Fee Review-notes | 7/25/2001 | 7/25/2001 | 6/24/2002 | | DONE |
|
|
|
|
BLD-Final | 1/9/2002 | 1/9/2002 | 1/9/2002 | P | PASS |
Jim Storey
|
|
|
###-#### FOR OCCUPANCY signed card on site final ok. 1/9/2002 2:24:31 PM
|
Permanent Occupancy | | 1/9/2002 | 1/9/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/9/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #8986 issued 1-9-02 to Dr. Dwyer & Harrington.
|
FIRE-Final Inspection | 12/27/2001 | 12/27/2001 | 12/27/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 12/27/2001 9:49:41 AM
|
(F) Reprint permit | | | 10/8/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/4/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/4/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/4/2001 | | DONE |
|
|
|
permit ready
|
Routing - FIRE | 8/27/2001 | | 8/31/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 8/31/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/31/2001 | | 8/31/2001 | | PASS |
Ron Hill
|
|
|
|
Plan Review Report | | | 8/31/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2001 | | PASS |
Ron Hill
|
|
|
|
Plan resubmittals received | | | 8/29/2001 | | DONE |
|
|
|
two revised sheets A1.0 routed to Ron Hill
|
Case Summary (BLD) | | | 8/27/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/27/2001 | | FAIL |
Ron Hill
|
|
|
Faxed and mailed requirements to architect, route to fire for review
|
Plan assigned to (R_H) | 7/27/2001 | | 8/27/2001 | | |
|
|
|
< $25,000> Plans failed in building plan review. Faxed and Mailed requirements to Matt Rhees of Cole and Associates Architecture. Routed to Fire department for their review.
|
Routing - PLAN CHECK | 7/27/2001 | | 8/27/2001 | | FAIL |
Ron Hill
|
|
|
Route to fire, Failed in building plan review.
|
Application received | | | 7/25/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/25/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 7/25/2001 | | DONE |
|
|
|
<$25,000
|