DOC-Permit Expired | 8/18/2003 | 8/18/2003 | 8/18/2003 | | DONE |
Russ Owen
|
|
|
Permit expired by limitations.
|
Expired/Cancelled | | | 8/18/2003 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | | | 6/17/2002 | | DONE |
|
|
|
Project complete, Cathy W. to sign for PW. G.Fitts 06/17/02
|
BLD-Conference | 12/20/2001 | 12/20/2001 | 12/20/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/20/2001 4:53:56 PM Fire life/safety and fire sprinkler finaled
|
BLD-Aging Inspection | 11/28/2001 | 11/28/2001 | 11/28/2001 | | PART |
Russ Owen
|
|
|
|
Print Occupancy Form | | | 8/22/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/22/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2001 | | DONE |
|
|
|
left message with katherine gave dollar amount
|
Inspection Record Card- Bld | | | 8/22/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/22/2001 | | DONE |
|
|
|
|
Routing - FIRE | 8/21/2001 | 8/21/2001 | 8/21/2001 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/21/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/20/2001 | | 8/21/2001 | | DONE |
|
|
|
|
Plan assigned to (KMM) | 7/3/2001 | | 8/21/2001 | | PASS |
Kathy Miller
|
|
|
8/21/01 11:45:54 KMM - activity updated through activity BLDA022 from case BLD01-01794.
|
Routing - PLUMBING | 8/18/2001 | | 8/20/2001 | | PASS |
|
|
|
|
Routing - FIRE | 8/20/2001 | | 8/20/2001 | | FAIL |
|
|
|
WATER SUPPLY & OBSTRUCTED HYDRANT
|
Routing - PLAN CHECK | 7/24/2001 | | 8/18/2001 | | |
|
|
|
|
Plan resubmittals received | | | 8/6/2001 | | |
|
|
|
|
Plan resubmittals received | | | 8/6/2001 | | DONE |
|
|
|
Received six sets of plan resubmittals . 8/6/01 DAR
|
Plan resubmittals received | | | 8/6/2001 | | DONE |
|
|
|
Received plan resubmittals from BRS Architects two sets of sheet A-3, forwarded same to Mike Otto. 8/6/01 DAR
|
Routing - PUBLIC WORKS | 8/6/2001 | | 8/6/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/23/2001 | | 7/24/2001 | | FAIL |
|
|
|
Requires drainage plan revision per Brian Murphy. 7/24/01 DAR
|
Routing - PLAN CHECK | 7/18/2001 | | 7/23/2001 | | |
|
|
|
|
Plan resubmittals received | | | 7/23/2001 | | DONE |
|
|
|
Received five copies of revised sheets A.0e, L.1d, C-1, C-2, C-3, C-4. One copy of revised O & M manual and one copy of post development drainage calculations. Put with plans . KMM
|
Routing - PUBLIC WORKS | 7/17/2001 | | 7/18/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/16/2001 | | 7/17/2001 | | |
|
|
|
|
Routing - FIRE | 7/12/2001 | | 7/16/2001 | | FAIL |
|
|
|
water supply & hydrant location
|
Plan Review Completed(1st rev) | | | 7/16/2001 | | FAIL |
|
|
|
|
Routing - PLUMBING | 7/10/2001 | | 7/12/2001 | | FAIL |
|
|
|
|
Routing - PLANNING | 7/9/2001 | | 7/10/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/3/2001 | | 7/9/2001 | | FAIL |
|
|
|
brian m failed requires revised drainage plan
|
Plan routing begun/NEW & ADDTN | | | 7/3/2001 | | DONE |
|
|
|
|
Application received | | | 7/3/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/3/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 7/3/2001 | | DONE |
|
|
|
|