Case Summary (BLD) | | | 7/12/2007 | | |
|
|
|
|
Case Summary (BLD) | | | 10/5/2005 | | |
|
|
|
|
BLD-Final | 9/23/2002 | 9/24/2002 | 9/24/2002 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/23/2002 at 11:54:12. Contact: ###-####. shell is complet ok to doc final 9/23/2002 2:39:25 PM
|
Fee Review-notes | 5/31/2001 | 5/31/2001 | 9/23/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 9/23/2002 | | DONE |
|
|
|
Letter of Compliance #22734 issued 9-23-02.
|
BLD-Final | 9/16/2002 | 9/17/2002 | 9/17/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/16/2002 at 14:33:45. Contact: ###-####.needs to finish 1 hr wall around mec room area in soffit have letters from engineer and mti approving project 9/17/2002 10:47:34 AM
|
FIRE-Final Inspection | 9/11/2002 | 9/12/2002 | 9/12/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/11/2002 at 16:50:02. Contact: ###-####.
|
BLD-Final | 9/12/2002 | 9/12/2002 | 9/12/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/12/2002 at 09:08:31. Contact: ###-####....need spec insp summary report, eng's ok,..other signature's 9/12/2002 1:26:51 PM
|
FIRE-Final Inspection | 6/20/2002 | 6/21/2002 | 6/21/2002 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 6/20/2002 11:07:42 AM curbing for fire lanes; alarm account active; ball drip for sprinkler FDC to outside; complete one hour riser room; keys for knox box; sign on door to riser room indicating sprinkler controls and FACP 6/21/2002 3:55:48 PM
|
FIRE-Final Inspection | 6/19/2002 | 6/20/2002 | 6/20/2002 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/19/2002 at 13:17:46. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/6/2001 | 12/6/2001 | 12/6/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/6/2001 11:44:08 AM gen'l walk-thru for shell only...need eng's/spec. insp reports & affidavits.
|
BLD-Aging Inspection | 12/5/2001 | 12/5/2001 | 12/5/2001 | | NR |
Carl Dependahl
|
|
|
wip 12/6/2001 11:44:40 AM
|
BLD-Framing/Rough-in | 10/4/2001 | 10/5/2001 | 10/5/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/04/2001 at 13:20:20. Contact: ###-####. ok to cover ext parapet const only 10/5/2001 11:45:22 AM
|
BLD-Concrete | 8/22/2001 | 8/23/2001 | 8/23/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 14:45:48. Contact: ###-####...ok w/ si report pending. 8/23/2001 9:25:15 AM
|
BLD-Concrete | 8/13/2001 | 8/14/2001 | 8/14/2001 | A | PART |
Carl Dependahl
|
|
|
Bob ###-#### panels look good, pending insp report 8/14/2001 4:02:10 PM
|
BLD-Foundation | 8/13/2001 | 8/13/2001 | 8/13/2001 | P | PART |
Carl Dependahl
|
|
|
tilt wall foundation bob ###-#### 8/13/2001 2:34:31 PM pend spec. insp report 8/13/2001 2:43:03 PM
|
BLD-Concrete | 8/7/2001 | 8/7/2001 | 8/7/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/7/2001 3:32:15 PM wall panels, pend report
|
BLD-Footing | 8/2/2001 | 8/2/2001 | 8/2/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/02/2001 at 10:29:40. Contact: ###-####...panels ok pend spec insp report 8/2/2001 3:54:03 PM
|
BLD-Footing | 7/19/2001 | 7/19/2001 | 7/19/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/19/2001 at 08:12:08. Contact: ###-####. pad footings ok special insp on site scope of work to be supplied at next insp. 7/19/2001 1:28:39 PM
|
(F) Reprint permit | | | 7/17/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/16/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2001 | | DONE |
|
|
|
left mess with cornel that permit is ready
|
Routing - PLAN CHECK | 7/2/2001 | | 7/5/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/5/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/5/2001 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 6/1/2001 | | 7/5/2001 | | PASS |
John Menard
|
|
|
7/5/01 14:24:38 JCM - activity updated through activity BLDA022 from case BLD01-01469.
|
Routing - FIRE | 6/29/2001 | 6/29/2001 | 6/29/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 6/28/2001 | | 6/29/2001 | | |
|
|
|
|
Plan resubmittals received | | | 6/29/2001 | | DONE |
|
|
|
Received two copies of revised sheets S-4, S-4A, S-5, S-6, S-12 AND S-13. One copy of response letter. Routed to John M. KMM
|
Routing - FIRE | 6/22/2001 | | 6/27/2001 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/4/2001 | | 6/22/2001 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. KMM Received a comment list from the consulting engineer requesting revisions. JCM
|
Plan Reviewer's activity | | | 6/22/2001 | | PASS |
|
|
|
Plans reviewed and approved as submitted with attached comment list. JCM
|
Plan resubmittals requested | | | 6/22/2001 | | |
|
|
|
Mailed the architect of record a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 6/18/2001 | | 6/22/2001 | | PASS |
|
|
|
|
Routing - PLUMBING | 6/13/2001 | | 6/18/2001 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - PUBLIC WORKS | 6/13/2001 | | 6/13/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 6/11/2001 | | 6/12/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/1/2001 | | 6/11/2001 | | FAIL |
|
|
|
Requires proof of legal land division and has a incomplete legal description, per Jim Rich. KMM
|
Plan routing begun/NEW & ADDTN | | | 6/1/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/1/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 5/31/2001 | | DONE |
|
|
|
|
Application received | | | 5/31/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/31/2001 | | |
|
|
|
|