Agreement of Future work | 12/21/2001 | 12/21/2006 | 6/15/2007 | | DONE |
Jason Blais
|
|
|
Per discussion with Fire Department, fire sprinklers were to be installed in the shopping center exterior canopy in front of the bowling alley building. Owner has requested a delay or upgrade agreement in case the bowling alley is remodeled and then they will sprinkler the bowling alley building and the canopy in front at the same time or sprinkler the canopy within a 5 year maximum time frame.
8/10/06 Sent reminder letter that the Upgrade Agreement will expire within the next few months. Appropriate permits are to be obtained and work completed by the deadline. Letter is attached to this case.
12/13/06 Talked with Jenifer Gilliland about this Upgrade Agreement getting ready to expire on 12/21/06. Have not received any response to my letter sent on 8/10/06. Jenifer will discuss with Bob Archibald. Matter forwarded to Management.
6/15/2007 Upgrade Agreement work completed. Fire sprinkler and alarm work done under permits FIR07-00152 and FIR07-00439 which are both finaled.
|
MISC ACTIONS | | | 5/9/2007 | | PART |
Bob Archibald
|
|
|
FIR07-00439 submitted for alarm permit.
|
Telephone call | | | 5/4/2007 | | PART |
Bob Archibald
|
|
|
Left voice message with Mike Z. requesting alarm connection update.
|
Telephone call | | | 4/23/2007 | | PART |
Bob Archibald
|
|
|
Phone conference with Mike Zenher alarm connection should begin this week.
|
Telephone call | | | 4/19/2007 | | PART |
Bob Archibald
|
|
|
Bids being received to install relays for sprinkler sysytem permit application to follow.
|
BLD-Other | 3/15/2007 | 3/15/2007 | 3/14/2007 | P | PART |
Bob Archibald
|
|
|
Sprinkler materials onsite for canopy.
|
Telephone call | | | 3/6/2007 | | PART |
Bob Archibald
|
|
|
Site visit and phone conversation with Ron from Viking. Parts are being shipped from Portland 3/9 and installation of sprinkler system should begin on 3/12/07.
|
MISC ACTIONS | | | 3/5/2007 | | PART |
Bob Archibald
|
|
|
Sprinkler permit for front canopy issued 2/27/07 FIR07-00152
|
MISC ACTIONS | | | 2/26/2007 | | PART |
Bob Archibald
|
|
|
Permit Application under review FIR07-00152
|
MISC ACTIONS | | | 2/21/2007 | | PART |
Bob Archibald
|
|
|
Plans submitted for sprinkler sysytem at canopy FIR07-00152.
|
Telephone call | | | 2/15/2007 | | PART |
Bob Archibald
|
|
|
Spoke with Brett Lawatts from Viking, sprinkler plans will be submitted this afternoon.
|
Telephone call | | | 2/14/2007 | | PART |
Bob Archibald
|
|
|
WIth Mike Zenher, sprinkler plans should be received on 2/16/07.
|
Telephone call | | | 2/12/2007 | | PART |
Bob Archibald
|
|
|
Left voice messages with both owner and sprinkler contractor requesting information on permit status.
|
(F) Reprint permit | | | 2/7/2007 | | |
|
|
|
|
Telephone call | | | 2/1/2007 | | PART |
Bob Archibald
|
|
|
Phone call to Ron Larsen with Viking Sprinkler. Informed him that owner had less then 2 weeks to get started on sprinkler system. Ron informed me permit application would be expedited.
|
Telephone call | | | 1/25/2007 | | PART |
Bob Archibald
|
|
|
SPoke with Mike Zenher and Ron Larson(Viking). Ron will prepare drawings and submit for fire sprinkler permit.
|
Telephone call | | | 1/17/2007 | | PART |
Bob Archibald
|
|
|
Phone conference with Mike Zenher, ###-####, on N&O. Bids are being received and should be completed by 1/24/07. Mike will contact and have contractor submit plans for permit.
|
MISC ACTIONS | | | 1/16/2007 | | PART |
Bob Archibald
|
|
|
Certified mail receipt returned.
|
MISC ACTIONS | | | 1/11/2007 | | PART |
Bob Archibald
|
|
|
Notice and Order sent certified and regular mail ( expired ugrade agreement)
|
BLD-Conference | 3/3/2003 | 3/3/2003 | 3/3/2003 | P | PART |
Tony Young
|
|
|
see comments, all were inspected under other permits listed 3/3/2003 1:57:10 PM
|
DOC - Permit Finaled | 3/3/2003 | 3/3/2003 | 3/3/2003 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 3/3/2003 1:57:26 PM
|
Case Summary (BLD) | | | 3/13/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/13/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/13/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/13/2002 | | DONE |
|
|
|
|
BLD-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/11/2001 | | PART |
Tony Young
|
|
|
wip? 12/12/2001 8:47:53 AM
|
BLD-Aging Inspection | 10/11/2001 | 10/11/2001 | 10/11/2001 | | PART |
Tony Young
|
|
|
active bp 10/11/2001 10:05:49 AM
|
Issue PAID IN FULL permit | | | 7/11/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/5/2001 | | 7/6/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/6/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/6/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2001 | | DONE |
|
|
|
TALKED TO GERAD TO VERIFY PLANS ARE READY
|
Plan assigned to (JCB) | 6/6/2001 | | 7/6/2001 | | PASS |
Jason Blais
|
|
|
7/6/2001 07:53:45 JCB - activity updated through activity BLDA022 from case BLD01-01425.
|
Routing - FIRE | 7/2/2001 | | 7/5/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/5/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/5/2001 | | DONE |
|
|
|
Received plan resubmittals from Teal Architects, forwarded same to Jason Blais. 7/5/01 DAR
|
Routing - PLAN CHECK | 6/11/2001 | | 7/2/2001 | | PEND |
|
|
|
Plan review report sent and faxed to architect. No response required. When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept. for review.
|
Plan resubmittals received | | | 6/26/2001 | | DONE |
|
|
|
Received plan resubmittals from Teal Architects, two sets plus transmittal letter, forwarded same to Jason Blais. 6/26/01 DAR
|
Routing - PLANNING | 6/6/2001 | | 6/8/2001 | | PASS |
|
|
|
Approved per DRH01-78.
|
First Notice | 5/25/2001 | 5/25/2001 | 5/25/2001 | | DONE |
|
|
|
|
Application received | | | 5/25/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/25/2001 | | DONE |
|
|
|
|