Fee Review-notes | 8/3/2001 | 8/3/2001 | 2/7/2002 | | DONE |
|
|
|
called Kreizenbeck for final certs. they are working on them
|
DOC - L/C Approved | | | 1/4/2002 | | DONE |
|
|
|
LC #22100 issued to Dave Maloney ###-####
|
BLD-Final | 12/21/2001 | 12/24/2001 | 12/24/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/21/2001 at 13:35:49. Contact: ###-####. ok for perm occ 12/24/2001 9:55:01 AM
|
FIRE-Final Inspection | 12/21/2001 | 12/21/2001 | 12/21/2001 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Conference | 12/7/2001 | 12/10/2001 | 12/10/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/07/2001 at 11:59:59. Contact: ###-####.. misc.firestops at flutes & penetrations will be open for inspat final. 12/10/2001 12:20:41 PM
|
BLD-Other | 12/6/2001 | 12/7/2001 | 12/7/2001 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/06/2001 at 15:31:48. Contact: ###-####. no one at site no c/notice on site 12/7/2001 9:51:58 AM
|
BLD-Framing/Rough-in | 12/3/2001 | 12/3/2001 | 12/3/2001 | P | FAIL |
Russ Owen
|
|
|
mark ###-####. firewall needs to be complete at top of flutes. 12/3/2001 5:03:08 PM
|
BLD-Conference | 10/16/2001 | 10/16/2001 | 10/16/2001 | P | PASS |
Tom Arcoraci
|
|
|
4TH FLOOR NORTH TOWER ###-#### MARK wip ok to cover check fire stopping and dampers at grid inspection 10/16/2001 4:00:11 PM
|
Inspection Record Card- Bld | | | 9/10/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/10/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/10/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/7/2001 | | DONE |
|
|
|
Received two copies of revised sheets A0.2, A2.1, A3.1, A4.1, A9.1, S1.0, M2.2, E2P. Routed to Dan S. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2001 | | PASS |
|
|
|
To permit desk to process for issue.
|
Routing - PLAN CHECK | 9/7/2001 | | 9/7/2001 | | PASS |
|
|
|
Inserted corrected copies and red-lined items still in question. Approved per notes on plans and attached plan review conditions of fire & plan check divisions.
|
Plan assigned to (DRS) | 8/10/2001 | | 9/7/2001 | | PASS |
Dan Stuart
|
|
|
9/7/2001 18:47:12 DRS - activity updated through activity BLDA022 from case BLD01-02133.
|
Routing - PLAN CHECK | 8/30/2001 | | 9/6/2001 | | FAIL |
|
|
|
Suibmittals not complete. Called Vince Johnson to submit complete stamped & signed re-subittals.
|
Plan resubmittals received | | | 9/6/2001 | | DONE |
|
|
|
Received two copies of revised sheets A0.2, A2.1, A3.1, A4.1, A9.1 UNSIGNED, and two copies of stamped and signed revised sheets S1.0, M2.2, E2P. One copy of cover letter to plan review response and one hardware schedual. Routed to Dan S. KMM
|
Plan resubmittals received | | | 8/31/2001 | | |
|
|
|
Received new electrical sheet - E2P, two copies directly from office of DC Engineering to go with Vince Johnson's plans due on the 4th of September.
|
Telephone call | | | 8/30/2001 | | DONE |
|
|
|
Call to Vince Johnson to let him know the plans were back from fire today and approved. Need resubmittals to my review and if complete, the plans will be ready to issue. Vince thought the plan resubmittals were be here tomorrow as they are wrapping them up now.
|
Telephone call | | | 8/30/2001 | | DONE |
|
|
|
Call to Dennis Adams, SARMC in house architect to let him know the plans were back from fire and approved. Waiting for response to my review from NJRA. I talked with Vince and plans should be here tommorrow. If complete, will prepare plans for processing for permit ASAP.
|
Plan Review Completed(1st rev) | | | 8/30/2001 | | DONE |
|
|
|
|
Routing - FIRE | 8/25/2001 | | 8/30/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 8/15/2001 | 8/24/2001 | 8/25/2001 | | FAIL |
|
|
|
Resubmittals required. Have been request of architect by fax & hard copy. Routing to fire code analsyst for review.
|
Plan resubmittals requested | | | 8/25/2001 | | FAIL |
|
|
|
copy of conditions needing response faxed and mailed to architect
|
Routing - PLUMBING | 8/10/2001 | | 8/15/2001 | | PASS |
|
|
|
pern plans and 97 upc
|
Routing - PUBLIC WORKS | 8/10/2001 | | 8/10/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/3/2001 | | DONE |
|
|
|
|
Application received | | | 8/3/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/3/2001 | | DONE |
|
|
|
|