Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD01-01951
StatusFinaled
Name DILLON LTD. PARTNERSHIP
Site Address 2713 S HILTON ST
Project NameDILLON LTD. PARTNERSHIP
Customer Number 
ePlanReviewNo
Description
(DILLON LTD. PARTNERSHIP - CONVERT HOUSE TO OFFICE) This building is NOT fire sprinklered. To convert a 1,735 square foot dwelling (1,055 square foot first floor and 680 square foot basement) to an office. The 340 square foot 2nd floor is being abandoned and is not approved for occupancy. Work is to include a new exterior basement stairway, a basement enclosure, a restroom accessible to the disabled, a glass sliding door, an exterior deck, and an accessible exterior ramp all per approved drawings and plan review conditions on file. The parking lot improvements are covered under permit BLD00-03546. CUP99-00136 PC-0606-01 **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection12/18/200312/18/200312/18/2003 PASS
DetailsTom Arcoraci
DOC - Permit Finaled12/18/200312/18/200312/18/2003PPASS
DetailsTom Arcoraci
Finaled by inspector at 12/18/2003 2:31:43 PM
Permanent occupancy  2/3/2003 DONE
Perm. Occ. Cert. #9549 issued 2-3-03 to Dillon Partnership, LTD
BLD-Final1/30/20031/31/20031/31/2003APASS
DetailsTom Arcoraci
###-#### ok for perm occ 1/31/2003 11:10:37 AM
Permanent Occupancy 1/31/20031/31/2003 DONE
Details
BLD-Final11/7/200211/8/200211/8/2002ANR
DetailsTom Arcoraci
###-####--scott
Case Summary (BLD)  11/7/2002  
BLD-Conference6/4/20026/4/20026/4/2002PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 6/4/2002 1:52:40 PM explained hand rail requirements 6/4/2002 4:29:44 PM
Telephone call  5/31/2002 DONE
Talked w/Scott (owner's rep.) re: completing correction notice items asap for perm. occ.
BLD-Final5/29/20025/30/20025/30/2002AFAIL
DetailsJim Storey
1. (Ramp handrails) Ramps having slopes steeper than 1 unit vertical in 20 units horizontal shall have handrails as required for stairways, except that intermediate handrails shall not be required. (1997 UBC 1003.3.4.5)

2. (Handrail extensions and returns at ramps) Handrails shall be continuous the full length of the ramp and at least one handrail shall extend in the direction of the ramp run not less than 12 inches beyond the top of the ramp nor less than 12 inches beyond the bottom of the ramp. Ends shall be returned or shall have rounded terminations or bends. (1997 UBC 1003.3.3.6) Note the exceptions for private ramps and dwelling units.

3. (Allowed projections into stairway width) Handrails may project into the required width a distance of 3-1/2 inches from each side of a stairway. Stringers and other projections such as trim and similar decorative features may project into the required width 1-1/2 inches from each side. (1997 UBC 1003.3.3.2)



5. (Height of handrails for stairways) The top of handrails and handrail extensions shall not be placed less than 34 inches nor more than 38 inches above landings and the nosing of treads. (1997 UBC 1003.3.3.6)

6. smoke seal on 20 min fire door.
Fee Review-notes7/19/20017/19/20013/11/2002 DONE
BLD-Final2/13/20022/14/20022/14/2002PPART
DetailsTom Arcoraci
fn insp todd- ###-#### ok for temp occ see c/notice 2/14/2002 11:10:41 AM
Temporary occupancy  2/14/2002 PART
Temp. Occ. Cert. #4724 issued 2-14-02 to Dillon Ltd. Partnership.
BLD-Final2/11/20022/12/20022/12/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/11/2002 at 14:13:31. Contact: ###-####. Needs all required signatures on job card, Still has bld corrections but would be ok for a temporary oc, when other agencies sign off. 2/12/2002 12:11:40 PM 2/12/2002 12:12:07 PM
BLD-Final2/7/20022/8/20022/8/2002AFAIL
DetailsJim Sly
###-#### C/N on site. 2/8/2002 10:30:12 AM
FIRE-Final Inspection2/7/20022/7/20022/7/2002PPASS
DetailsTroy Cobbley
Life/safety finaled. Notified contractor to change door hardware in basement corridor 2/7/2002 3:30:10 PM
BLD-Framing/Rough-in12/14/200112/17/200112/17/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/14/2001 at 16:41:53. Contact: . masonary wall header insp only 12/17/2001 9:58:01 AM
BLD-Foundation11/15/200111/15/200111/15/2001PPASS
DetailsTom Arcoraci
###-####
BLD-Conference11/15/200111/15/200111/15/2001PFAIL
DetailsTom Arcoraci
Added by Inspector: 408 On 11/15/2001 3:03:42 PM needs eng for cut out in masonary wall for door no detail on plan
BLD-Footing11/5/200111/6/200111/6/2001PPASS
DetailsTom Arcoraci
###-#### ROBERT
Issue PAID IN FULL permit  11/1/2001 DONE
Plan resubmittals received  10/18/2001 PASS
Reviewed resubmitted drawings and approved them.
PLANS/APPL TAKEN TO FRONT DESK  10/18/2001 PASS
Returned drawings to the permits desk for permit issuance.
CHANGE STATUS TO (PND)  10/17/2001 DONE
Drawings pulled back from the permits desk to do resubmittal review.
Plan resubmittals received  10/17/2001 DONE
Received two copies of sheet A3 with cover letter.
Inspection Record Card- Bld  8/8/2001 DONE
Print Occupancy Form  8/8/2001 DONE
Telephone call  8/8/2001 DONE
left message gave dollar amount achd is also required
Routing - PUBLIC WORKS8/1/2001 8/7/2001 PASS
Routing - PLAN CHECK8/7/2001 8/7/2001 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/7/2001 PASS
Plan assigned to (CJW)7/19/2001 8/7/2001 PASS
DetailsCarl Westfall
8/7/01 14:10:38 CJW - activity updated through activity BLDA022 from case BLD01-01951.
Routing - FIRE8/1/2001 8/6/2001 PASS
appproved without written comment
Routing - PLAN CHECK7/31/2001 8/1/2001 PASS
Routing - PLANNING7/20/2001 7/31/2001 PASS
Approved per building permit plans. (DAA & MGS).
Plan Reviewer's activity  7/31/2001 PASS
UBC plan review started July 31, 2001 and finished the next day. The drawings were approved with conditions. See the conditions list.
Routing - PUBLIC WORKS7/19/2001 7/20/2001  
Failed first review. Requires drainage plan. What site work is being done? Per Brian M. KMM
Plans ACCEPTED BY PLAN TECH  7/19/2001 DONE
Print Pending Permit.LaserJet4  7/19/2001  
Routing - PLAN CHECK10/17/2001