Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-01795
StatusFinaled
Name REILLY O'REILLY
Site Address 242 N 8TH ST Unit: 200
Project NameFIDELITY BLDG-2ND FLR
Customer Number 
ePlanReviewNo
Description
(REILLY O'REILLY - FIDELITY BLDG - 2ND FLR) This building is fire sprinklered to substitute for 1-hr fire-resistive construction. To create a 2,000 square foot office tenant space on the 2nd floor of a historic building. A 250 square foot common lobby is also being constructed. Selective nonstructural demolition is also covered under this permit. Work is to include interior nonbearing walls, interior doors, interior windows, and finishes all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. PC-0541-01 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes7/3/20017/3/20013/22/2002 DONE
Permanent occupancy  10/3/2001 DONE
Perm. Occ. Cert. #8849 issued 10-3-01 to Reilly O'Reilly.
Permanent Occupancy 10/2/200110/2/2001 DONE
Details
BLD-Final10/1/200110/2/200110/2/2001APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 10/01/2001 at 08:50:55. Contact: ###-####.
FIRE-Final Inspection8/20/20018/21/20018/21/2001PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/20/2001 at 14:36:53. Contact: ###-####.
BLD-Framing/Rough-in8/2/20018/3/20018/3/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/02/2001 at 12:00:32. Contact: ###-####. walls ok pend elec. 8/3/2001 2:49:59 PM
Print Occupancy Form  8/2/2001 DONE
Inspection Record Card- Bld  8/2/2001 DONE
Telephone call  8/2/2001 DONE
permit ready
Issue PAID IN FULL permit  8/2/2001 DONE
Plan Review Completed(1st rev)  8/1/2001 PASS
Routing - PLAN CHECK8/1/2001 8/1/2001 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/1/2001 PASS
Plan assigned to (CJW)7/3/2001 8/1/2001 PASS
DetailsCarl Westfall
8/1/01 15:32:05 CJW - activity updated through activity BLDA022 from case BLD01-01795.
Routing - FIRE7/26/2001 8/1/2001 PASS
RLD
Routing - PLAN CHECK7/9/2001 7/26/2001 PASS
Drawings approved.
Plan Reviewer's activity  7/25/2001 PASS
UBC plan review started July 25, 2001 and finished the same day. The drawings were approved with conditions. See the conditions list.
Routing - PUBLIC WORKS7/3/2001 7/9/2001 PASS
Plans ACCEPTED BY PLAN TECH  7/3/2001 DONE
not fully dimensioned
Received Certificate of Value  7/3/2001 DONE
Application received  7/3/2001