CHANGE STATUS TO (FNL) | | | 10/27/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/20/2003 | | |
|
|
|
|
(F) Reprint permit | | | 5/7/2003 | | |
|
|
|
|
BLD-Final | 5/28/2002 | 5/29/2002 | 5/29/2002 | A | CANC |
Jim Storey
|
|
|
###-#### ERIC called and cancled. 5/29/2002 11:32:24 AM
|
BLD-Final | 5/29/2002 | 5/29/2002 | 5/29/2002 | P | PASS |
Steven Webb
|
|
|
###-#### ERIC C. of C. #22407 issued. 5/29/2002 2:28:40 PM
|
DOC - Permit Finaled | 5/29/2002 | 5/29/2002 | 5/29/2002 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 5/29/2002 2:28:56 PM
|
BLD-Grading Inspection | 5/23/2002 | 5/23/2002 | 5/23/2002 | | PASS |
Rita DeYoung
|
|
|
Final grading and drainage complete and approved.
|
BLD-Final | 5/22/2002 | 5/22/2002 | 5/22/2002 | P | FAIL |
Tony Young
|
|
|
ERIC ###-####
need trades b-4 we can sign off ,,(hillside), no inspection made 5/22/2002 2:28:47 PM
|
BLD-Conference | 5/16/2002 | 5/16/2002 | 5/16/2002 | P | PART |
Tony Young
|
|
|
eric ###-#### call 1st
walk through on final, ///trades, handrail, plans, firecaulk, trades, hillside, etc. 5/16/2002 1:32:54 PM
|
BLD-Final | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | NR |
Russ Owen
|
|
|
fn occ- ###-####- rente . Needs hill side approval prior to calling for a bld final, called this number. 5/13/2002 12:00:35 PM
|
BLD-Conference | 4/24/2002 | 4/24/2002 | 4/24/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/24/2002 at 08:01:58. Contact: ###-####. 1 step less than 8 inch ok after landing 4/24/2002 1:29:25 PM
|
BLD-Framing/Rough-in | 12/19/2001 | 12/19/2001 | 12/19/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/19/2001 at 08:35:24. Contact: ###-####.
|
BLD-Energy code compliance | 12/19/2001 | 12/19/2001 | 12/19/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/19/2001 at 08:36:29. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/17/2001 | 12/18/2001 | 12/18/2001 | A | PART |
Tony Young
|
|
|
re- inspect shear on new addition, ////not ready, will look at framing 12/18/2001 2:25:38 PM
|
BLD-Other | 12/17/2001 | 12/18/2001 | 12/18/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/17/2001 at 15:20:33. Contact: ###-####.part ok, need full height studs on hold downs, headers installed 12/18/2001 2:19:18 PM
|
BLD-Other | 12/17/2001 | 12/17/2001 | 12/17/2001 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/17/2001 at 10:24:09. Contact: ###-####.
|
BLD-Footing | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 14:14:08. Contact: ###-####. called to canc this inspection 11-21-01///dld
|
BLD-Energy code compliance | 11/19/2001 | 11/20/2001 | 11/20/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/19/2001 at 09:15:25. Contact: ###-####. ok to cover 11/20/2001 2:51:02 PM
|
BLD-Energy code compliance | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | DONE |
Tony Young
|
|
|
420 took this 11/20/2001 3:56:28 PM
|
BLD-Framing/Rough-in | 11/16/2001 | 11/16/2001 | 11/16/2001 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/16/2001 at 08:10:15. Contact: ###-####. un able to under stand c/n to verrfy complince. 11/16/2001 2:51:19 PM
|
BLD-Framing/Rough-in | 11/14/2001 | 11/15/2001 | 11/15/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/14/2001 at 20:11:41. Contact: ###-####. c/n posted on right side unit main floor--ok to insulate 11/15/2001 10:38:10 AM
|
BLD-Framing/Rough-in | 11/13/2001 | 11/14/2001 | 11/14/2001 | A | FAIL |
Dave Hannah
|
|
|
###-#### no city approved plans or truss engin on site called contact # left message 11/14/2001 11:00:18 AM
|
BLD-Wall cover | 10/16/2001 | 10/17/2001 | 10/17/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/16/2001 at 14:41:47. Contact: ###-####.
ok to rock part of lid for ducting and rock between floor joists for firewall 10/17/2001 12:01:06 PM
|
BLD-Other | 10/11/2001 | 10/12/2001 | 10/12/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/11/2001 at 10:12:51. Contact: ###-####. sheer nailling ok/drop soffit gyp in place for p/l side of wall. 10/12/2001 9:55:41 AM
|
BLD-Other | 10/3/2001 | 10/4/2001 | 10/4/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/03/2001 at 14:51:42. Contact: ###-####.
need draft stops, and arch re-submit on duplex vs. townhouse, //// built as duplex when plans show to be built as town house, also need a complete set of plans w/ plan check notes 10/4/2001 1:49:44 PM
|
BLD-Framing/Rough-in | 9/26/2001 | 9/26/2001 | 9/26/2001 | P | PASS |
Steven Webb
|
|
|
for wall insp -###-####- mike Fire wall 1st. floor between units. 9/26/2001 3:40:51 PM
|
BLD-Foundation | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PART |
Tony Young
|
|
|
###-#### jared
wip, verbal corrections on horizontal bar, may need ltr from eng. 8/20/2001 1:14:48 PM
|
BLD-Grading Inspection | 8/10/2001 | 8/10/2001 | 8/10/2001 | | PASS |
Rita DeYoung
|
|
|
footing subgrade has been approved by Briggs Engineering.
|
BLD-Footing | 8/8/2001 | 8/8/2001 | 8/8/2001 | P | NR |
Tony Young
|
|
|
FT INSP GERAD- ###-####
need soils test and T. Records approval 8/8/2001 2:13:58 PM
|
Issue PAID IN FULL permit | | | 8/6/2001 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 7/23/2001 | | 8/1/2001 | | PASS |
Steve Munroe
|
|
|
8/1/2001 10:35:17 SAM - activity updated through activity BLDA022 from case BLD01-01691.
|
Plan Reviewer's activity | | | 8/1/2001 | | PEND |
|
|
|
8/1/01 Only one set of plans being approved due to excessive red-lining.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan Reviewer's activity | | | 7/30/2001 | | PEND |
|
|
|
7/30/01 13:50 Talked to John Mortin, the engineer. He and I went over questions and the way he looked at the engineering. He went with standard, UBC, design on interior brace wall panels. The MST 27 straps need to go into the beam from the upper floor.
|
Plan Reviewer's activity | | | 7/26/2001 | | PEND |
|
|
|
7/26/01 15:05 I called and left a message for John Mortin, with Briggs, to call me. This is the second phone call in two days to John. 15:21 I got a message from John saying he will not be able to get with me till Monday, 7/30/01.
|
Routing - PLANNING | 7/16/2001 | 7/16/2001 | 7/23/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 6/22/2001 | 6/22/2001 | 7/16/2001 | | PASS |
|
|
|
tap permit may be required. lw
|
Routing - PUBLIC WORKS GRADING | 6/22/2001 | 6/22/2001 | 7/12/2001 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 3 with conditions of approval in letter attached to plans. Soils report needed revsion. 6/23/01 took to terry records 6/22/2001/pe
|
Application received | | | 6/22/2001 | | |
|
|
|
|