Fee Review-notes | 7/8/2003 | 7/8/2003 | 7/8/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Fee Review-notes | 6/8/2001 | 6/8/2001 | 4/25/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/25/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8839 issued 9-25-01 to Schindler Elevator Corp.
|
Permanent Occupancy | | 9/24/2001 | 9/24/2001 | | DONE |
|
|
|
|
BLD-Final | 9/20/2001 | 9/24/2001 | 9/24/2001 | P | PASS |
Jim Storey
|
|
|
###-#### call first final ok storage below 8 ft. 9/24/2001 1:24:40 PM
|
FIRE-Final Inspection | 9/21/2001 | 9/24/2001 | 9/24/2001 | A | PASS |
Rick Jackson
|
|
|
fire gene- ###-####
|
FIRE-Final Inspection | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | FAIL |
Joe Tawney
|
|
|
Reinsp Fail duct detectors would not trip on can n ed smoke. FIR01-00419 9/21/2001 10:43:39 AM 9/21/2001 10:44:15 AM
|
Temporary occupancy | | | 9/18/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4592 issued 9-18-01 to Schindler Elevator Corp.
|
BLD-Final | 9/17/2001 | 9/17/2001 | 9/17/2001 | P | PASS |
Jim Storey
|
|
|
###-#### call first
tmp occ ok pending fire alarm reinsp. engineering recived to make c/n approved on framing.archived to plan.temp ok. 9/18/2001 11:15:44 AM
|
FIRE-Final Inspection | 9/12/2001 | 9/13/2001 | 9/13/2001 | A | PART |
Rick Jackson
|
|
|
###-#### call first temp approved per Dave Miller and completion of duct detectors to alarm panel and approval of plans; high pile storage racks installed without plans. talked to rep of schindler and he said they will be submitted as soon as possible 9/13/2001 9:11:28 AM
|
BLD-Final | 9/12/2001 | 9/13/2001 | 9/13/2001 | A | FAIL |
Dave Hannah
|
|
|
###-#### call first c/n on site they premits for racking sytem no temp occ issued until racks are permited 9/13/2001 10:06:42 AM
|
BLD-Framing/Rough-in | 8/22/2001 | 8/23/2001 | 8/23/2001 | A | PASS |
Russ Owen
|
|
|
jean ###-#### call first ceiling grid
|
Plan resubmittals received | | | 8/9/2001 | | DONE |
|
|
|
Received plan resubmittals from DeBest Plumbing, forwarded same to David Lightfoot. 8/9/01 DAR
|
BLD-Framing/Rough-in | 7/31/2001 | 7/31/2001 | 7/31/2001 | P | PART |
Russ Owen
|
|
|
###-#### call first to meet. ok to complete all interior shear walls etc,need ok for 3/4" substitution of 1" bolts for ledgers,cont will provide ok from engineer.also stairs not yet constructed. 7/31/2001 3:54:29 PM
|
Issue PAID IN FULL permit | | | 7/16/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/11/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/11/2001 | | DONE |
|
|
|
left mess for cornell larson that permit is ready
|
Routing - PLAN CHECK | 7/3/2001 | | 7/10/2001 | | PASS |
Ron Hill
|
|
|
took to ron
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2001 | | PASS |
Ron Hill
|
|
|
|
Case Summary (BLD) | | | 7/10/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/10/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/10/2001 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 6/11/2001 | | 7/10/2001 | | PASS |
|
|
|
7/10/2001 10:37:41 RMH - activity updated through activity BLDA022 from case BLD01-01538.
|
Routing - FIRE | 6/29/2001 | | 7/3/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/3/2001 | | DONE |
|
|
|
Received three copies of revised sheets A-1, A-2, A-3, A-4. Three copies of additional struct. calcs. and one copy of response letter. Routed to Ron H. KMM
|
Plan Review Completed(1st rev) | | | 7/3/2001 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 6/29/2001 | | FAIL |
Ron Hill
|
|
|
Faxed and mailed requirements to the architect, routed to fire department.
|
Case Summary (BLD) | | | 6/29/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/12/2001 | | 6/29/2001 | | FAIL |
Ron Hill
|
|
|
|
Routing - PUBLIC WORKS | 6/11/2001 | | 6/12/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/11/2001 | | |
|
|
|
|
Application received | | | 6/8/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/8/2001 | | |
|
|
|
|