BLD-Final | 12/7/2001 | 12/10/2001 | 12/10/2001 | A | PASS |
Jim Storey
|
|
|
###-####
|
DOC - Permit Finaled | 12/10/2001 | 12/10/2001 | 12/10/2001 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 12/10/2001 11:25:21 AM
|
BLD-Final | 12/6/2001 | 12/7/2001 | 12/7/2001 | A | CANC |
Jim Storey
|
|
|
###-#### GREG
|
BLD-Energy code compliance | 9/5/2001 | 9/6/2001 | 9/6/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/05/2001 at 14:12:16. Contact: ###-####. fr made ok insulation ok for cover. 9/6/2001 1:43:21 PM
|
BLD-Framing/Rough-in | 8/29/2001 | 8/30/2001 | 8/30/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/29/2001 at 15:08:10. Contact: ###-####.c/n posted. 8/30/2001 12:12:07 PM
|
BLD-Framing/Rough-in | 8/8/2001 | 8/8/2001 | 8/8/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/08/2001 at 07:51:28. Contact: ###-####. brace wall panel nailling as per plan ok for cover. 8/8/2001 3:59:00 PM
|
BLD-Foundation | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### walls ok 7/12/2001 3:36:53 PM
|
BLD-Footing | 7/9/2001 | 7/10/2001 | 7/10/2001 | A | PART |
Steven Webb
|
|
|
Jed ###-#### wip--Received soil compaction report from contractor 95% compaction received. 7/10/2001 10:36:38 AM
|
Issue PAID IN FULL permit | | | 7/5/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 6/26/2001 | 6/26/2001 | 6/27/2001 | | PASS |
Dan Overy
|
|
|
6/27/2001 09:49:35 DJO - activity updated through activity BLDA022 from case BLD01-01709.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/27/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/27/2001 | | DONE |
|
|
|
talked to Steve gave dollar amount
|
Plans ACCEPTED BY PLAN CHECK | | | 6/26/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/26/2001 | | PEND |
|
|
|
have spoke with eric from pinnacle about garage front wall length being different from what is spec. in calculations. he will refigure and fax addendum. will issue when received.
|
Routing - PLANNING | 6/25/2001 | 6/25/2001 | 6/25/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/25/2001 | 6/25/2001 | 6/25/2001 | | PASS |
|
|
|
|
Application received | | | 6/25/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 6/25/2001 | 6/25/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 6/25/2001 | | | | PEND |
Dan Overy
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | PEND |
|
|
|
|
Plan Review Report | | | | | PEND |
|
|
|
|