Fee Review-notes | 7/8/2003 | 7/8/2003 | 7/8/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 5/9/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9130 issued 5-9-02 to Zion's Bank in the old Alexander Bldg.
|
BLD-Final | 4/29/2002 | 4/30/2002 | 4/30/2002 | A | PASS |
Tom Arcoraci
|
|
|
###-#### DAVE ok for perm occ 4/30/2002 11:12:12 AM
|
Permanent Occupancy | | 4/30/2002 | 4/30/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/29/2002 | 4/29/2002 | 4/29/2002 | P | PASS |
Rick Jackson
|
|
|
###-#### DAVE
|
Telephone call | | | 2/28/2002 | | DONE |
|
|
|
Left msg. w/Chris about current status of temp. occ. - fire alarm control panel issue.
|
BLD-Aging Inspection | 1/21/2002 | 1/21/2002 | 1/23/2002 | | NR |
Carl Dependahl
|
|
|
zions bank; complete fire "agreement " items 1/23/2002 6:23:03 PM
|
Conference | 1/18/2002 | 1/18/2002 | 1/18/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4593 cont. thru 3-20-02 per Tim Hogland.
|
BLD-Aging Inspection | 11/19/2001 | 11/19/2001 | 11/26/2001 | | NR |
Carl Dependahl
|
|
|
called bldr, left msg, consulted w/ 409 re FACP upgrade agreement. keep c/n wip 11/26/2001 11:44:06 AM
|
Code Occupancy Approval | | | 9/20/2001 | | PASS |
|
|
|
NO REAL REQUIREMENTS SO SIGNED FINAL.
|
Temporary occupancy | | | 9/20/2001 | | DONE |
|
|
|
Temp. Occ. Cert. #4593 issued 9-20-01 to Zion's Bank.
|
FIRE-Final Inspection | 9/19/2001 | 9/19/2001 | 9/19/2001 | P | PART |
Rick Jackson
|
|
|
fire fn- terry ###-#### per agreement with Dave Miller the FACP will be upgraded to handle the AHU detectors; smoke fire damper operation; sprinkler monitoring and other items to comply with code 9/19/2001 4:23:08 PM
|
BLD-Final | 9/19/2001 | 9/19/2001 | 9/19/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####, c/n, fire alarm agreement to be in place, seal floor & shaft penetrations, etc. 9/19/2001 5:56:40 PM
|
FIRE-Final Inspection | 9/17/2001 | 9/18/2001 | 9/18/2001 | P | FAIL |
Rick Jackson
|
|
|
TERRY ###-#### AHU detector not wired; need approval from Dave Miller for temp 9/18/2001 5:29:51 PM
|
FIRE-Final Inspection | 9/17/2001 | 9/17/2001 | 9/17/2001 | P | NR |
Rick Jackson
|
|
|
fire fn terry-- ###-####
|
Inspection Record Card- Bld | | | 9/17/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/17/2001 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 9/12/2001 | 9/12/2001 | 9/12/2001 | P | PART |
Carl Dependahl
|
|
|
fire walls dave ###-#### shaft thru 2nd fl ok per detail. 9/12/2001 3:52:28 PM ok to cover vert & horiz. portion of shaft 9/12/2001 3:53:11 PM
|
BLD-Conference | 9/11/2001 | 9/11/2001 | 9/11/2001 | P | PASS |
Carl Dependahl
|
|
|
dave- ###-#### for conf ...rec'd detail; added clarifications to sheet & approved. 9/11/2001 1:43:52 PM
|
BLD-Framing/Rough-in | 9/11/2001 | 9/11/2001 | 9/11/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/11/2001 1:46:15 PM need install int layers gyp at horiz. shaft; infill 1st floor openings & seal "shaft" & verify s/f damper at bsmt side entry to shaft.
|
BLD-Conference | 9/6/2001 | 9/7/2001 | 9/10/2001 | A | PASS |
Carl Dependahl
|
|
|
###-#### keep c/n, still need arch's detail, complete shaft at horiz section. 9/11/2001 1:42:59 PM
|
BLD-Conference | 9/7/2001 | 9/7/2001 | 9/7/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/7/2001 5:25:57 PM need archs detail...not submitted as yet.
|
BLD-Conference | 9/5/2001 | 9/6/2001 | 9/6/2001 | A | FAIL |
Jim Storey
|
|
|
###-#### early am billy ray not able to attened meetting / remove shaft and resch. 9/6/2001 10:06:58 AM
|
BLD-Conference | 9/5/2001 | 9/6/2001 | 9/6/2001 | P | CANC |
Jim Storey
|
|
|
Scheduled by Inspector: 340 On 9/5/2001 5:23:23 PM dave ###-####...re shaft w/ BRS. for Bob
|
BLD-Framing/Rough-in | 9/4/2001 | 9/5/2001 | 9/5/2001 | A | FAIL |
Carl Dependahl
|
|
|
###-####, c/n, shaft details, hvac penetrations at bsmt lid, fireblocks at soffits, need fire sprinkler r/i 9/4/2001 4:53:10 PM
|
BLD-Framing/Rough-in | 9/4/2001 | 9/5/2001 | 9/5/2001 | A | FAIL |
Carl Dependahl
|
|
|
###-####; keep c/n re shaft; wants to meet w/ arch onsite 9-6 9/5/2001 5:25:47 PM
|
BLD-Conference | 9/5/2001 | 9/5/2001 | 9/5/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/5/2001 10:29:13 AM w/ ah re shaft const...keep c/n
|
BLD-Framing/Rough-in | 8/7/2001 | 8/8/2001 | 8/8/2001 | P | PART |
Carl Dependahl
|
|
|
9415036 8/7/2001 5:01:06 PM; 1st floor ok pend elec. 8/8/2001 3:32:36 PM
|
BLD-Conference | 8/7/2001 | 8/7/2001 | 8/7/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/7/2001 11:25:53 AM ok to cover back of ATM kiosk pend elec...
|
BLD-Conference | 8/3/2001 | 8/6/2001 | 8/6/2001 | A | PASS |
Carl Dependahl
|
|
|
conf-- insp terry-- ###-#### ; c/n issued re roof drains; ok to use 3rd floor offices pending fire ok 8/6/2001 11:53:40 AM
|
FIRE-Conference | 8/6/2001 | 8/6/2001 | 8/6/2001 | P | PART |
Rick Jackson
|
|
|
Terry ###-#### okat to occupy 3rd floor 8/6/2001 4:09:42 PM
|
BLD-Final | 8/2/2001 | 8/3/2001 | 8/3/2001 | P | NR |
Carl Dependahl
|
|
|
###-####; n/r...need consult w/ GS & plan chk re partial ok for occupancy 8/6/2001 9:42:25 AM
|
Issue PAID IN FULL permit | | | 7/19/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/16/2001 | | 7/17/2001 | | PASS |
|
|
|
Drawings approved after letter from ACHD.
|
Plan Reviewer's activity | | | 7/17/2001 | | PASS |
|
|
|
Received letter from ACHD. ACHD supported issuing the building permit with the following conditions: (1) Zion's Bank obtain a right-of-way permit from ACHD's Construction Division for the installation of the storm drain pipe and connection to the tree well, and (2) Zion's Bank provide verification that a Temporary License Agreement granted by ACHD is in effect prior to occupancy.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/17/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/17/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/10/2001 | | 7/16/2001 | | |
|
|
|
Failed 2nd UBC review. At CJW's desk waiting for easment documentation.
|
Plan Reviewer's activity | | | 7/16/2001 | | |
|
|
|
Failed 2nd UBC review. Waiting for easment documentation to allow the marquee.
|
Routing - PLANNING | 7/16/2001 | | 7/16/2001 | | PASS |
|
|
|
Approve
|
Plan resubmittals received | | | 7/13/2001 | | DONE |
|
|
|
Received plan resubmittals from BRS Architects, two sets of sheets A-1, A-2 and A-5, forwarded same to CArl Westfall. 7/13/01 DAR
|
Plan Reviewer's activity | | | 7/11/2001 | | |
|
|
|
Sent letter to architect. Previous letter had been "returned for proper postage". Report was faxed July 10, 2001.
|
Routing - FIRE | 7/5/2001 | | 7/9/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/9/2001 | | |
|
|
|
Failed first UBC and Planning/Zoning reviews.
|
Routing - PLAN CHECK | 6/28/2001 | | 7/5/2001 | | |
|
|
|
Failed first UBC review.
|
Plan Reviewer's activity | | | 7/3/2001 | | |
|
|
|
Failed first UBC review. UBC plan review started July 3, 2001 and finished July 5, 2001. A response from the architect was required. See the conditions list.
|
Routing - PLANNING | 6/18/2001 | | 6/28/2001 | | |
|
|
|
Failed first P&Z review. Continue to route while historic issues are being discussed with the architect.
|
Routing - PUBLIC WORKS | 6/15/2001 | | 6/18/2001 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 6/15/2001 | | 6/15/2001 | | |
Carl Westfall
|
|
|
Drawings received June 12, 2001. 2 weeks (June 26). 3 weeks (July 3). 4 weeks (July 10).
|
Application received | | | 6/12/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/12/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 6/12/2001 | | DONE |
|
|
|
|