BLD-Aging Inspection | 10/25/2006 | 10/25/2006 | 10/26/2006 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/11/2006 | 5/15/2006 | 5/15/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/11/2006 at 8:52:52 AM. Contact: ###-####. ok for perm occ
|
FIRE-Final Inspection | 5/9/2006 | 5/10/2006 | 5/10/2006 | A | PASS |
Forrest France
|
|
|
Project related FIR permits have been finaled, fire life safety walk through is acceptable for final.
|
BLD-Final | 5/3/2006 | 5/4/2006 | 5/5/2006 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/3/2006 at 10:17:32 AM. Contact: ###-####. needs fire life safty final no inspection done
|
BLD-Final | 3/8/2006 | 3/9/2006 | 3/9/2006 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/8/2006 at 10:39:48 AM. Contact: ###-####.
|
BLD-Wall cover | 2/22/2006 | 2/23/2006 | 2/23/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/22/2006 at 10:55:58 AM. Contact: ###-####. ceiling grid ok to cover
|
BLD-Aging Inspection | 1/9/2006 | 1/9/2006 | 1/12/2006 | | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 11/9/2005 | 11/9/2005 | 11/10/2005 | P | PART |
Dave Hannah
|
|
|
dan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles framing ok but need tth two shafts built
|
BLD-Framing/Rough-in | 9/26/2005 | 9/27/2005 | 9/27/2005 | A | PART |
Dave Hannah
|
|
|
dan ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie framing just starting questions on shafts
|
BLD-Aging Inspection | 9/26/2005 | 9/26/2005 | 9/26/2005 | | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 7/25/2005 | 7/25/2005 | 7/25/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/25/2005 at 7:30:33 AM. Contact: ###-####. work to start soon
|
BLD-Framing/Rough-in | 7/20/2005 | 7/22/2005 | 7/22/2005 | A | CANC |
Jim Storey
|
|
|
dan wilson; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Aging Inspection | 5/30/2005 | 5/30/2005 | 5/31/2005 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/29/2005 | 3/29/2005 | 3/29/2005 | | PART |
Dave Hannah
|
|
|
wip 3/29/2005 1:17:30 PM
|
BLD-Aging Inspection | 11/2/2004 | 11/2/2004 | 11/2/2004 | | PASS |
Dave Hannah
|
|
|
wip 11/2/2004 10:35:16 AM
|
BLD-Aging Inspection | 8/31/2004 | 8/31/2004 | 8/31/2004 | | PASS |
Dave Hannah
|
|
|
wip 8/31/2004 8:51:14 AM
|
BLD-Aging Inspection | 6/29/2004 | 6/29/2004 | 6/29/2004 | | PASS |
Dave Hannah
|
|
|
wip 6/30/2004 1:50:55 PM
|
BLD-Aging Inspection | 4/28/2004 | 4/28/2004 | 4/28/2004 | | DONE |
Dave Hannah
|
|
|
|
Case Summary (BLD) | | | 4/14/2004 | | |
|
|
|
|
BLD-Aging Inspection | 9/30/2003 | 9/30/2003 | 9/30/2003 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 7/8/2003 | 7/8/2003 | 7/8/2003 | | PASS |
Carl Dependahl
|
|
|
wp, at demo phasei 7/8/2003 8:12:03 AM
|
BLD-Conference | 5/8/2003 | 5/8/2003 | 5/8/2003 | A | PASS |
Carl Dependahl
|
|
|
w/ Rick J re corridors 5/8/2003 9:18:43 AM
|
BLD-Aging Inspection | 4/30/2003 | 4/30/2003 | 4/30/2003 | | PASS |
Carl Dependahl
|
|
|
rec'd eng's report re seismic upgrade of north portion,, ok 5/1/2003 11:41:57 AM
|
Case Summary (BLD) | | | 2/7/2003 | | |
|
|
|
|
BLD-Aging Inspection | 1/8/2002 | 1/8/2002 | 1/9/2002 | | NR |
Carl Dependahl
|
|
|
st lukes west wing, 3rd fl south, work may be post poned? 1/9/2002 8:52:41 AM
|
Issue & PRINT to be Invoiced | | | 10/9/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/5/2001 | | DONE |
|
|
|
emailed Curtis at St. Luke's permit ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2001 | | PASS |
|
|
|
Plans to permit desk to issue.
|
Routing - PLAN CHECK | 9/13/2001 | | 10/4/2001 | | PASS |
|
|
|
Inserted new plan sheets received 10/1/01 in response to 9/11/01 plan review. Approved as noted and plan review comments attached to and part of the approved plans.
|
Plan assigned to (DRS) | 6/21/2001 | | 10/4/2001 | | PASS |
Dan Stuart
|
|
|
10/4/2001 08:45:21 DRS - activity updated through activity BLDA022 from case BLD01-01631.
|
Plan resubmittals received | | | 10/2/2001 | | DONE |
|
|
|
Received two copies of revised sheets A2.3B, M1.3B, E7.0, E7.1, and one copy of cover letter. Routed to Dan S. kmm
|
Routing - FIRE | 9/11/2001 | | 9/13/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 9/13/2001 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/11/2001 | | FAIL |
|
|
|
Faxed and mailed copy of corrections / clarifications and or details required as result of plan review for this project.
|
Routing - PLAN CHECK | 6/27/2001 | | 9/11/2001 | | FAIL |
|
|
|
Routing to fire code analyst for review.
|
Routing - PLUMBING | 6/22/2001 | | 6/27/2001 | | PASS |
|
|
|
floor drain in breakroom must not be inclosed in a cabinet
|
Routing - PUBLIC WORKS | 6/21/2001 | | 6/22/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/19/2001 | | PEND |
|
|
|
6/20/01 Mech. and Plumb signed. Still requires updated application. No code data on cover sheet of plans. KMM
Requires. 1. Updated application
2. Mech. and Plumb. and last page of Elect. need to be signed
Faxed Gred Ostrow of these needs. KMM
|
Received Certificate of Value | | | 6/18/2001 | | PEND |
|
|
|
Requires updated application. KMM
|
Application received | | | 6/18/2001 | | |
|
|
|
|
Fee Review-notes | 6/18/2001 | 6/18/2001 | | | |
|
|
|
|