DOC - Permit Finaled | | | 11/6/2002 | | DONE |
|
|
|
|
PostCard Mailed | | | 11/1/2002 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
PostCard Mailed | | | 9/29/2002 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
BLD-Final | 3/26/2002 | 3/27/2002 | 3/27/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/26/2002 at 08:29:57. Contact: ###-####.
hand rail ok'd by 325, c of c issued 3/27/2002 11:15:16 AM
|
BLD-Final | 2/12/2002 | 2/13/2002 | 2/13/2002 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/12/2002 at 15:01:32. Contact: ###-####.
c/n posted 2/13/2002 2:36:13 PM
|
BLD-Grading Inspection | 2/13/2002 | 2/13/2002 | 2/13/2002 | | DONE |
Rita DeYoung
|
|
|
Final grading and drainage approved
|
BLD-Final | 1/30/2002 | 1/31/2002 | 1/31/2002 | A | NR |
Tony Young
|
|
|
call chris conner 1st, see history for ph# 1/30/2002 4:26:38 PM
|
BLD-Final | 1/29/2002 | 1/30/2002 | 1/30/2002 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 01/29/2002 at 07:53:37. Contact: ###-####.
|
BLD-Final | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | NR |
Tony Young
|
|
|
final inspection 1/30/2002 10:53:07 AM
|
BLD-Aging Inspection | 1/7/2002 | 1/7/2002 | 1/7/2002 | | PART |
Tony Young
|
|
|
wip 1/7/2002 10:16:40 AM
|
BLD-Wall cover | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 11:29:41. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### CHRIS cn posted 11/5/2001 3:44:30 PM
|
BLD-Framing/Rough-in | 11/1/2001 | 11/2/2001 | 11/2/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/01/2001 at 10:55:55. Contact: ###-####.Shear only--not ready for frame-missing mechanical r. i. approval. Ok to side. 11/2/2001 10:36:49 AM
|
BLD-Footing | 9/13/2001 | 9/13/2001 | 9/13/2001 | P | PART |
Tony Young
|
|
|
chris ###-#### 9/13/2001 11:22:46 AM
great room epoxy cololm bolts, 8 total,,, t/w arch. via phone on procedure, ok 9/13/2001 2:17:09 PM
|
BLD-Footing | 8/20/2001 | 8/21/2001 | 8/21/2001 | A | PART |
Tony Young
|
|
|
###-#### tim
need letter from eng on alt. column on back shear wall 8/21/2001 10:52:00 AM
|
BLD-Footing | 8/15/2001 | 8/16/2001 | 8/16/2001 | A | PART |
Tony Young
|
|
|
###-####
wip but need to see more, need to clarify detail on steel column w/in stemwall 8/16/2001 11:38:57 AM
|
BLD-Footing | 8/16/2001 | 8/16/2001 | 8/16/2001 | P | PART |
Tony Young
|
|
|
verbal corrections 8/16/2001 2:15:27 PM
|
BLD-Grading Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade has been approved by the geotechnical engineer.
|
Plan assigned to (DJO) | 7/27/2001 | 7/27/2001 | 8/6/2001 | | PASS |
Dan Overy
|
|
|
8/6/2001 10:16:18 DJO - activity updated through activity BLDA022 from case BLD01-01938.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/6/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 8/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/6/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/6/2001 | | DONE |
|
|
|
permit ready
|
Issue PAID IN FULL permit | | | 8/6/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 8/1/2001 | 8/1/2001 | 8/1/2001 | | PASS |
|
|
|
per revised site plan
|
Plan Reviewer's activity | | | 7/30/2001 | | PEND |
|
|
|
started initial review late friday afternoon. additional engineering has been submitted for shear walls. after furthur review i found that the plans had not been seen by planning & zoning. took plans over to angie to ok setbacks.
|
Plans ACCEPTED BY PLAN CHECK | | | 7/27/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 7/18/2001 | 7/18/2001 | 7/24/2001 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3 with conditions of approval in letter attached to plans.
|
Routing - PUBLIC WORKS | 7/18/2001 | 7/18/2001 | 7/24/2001 | | DONE |
|
|
|
|
Application received | | | 7/18/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 7/24/2001 | 7/24/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 7/18/2001 | | | | PEND |
Dan Overy
|
|
|
|