Fee Review-notes | 5/30/2001 | 5/30/2001 | 2/1/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 10/18/2001 | | DONE |
|
|
|
Letter of Compliance #20924 issued 10-18-01.
|
FIRE-Final Inspection | 10/9/2001 | 10/10/2001 | 10/10/2001 | A | PASS |
Rick Jackson
|
|
|
call first ###-#### to meet there
|
BLD-Final | 10/9/2001 | 10/10/2001 | 10/10/2001 | P | PASS |
Jim Storey
|
|
|
call first to meet ###-#### final ok health dept? area not in the food service area. 10/10/2001 4:22:24 PM
|
BLD-Aging Inspection | 9/26/2001 | 9/26/2001 | 9/26/2001 | | PART |
Jim Storey
|
|
|
contact with gc said he would proceed to get finals. 9/27/2001 2:15:21 PM
|
BLD-Framing/Rough-in | 7/25/2001 | 7/27/2001 | 7/27/2001 | A | PASS |
Jim Storey
|
|
|
Mark ###-#### early please duct not on plan to be boxed out to maintane ceilling assembly. can check at final. 7/27/2001 12:16:00 PM
|
Plan assigned to (JCB) | 6/5/2001 | | 7/12/2001 | | PASS |
Jason Blais
|
|
|
7/12/2001 10:01:51 JCB - activity updated through activity BLDA022 from case BLD01-01448.
|
Routing - PLAN CHECK | 6/28/2001 | | 7/12/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/12/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/12/2001 | | DONE |
|
|
|
called Dewey Treat at ###-####
|
Issue PAID IN FULL permit | | | 7/12/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/11/2001 | | DONE |
|
|
|
Received plan resubmittals from M.H. Construction, two sheets. 7/11/01 DAR
|
Plan Review Completed(1st rev) | | | 6/28/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 6/25/2001 | | 6/28/2001 | | PASS |
|
|
|
APPROVED WITHOUT WRITTEN COMMENT
|
Plan resubmittals requested | | | 6/25/2001 | | |
|
|
|
Plan resubmittals required for further review.
|
Routing - PLAN CHECK | 6/5/2001 | | 6/25/2001 | | FAIL |
|
|
|
Plan review report sent and faxed to contractor. Plan resubmittals and response required for further review. Plans routed to Fire Dept.
|
Telephone call | | | 6/5/2001 | | DONE |
|
|
|
Bob Mayer, CDH, has given verbal approval for this work to be done. Begin processing plans.
|
Plans ACCEPTED BY PLAN TECH | | | 5/31/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/31/2001 | | DONE |
|
|
|
Spoke with Bob Mayer from Central District Health. CDH is requiring that the contractor contact them to approve this project prior to our review and issuance.
|
Application received | | | 5/30/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/30/2001 | | |
|
|
|
|