Case Summary (BLD) | | | 10/2/2012 | | DONE |
|
|
|
|
Fee Review-notes | 7/17/2001 | 7/17/2001 | 7/19/2002 | | DONE |
|
|
|
7/19-left mesg. with phil to call me back
|
(F) Reprint permit | | | 7/19/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/16/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9137 issued 5-16-02 to KFC/A & W.
|
BLD-Final | 5/8/2002 | 5/9/2002 | 5/9/2002 | P | PASS |
Jim Sly
|
|
|
###-#### call first to meet there OK for Perm Occ. 5/9/2002 5:01:34 PM
|
Permanent Occupancy | | 5/9/2002 | 5/9/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/8/2002 | 5/8/2002 | 5/8/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 5/8/2002 3:27:06 PM
|
BLD-Aging Inspection | 11/28/2001 | 11/28/2001 | 11/28/2001 | | PART |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 9/26/2001 | 9/26/2001 | 9/26/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/26/2001 at 01:52:24. Contact: ###-####.new metal studs added to the exterior. 9/26/2001 2:30:09 PM
|
Plan assigned to (R_H) | 7/20/2001 | | 9/24/2001 | | PASS |
|
|
|
9/24/2001 08:12:59 RMH - activity updated through activity BLDA022 from case BLD01-01925.
|
Routing - PLAN CHECK | 8/28/2001 | | 9/24/2001 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2001 | | PASS |
Ron Hill
|
|
|
|
Print Occupancy Form | | | 9/24/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/24/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/24/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/21/2001 | | |
|
|
|
Plan resubmittal sheets A-2, structural calculations, and new application submitted and routed to Ron.
|
Plan Reviewer's activity | | | 9/19/2001 | | FAIL |
Ron Hill
|
|
|
Second review failed 9-19-01, faxed requirements to the architect, PAT MCKEEGAN.
|
Plan resubmittals received | | | 9/14/2001 | | DONE |
|
|
|
Received two copies of revised sheetsT1.0, D1.0, A1.0, A2.0, A3.0, EQ1.0, one copy of cover letter. Routed to Ron Hill. KMM
|
Routing - FIRE | 8/24/2001 | | 8/28/2001 | | PASS |
|
|
|
approved without written comment
|
Plan Review Completed(1st rev) | | | 8/28/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/1/2001 | | 8/24/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/23/2001 | | FAIL |
Ron Hill
|
|
|
Faxed and mail plan review report to Architect, and routed plans to fire department for review.8-24-01
|
Routing - PLANNING | 7/27/2001 | | 8/1/2001 | | PASS |
|
|
|
Approved per DRH01-00137.
|
Routing - PLUMBING | 7/23/2001 | | 7/24/2001 | | PASS |
|
|
|
ADDITIONAL CROSS CONNECTION PROTECTION MAY BE REQUIRED
|
Routing - PUBLIC WORKS | 7/20/2001 | | 7/23/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/17/2001 | | DONE |
|
|
|
CDH signed off on 6/26/2001.
|
Application received | | | 7/17/2001 | | |
|
|
|
|