Office final | | | 8/23/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/22/2002 | 8/22/2002 | 8/22/2002 | A | PASS |
Troy Cobbley
|
|
|
Fire life/safety, fire alarm and fire sprinkler finaled
|
BLD-Final | 8/22/2002 | 8/22/2002 | 8/22/2002 | P | PASS |
Jim Sly
|
|
|
|
PubWorks Occupancy Approval | | | 8/6/2002 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 8/6/02. R.Rokovitz
|
BLD-Aging Inspection | 1/9/2002 | 1/9/2002 | 1/9/2002 | | PART |
Russ Owen
|
|
|
wip. 1/15/2002 9:14:19 AM
|
Override - Parcel Holds | | | 9/21/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/21/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/29/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 8/29/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 8/27/2001 | | 8/27/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/27/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2001 | | DONE |
|
|
|
|
Plan assigned to (KMM) | 7/24/2001 | | 8/27/2001 | | PASS |
Kathy Miller
|
|
|
8/27/01 13:46:34 KMM - activity updated through activity BLDA022 from case BLD01-01995.
|
Routing - PLAN CHECK | 8/7/2001 | | 8/27/2001 | | |
|
|
|
In hold box. 8/7/01 DAR
|
Plan Review Completed(1st rev) | | | 8/7/2001 | | PASS |
|
|
|
|
Routing - FIRE | 8/2/2001 | | 8/7/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/26/2001 | | 8/2/2001 | | FAIL |
|
|
|
Site plan doesn't comply with recorded plat and /or legal description per April Miller. 8/2/01 DAR
|
Routing - PLUMBING | 8/2/2001 | | 8/2/2001 | | PASS |
|
|
|
per plans and 97 upc and no connection from glycol system to sewer
|
Plan routing begun/NEW & ADDTN | | | 7/24/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 7/24/2001 | | 7/24/2001 | | PASS |
|
|
|
Approved per drh01-00123.
|
Application received | | | 7/24/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/24/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 7/24/2001 | | |
|
|
|
|