Fee Review-notes | 8/1/2001 | 8/1/2001 | 2/28/2003 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/30/2003 | 1/30/2003 | 1/30/2003 | | PASS |
Tony Young
|
|
|
trades finaled, ok for perm. c of o 1/30/2003 8:00:36 AM
|
DOC - Permit Finaled | 1/30/2003 | 1/30/2003 | 1/30/2003 | A | PASS |
Tony Young
|
|
|
Finaled by inspector at 1/30/2003 8:00:38 AM
|
BLD-Final | 6/3/2002 | 6/4/2002 | 6/4/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/03/2002 at 16:38:48. Contact: ###-####.
ok for c of o pending trades 6/4/2002 10:19:02 AM
|
BLD-Aging Inspection | 12/10/2001 | 12/10/2001 | 12/10/2001 | | PART |
Tony Young
|
|
|
wip 12/11/2001 3:36:34 PM
|
BLD-Footing | 10/8/2001 | 10/8/2001 | 10/8/2001 | P | PART |
Tony Young
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 9/19/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/13/2001 | | DONE |
|
|
|
Letter from Boise Valley Irrigation Ditch Company received. Marlene reviewed and accepted. Plans and permit prepared for issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2001 | | DONE |
|
|
|
Took plans to front desk on behalf of Mike Phillips.
|
Inspection Record Card- Bld | | | 9/13/2001 | | |
|
|
|
|
Print Occupancy Form | | | 9/13/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 8/1/2001 | | 9/13/2001 | | PASS |
Mike Phillips
|
|
|
9/13/2001 10:23:03 MYS - activity updated through activity BLDA022 from case BLD01-02084.
|
Routing - PLAN CHECK | 8/31/2001 | | 9/13/2001 | | PASS |
|
|
|
Received letter required from Boise Valley Irrigation Ditch Company. Leter accepted and plans prepared for issuance.
|
Plan resubmittals received | | | 9/7/2001 | | DONE |
|
|
|
Received two copies of revised sheets SD1 and one cover letter. Routed to Mike P. KMM
|
Plan Reviewer's activity | | | 9/7/2001 | | PEND |
|
|
|
Waiting for letter fromn Canal company reflecting the intent and time span for the canal. This letter must be approved prior to issuing permit.
|
Plan Reviewer's activity | | | 9/5/2001 | | FAIL |
|
|
|
1). Building over area.
2). Possible Occupancy separation at mechanical room.
3). Letter from canal Company about intent for improvements to canal.
|
Routing - FIRE | 8/27/2001 | 8/30/2001 | 8/31/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 8/31/2001 | | DONE |
|
|
|
Received two copies of revised sheets SD1, and two copies of allowable floor area calculation. Routed to Mike P. KMM
|
Plan Review Completed(1st rev) | | | 8/31/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/27/2001 | | FAIL |
|
|
|
Waiting for informaiton about canal and using as area increase for building.
|
Routing - PLAN CHECK | 8/10/2001 | | 8/17/2001 | | FAIL |
|
|
|
Routed to planing.
|
Routing - PLANNING | 8/17/2001 | | 8/17/2001 | | PASS |
|
|
|
Approved per DRH01-141, and as noted on the attached letter from Bill Matter dated July 31, 2001.
|
Routing - PLAN CHECK | 8/17/2001 | | 8/17/2001 | | |
|
|
|
|
Routing - PLANNING | 8/6/2001 | | 8/9/2001 | | FAIL |
|
|
|
Landscape plan does not comply with DRH01-141 conditions of approval #1b and #1g.
|
Routing - PUBLIC WORKS | 8/1/2001 | | 8/6/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 8/1/2001 | | DONE |
|
|
|
|
Application received | | | 8/1/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/1/2001 | | |
|
|
|
|