Fee Review-notes | 6/19/2001 | 6/19/2001 | 4/17/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/25/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9081 issued 3-25-02 to the Nez Perce Apartments for office and work shop.
|
Permanent Occupancy | | 3/22/2002 | 3/22/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/22/2002 | 3/22/2002 | 3/22/2002 | P | PASS |
Rick Jackson
|
|
|
Shan, ###-#### - call before you go so someone can meet you there
|
BLD-Final | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 12:08:51. Contact: ###-####. final ok c/n made ok. 3/21/2002 11:32:58 AM
|
DOC - Permit Finaled | 3/21/2002 | 3/21/2002 | 3/21/2002 | P | PASS |
Jim Storey
|
|
|
Finaled by inspector at 3/21/2002 11:33:00 AM
|
BLD-Final | 3/11/2002 | 3/12/2002 | 3/12/2002 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/11/2002 at 17:10:01. Contact: ###-####. saftey glazing at office door/ hand railling. 3/12/2002 9:06:19 AM
|
Print Occupancy Form | | | 2/12/2002 | | DONE |
|
|
|
|
BLD-Conference | 2/8/2002 | 2/11/2002 | 2/11/2002 | A | NR |
Jim Storey
|
|
|
###-#### Tom Heinz please call befor going out. need to sort out all permits. 2/11/2002 2:27:10 PM
|
BLD-Framing/Rough-in | 1/9/2002 | 1/10/2002 | 1/10/2002 | A | PASS |
Jim Storey
|
|
|
###-#### c/n made ok. 1/10/2002 10:14:17 AM
|
BLD-Conference | 1/10/2002 | 1/10/2002 | 1/10/2002 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 1/10/2002 10:15:40 AM insulation ok
|
BLD-Framing/Rough-in | 1/8/2002 | 1/9/2002 | 1/9/2002 | A | PART |
Dave Hannah
|
|
|
###-#### need to fire block areas around wall becouse of drop ceiling 1/9/2002 10:58:54 AM
|
BLD-Framing/Rough-in | 1/4/2002 | 1/4/2002 | 1/4/2002 | P | PART |
Jim Storey
|
|
|
###-#### office and storage areas ok to rock. 1/4/2002 2:53:16 PM
|
BLD-Footing | 10/9/2001 | 10/9/2001 | 10/9/2001 | P | PART |
Russ Owen
|
|
|
###-#### TODD. footings appear ok ,to frost depth for new conditioned space. 10/9/2001 3:37:23 PM
|
BLD-Footing | 10/5/2001 | 10/8/2001 | 10/8/2001 | A | FAIL |
Jim Storey
|
|
|
ft insp--todd- ###-#### cell clean ft soil flooded/ maintain bar clearance. 10/8/2001 9:48:41 AM
|
BLD-Framing/Rough-in | 9/13/2001 | 9/14/2001 | 9/14/2001 | A | NR |
Dave Hannah
|
|
|
JAMIE ###-####
|
Issue PAID IN FULL permit | | | 7/12/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 6/25/2001 | | 7/3/2001 | | PASS |
Mike Phillips
|
|
|
7/3/2001 10:43:14 M_P - activity updated through activity BLDA022 from case BLD01-01646.
|
Routing - PLAN CHECK | 6/27/2001 | | 7/3/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 7/3/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/3/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/3/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/3/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/3/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/3/2001 | | DONE |
|
|
|
called Marlie Carlson at ###-#### permit ready for pickup
|
Routing - PLANNING | 6/25/2001 | | 6/27/2001 | | PASS |
|
|
|
Sev Jones. As per CUP00-00126
|
Routing - PUBLIC WORKS | 6/25/2001 | | 6/25/2001 | | PASS |
|
|
|
|
Application received | | | 6/19/2001 | | |
|
|
|
|