/18/2001 DONE
Application received  5/18/2001