Letter of compliance | | | 4/29/2003 | | DONE |
|
|
|
Letter of Compliance #22847 issued 4-29-03.
|
BLD-Final | 4/22/2003 | 4/23/2003 | 4/23/2003 | A | PASS |
Jim Storey
|
|
|
JOSE- ###-####
|
Override - Parcel Holds | | | 4/22/2003 | | |
|
|
|
|
BLD-Aging Inspection | 4/17/2003 | 4/17/2003 | 4/17/2003 | | PART |
Jim Storey
|
|
|
wip 4/17/2003 8:08:04 AM
|
FIRE-Final Inspection | 2/4/2003 | 2/6/2003 | 2/6/2003 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 2/4/2003 at 9:18:58 AM. Contact: ###-####.
|
Code Occupancy Approval | | | 2/6/2003 | | PASS |
|
|
|
OK FINAL SIGNED OFF.
|
BLD-Footing | 3/4/2002 | 3/5/2002 | 3/5/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/04/2002 at 12:50:45. Contact: ###-####. ft for retaining wall at tower ok pending special insp report. 3/5/2002 10:47:04 AM
|
BLD-Grading Inspection | 10/8/2001 | 10/9/2001 | 10/9/2001 | P | PART |
Rita DeYoung
|
|
|
Scheduled by a contractor via Hello! on 10/08/2001 at 17:12:42. Contact: ###-####. west /north of site paving ok at old boise cascade bld site. 10/9/2001 11:47:19 AM
|
Issue & PRINT to be Invoiced | | | 9/14/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/3/2001 | | 7/5/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/5/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/5/2001 | | DONE |
|
|
|
e-mailed Matt Petaja that permit is ready for pickup
|
Plan assigned to (JCM) | 6/6/2001 | | 7/5/2001 | | PASS |
John Menard
|
|
|
7/5/01 13:44:49 JCM - activity updated through activity BLDA022 from case BLD01-01511.
|
Routing - FIRE | 6/28/2001 | | 7/3/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/28/2001 | | PASS |
|
|
|
Plans reviewed and approved as submitted with attached comment list. JCM
|
Routing - PLAN CHECK | 6/25/2001 | | 6/28/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 6/22/2001 | | 6/25/2001 | | PASS |
|
|
|
Approve per DRH99-206
|
Routing - PUBLIC WORKS | 6/22/2001 | | 6/22/2001 | | PASS |
|
|
|
Took plans from TKW. Will reroute to her after PW. KMM/ took to tkw/pe
|
Routing - AIRPORT | 6/13/2001 | | 6/19/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/13/2001 | | DONE |
|
|
|
Received five copies of revised sheets C3.1, C3.2, C3.3, C3.4, C3.5, C3.6. Put with plans. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 6/13/2001 | | DONE |
|
|
|
Received drainage calcs. Put with plans. KMM
|
Telephone call | | | 6/11/2001 | | DONE |
|
|
|
put a call into Brett Labrie. He stated calcs are coming. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 6/11/2001 | | DONE |
|
|
|
Still requires drainage calcs. however I am routing to PW to let Brian handle that matter. I received soils report and struct. calcs for the retaining wall 6/8/01. KMM
|
Plan routing begun/NEW & ADDTN | | | 6/11/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 6/11/2001 | | 6/11/2001 | | FAIL |
|
|
|
Requires drainage calcs. and airport approval. per Brian M. KMM
|
First Notice | 6/6/2001 | 6/6/2001 | 6/6/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/6/2001 | | HOLD |
|
|
|
Waiting for 1. Drainage Calculations.
2. soils report
3. Struct. calcs. for the retaining wall.
Applicant stated I should have those by 6-7-01 KMM
|
Received Certificate of Value | | | 6/6/2001 | | DONE |
|
|
|
|
Application received | | | 6/6/2001 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | | | DONE |
|
|
|
Waiting for drainage calcs, soils report, and struct. calcs. for the retaining wall. KMM
|