Case Summary (BLD) | | | 3/28/2003 | | |
|
|
|
|
Fee Review-notes | 5/30/2001 | 5/30/2001 | 2/20/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/3/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9509 issued 1-3-03 to Latta, LLC in the Jordan Bldg.
|
Permanent Occupancy | | 12/18/2002 | 12/18/2002 | | DONE |
|
|
|
|
BLD-Aging Inspection | 12/18/2002 | 12/18/2002 | 12/18/2002 | | DONE |
Dave Hannah
|
|
|
stopped and talked with shop owner he will go get occ card from kathy 12/24/2002 10:47:30 AM
|
Print Occupancy Form | | | 12/18/2002 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/28/2002 | 1/28/2002 | 1/28/2002 | | PASS |
Carl Dependahl
|
|
|
1/28/2002 11:26:43 AM...previously finalled, called builder will turn in card 1/28/2002 2:00:36 PM
|
BLD-Conference | 1/28/2002 | 1/28/2002 | 1/28/2002 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 1/28/2002 2:01:22 PM re cards for finals/aging... 1/28/2002 4:17:11 PM
|
BLD-Final | 11/27/2001 | 11/28/2001 | 11/28/2001 | A | PASS |
Carl Dependahl
|
|
|
dave ###-#### ok 11/28/2001 4:47:48 PM for c/o 11/28/2001 4:47:57 PM
|
FIRE-Final Inspection | 11/16/2001 | 11/16/2001 | 11/16/2001 | P | PASS |
Rick Jackson
|
|
|
###-#### DAVE
|
BLD-Aging Inspection | 10/15/2001 | 10/15/2001 | 10/15/2001 | | NR |
Carl Dependahl
|
|
|
wip 10/15/2001 12:00:49 PM
|
BLD-Conference | 10/15/2001 | 10/15/2001 | 10/15/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/15/2001 11:35:44 AM visited site, finish in progress... Dave Schwalbe is contractor.
|
BLD-Conference | 8/13/2001 | 8/13/2001 | 8/13/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/13/2001 10:07:19 AM w/ bldr re obtaining finals
|
BLD-Framing/Rough-in | 8/9/2001 | 8/9/2001 | 8/9/2001 | P | PART |
Carl Dependahl
|
|
|
###-####, seal fireblock, complete stair treads; ok to cover 8/9/2001 5:13:05 PM
|
BLD-Framing/Rough-in | 7/17/2001 | 7/17/2001 | 7/17/2001 | P | PART |
Tony Young
|
|
|
###-####
stairs are wip, also curtain cove is not complete 7/17/2001 4:32:14 PM
|
Issue PAID IN FULL permit | | | 7/5/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/25/2001 | | 6/26/2001 | | PASS |
|
|
|
Drawings approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/26/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/26/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2001 | | DONE |
|
|
|
left mess that permit is ready for john price
|
Plan assigned to (CJW) | 5/31/2001 | | 6/26/2001 | | PASS |
Carl Westfall
|
|
|
6/26/01 15:28:16 CJW - activity updated through activity BLDA022 from case BLD01-01445.
|
Routing - FIRE | 6/20/2001 | | 6/25/2001 | | PASS |
|
|
|
approved without written comments
|
Plan Review Completed(1st rev) | | | 6/25/2001 | | |
|
|
|
Failed first UBC review.
|
Plan resubmittals received | | | 6/20/2001 | | DONE |
|
|
|
Received two copies of revised sheets A2.0 & A3.0. One copy of cover letter to Carl W. One copy of non stamped or signed revised 2nd floor structural analysis. Routed to Carl W. KMM
|
Routing - PLAN CHECK | 5/31/2001 | | 6/20/2001 | | |
|
|
|
Failed first UBC review.
|
Plan Reviewer's activity | | | 6/18/2001 | | |
|
|
|
Failed first UBC review. UBC plan review started June 18, 2001 and finished June 20, 2001. A response from the architect was required. See the conditions list.
|
Application received | | | 5/30/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/30/2001 | | DONE |
|
|
|
|