Fee Review-notes | 6/22/2001 | 6/22/2001 | 4/25/2002 | | DONE |
|
|
|
|
BLD-Final | 11/14/2001 | 11/15/2001 | 11/15/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-#### jim ok for perm occ 11/15/2001 8:36:43 AM
|
Letter of compliance | | | 11/15/2001 | | DONE |
|
|
|
Letter of Compliance #22070 issued 11-15-01.
|
FIRE-Final Inspection | 11/13/2001 | 11/14/2001 | 11/14/2001 | A | PASS |
Troy Cobbley
|
|
|
Fire/life safety OK. 11/14/2001 3:33:47 PM
|
FIRE-Alarm Testing | 11/12/2001 | 11/13/2001 | 11/13/2001 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 11/13/2001 5:18:10 PM
|
BLD-Final | 11/13/2001 | 11/13/2001 | 11/13/2001 | P | NR |
Dave Hannah
|
|
|
###-#### JIM needs flssign off 11/14/2001 6:13:47 AM
|
BLD-Framing/Rough-in | 10/24/2001 | 10/24/2001 | 10/24/2001 | P | PART |
Russ Owen
|
|
|
###-#### jim. front canopy. 10/25/2001 9:33:42 AM
|
BLD-Framing/Rough-in | 9/21/2001 | 9/24/2001 | 9/24/2001 | A | PART |
Russ Owen
|
|
|
###-#### " welding" . ok subject to s-i. 9/24/2001 10:01:59 AM
|
BLD-Footing | 9/6/2001 | 9/7/2001 | 9/7/2001 | A | PART |
Russ Owen
|
|
|
jim ###-#### -rebar. Ok pending s-i . 9/7/2001 10:43:25 AM
|
BLD-Footing | 9/4/2001 | 9/5/2001 | 9/5/2001 | A | PART |
Russ Owen
|
|
|
REBAR JIM ###-####
|
BLD-Footing | 9/4/2001 | 9/4/2001 | 9/4/2001 | P | PART |
Russ Owen
|
|
|
REBAR JIM ###-####
|
BLD-Concrete | 8/31/2001 | 8/31/2001 | 8/31/2001 | P | PART |
Russ Owen
|
|
|
###-#### jim. subject to s-i tilt up wall. 8/31/2001 2:29:05 PM
|
BLD-Concrete | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | PART |
Russ Owen
|
|
|
###-#### jim
|
BLD-Concrete | 8/20/2001 | 8/20/2001 | 8/20/2001 | P | PART |
Russ Owen
|
|
|
###-#### jim. ok also subject to s-i . 8/20/2001 4:24:22 PM
|
BLD-Footing | 8/15/2001 | 8/16/2001 | 8/16/2001 | A | PART |
Tom Arcoraci
|
|
|
###-#### STRATA WILL PROVIDE SPECIAL INSPECTION ON ALL CONCRETE 8/15/2001 9:22:28 PM
|
FIRE-Sprinkler Rough-in | 8/15/2001 | 8/16/2001 | 8/16/2001 | A | CANC |
Joe Tawney
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 8/15/2001 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/13/2001 | | 8/14/2001 | | PASS |
|
|
|
Sent structural resubmittals to consulanting structural engineer via PDQ. 8/13/01 dar
Received approval letter from consulting structural engineer. JCM
|
Inspection Record Card- Bld | | | 8/14/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/14/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/14/2001 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/2001 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 6/25/2001 | | 8/13/2001 | | PASS |
John Menard
|
|
|
8/13/01 13:45:12 JCM - activity updated through activity BLDA022 from case BLD01-01695.
|
Routing - PLAN CHECK | 8/10/2001 | | 8/13/2001 | | PASS |
|
|
|
|
Routing - FIRE | 8/9/2001 | 8/10/2001 | 8/10/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PUBLIC WORKS | 8/6/2001 | | 8/9/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/26/2001 | | 8/9/2001 | | FAIL |
|
|
|
Resubmittal of 7-26-01 sent to outside eng. via PDQ. KMM Received a comment list from the consulting structural engineer requesting additional revisions and calculations.
|
Routing - PLAN CHECK | 8/2/2001 | | 8/6/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/1/2001 | | 8/2/2001 | | FAIL |
|
|
|
Requires drainage plan revisions per Brian Murphy. 8/2/01 DAR
|
Routing - PLUMBING | 7/30/2001 | | 8/1/2001 | | PASS |
|
|
|
YOUR PLAN SHOWS A 2" CW AND A 1" HW HEADER IN THE RESTROOM, FULL SIZE FROM END TO END, INSTALL THIS WAY OR RESUBMIT, ST-12 THERMOL EXPANTION TANK REQUIRED.
|
Routing - PLAN CHECK | 8/1/2001 | | 8/1/2001 | | |
|
|
|
|
Routing - FIRE | 7/26/2001 | 7/30/2001 | 7/30/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 7/30/2001 | | 7/30/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/26/2001 | | PASS |
|
|
|
Reviewed and approved resubmitted plans sheets with redlined notes and attached comment list. JCM
|
Routing - PLAN CHECK | 7/24/2001 | | 7/26/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/26/2001 | | DONE |
|
|
|
Received one copy of response to plan review (Boise City). One copy of response to plan review (fire dept.). Water flow letter from United Water (Fire Dept.). Two copies of revised civil plans C1.0 to C1.3. Two copies of revised Storm water management plan. Three copies of revised structural sheet S-4 Three copies of additional structural calculations and three copies of response to structural plan review. Routed all of the above to John M. KMM
|
Routing - FIRE | 7/20/2001 | | 7/24/2001 | | FAIL |
|
|
|
HYDRANT FLOW
|
Plan Review Completed(1st rev) | | | 7/24/2001 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 7/20/2001 | | |
|
|
|
Faxed Gayle Jensen, at Van Auker, a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 7/20/2001 | | |
|
|
|
Mailed Gayle Jensen, at Van Auker, a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 7/11/2001 | | 7/20/2001 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/25/2001 | | 7/16/2001 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. KMM Received a comment list from the consulting engineer requesting revisions. JCM
|
Plan resubmittals received | | | 7/13/2001 | | DONE |
|
|
|
Received plan resubmittals for Bill Vandergrift, two sets, forwarded same to John Menard.
7/13/01 DAR
|
Routing - PLUMBING | 7/9/2001 | | 7/11/2001 | | FAIL |
|
|
|
PLEASE ADDRESS THE ABOVE ITEMS ALSO PROVIDE DETAIL OF MEZZANINE WATER HEATER IS LOCATED ON TO DETERMINE IF A PERMANENT LADDER WILL BE REQUIRED.
|
Routing - PLANNING | 7/6/2001 | | 7/9/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/25/2001 | | 7/6/2001 | | FAIL |
|
|
|
Requires drainage plan revisions per Brian Murphy. 7/6/01 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 6/25/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 6/25/2001 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 6/25/2001 | | DONE |
|
|
|
|
Application received | | | 6/22/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/22/2001 | | |
|
|
|
|