Fee Review-notes | 5/25/2001 | 5/25/2001 | 2/1/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 1/14/2002 | | DONE |
|
|
|
Letter of Compliance #22123 issued 1-14-02.
|
BLD-Final | 12/6/2001 | 12/7/2001 | 12/7/2001 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/06/2001 at 12:00:43. Contact: ###-####. ok 12/7/2001 12:20:28 PM
|
BLD-Final | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/05/2001 at 16:31:14. Contact: ###-####...recall 12/6/2001 2:33:31 PM
|
FIRE-Final Inspection | 12/4/2001 | 12/5/2001 | 12/5/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/04/2001 at 16:14:00. Contact: ###-####.
|
FIRE-Final Inspection | 11/28/2001 | 11/29/2001 | 11/29/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/28/2001 at 09:31:56. Contact: ###-####. rated door at corridors; penetrations; damper control; exit signs 11/29/2001 10:37:05 AM
|
FIRE-Final Inspection | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | NR |
Troy Cobbley
|
|
|
No approved fire alarm or fire sprinkler plans on site, no record of completion, main door does not have closer installed. Did not finish inspection 11/27/2001 3:48:23 PM
|
BLD-Framing/Rough-in | 10/22/2001 | 10/23/2001 | 10/23/2001 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/22/2001 at 16:17:07. Contact: ###-####...need elec, recall. 10/23/2001 12:01:37 PM
|
BLD-Framing/Rough-in | 10/23/2001 | 10/23/2001 | 10/23/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 10/23/2001 10:24:58 AM jason ###-#### grid & walls/firestops ok
10/23/2001 5:04:59 PM
|
BLD-Final | 10/18/2001 | 10/18/2001 | 10/18/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####..not all c/n complete; recall. 10/18/2001 5:15:06 PM
|
BLD-Framing/Rough-in | 10/18/2001 | 10/18/2001 | 10/18/2001 | A | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/18/2001 3:34:04 PM c/n re ceiling & light supports, recall.
|
BLD-Framing/Rough-in | 10/18/2001 | 10/18/2001 | 10/18/2001 | A | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/18/2001 3:34:04 PM c/n re ceiling & light supports, recall.
|
BLD-Framing/Rough-in | 9/18/2001 | 9/18/2001 | 9/18/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/18/2001 at 07:07:20. Contact: ###-####. complete firestops & s/f damper at soth corr wall; chk at clg insp 9/18/2001 3:39:47 PM
|
Issue & PRINT to be Invoiced | | | 9/13/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/4/2001 | | 9/5/2001 | | PASS |
|
|
|
Approved as noted and attached plan review comments / conditions, as part of the approved plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2001 | | PASS |
|
|
|
To permit desk to process for building permit.
|
Print Occupancy Form | | | 9/5/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/5/2001 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 5/30/2001 | | 9/5/2001 | | PASS |
Dan Stuart
|
|
|
9/5/2001 06:35:04 DRS - activity updated through activity BLDA022 from case BLD01-01418.
|
Routing - FIRE | 8/29/2001 | | 9/4/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 9/4/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/31/2001 | | 8/29/2001 | | PEND |
|
|
|
No resubmittals required. Routing to fire code analyst for their review and comment.
|
Plans ACCEPTED BY PLAN TECH | | | 5/31/2001 | | DONE |
|
|
|
Received correct application. Put with plans. KMM
|
Routing - PUBLIC WORKS | 5/30/2001 | | 5/31/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/30/2001 | | PEND |
|
|
|
Requires 1. Updated application. Faxed one to Curtis W. KMM
|
Received Certificate of Value | | | 5/25/2001 | | DONE |
|
|
|
|
Application received | | | 5/25/2001 | | |
|
|
|
|