Fee Review-notes | 8/6/2001 | 8/6/2001 | 7/22/2002 | | DONE |
|
|
|
|
BLD-Final | 4/18/2002 | 4/18/2002 | 4/18/2002 | P | PASS |
Jim Storey
|
|
|
harold ###-####
|
BLD-Final | 4/18/2002 | 4/18/2002 | 4/18/2002 | P | PASS |
Jim Storey
|
|
|
harold ###-####
|
Permanent Occupancy | | 4/18/2002 | 4/18/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/18/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9110 issued 4-18-02 to Syringa/PMT.
|
BLD-Final | 3/27/2002 | 3/27/2002 | 3/27/2002 | P | NR |
Jim Storey
|
|
|
###-#### HAROLD need ele and door closer on 90 min door. hartwell to resolve mech. 3/27/2002 1:49:31 PM
|
BLD-Final | 3/14/2002 | 3/14/2002 | 3/14/2002 | P | FAIL |
Jim Storey
|
|
|
###-#### HAROLD 60 min door and closer/fire stop at bus bar./ele final on gen set. 3/15/2002 1:53:01 PM
|
FIRE-Final Inspection | 3/14/2002 | 3/14/2002 | 3/14/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/14/2002 4:43:17 PM
|
Plan Review Report | | | 2/25/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 1/30/2002 3:25:08 PM fire lane signs; knox box
|
FIRE-Final Inspection | 1/4/2002 | 1/7/2002 | 1/7/2002 | A | PART |
Rick Jackson
|
|
|
###-#### per Dave Miller temp occ approved pending resolution of alarm system 1/7/2002 9:33:22 AM
|
BLD-Final | 1/4/2002 | 1/7/2002 | 1/7/2002 | P | PART |
Jim Storey
|
|
|
###-#### temp ok with agreement w/d.miller. 1/7/2002 1:57:51 PM
|
BLD-Final | 1/4/2002 | 1/7/2002 | 1/7/2002 | P | PART |
Jim Storey
|
|
|
###-#### temp ok with agreement w/d.miller. 1/7/2002 1:57:51 PM
|
Temporary occupancy | | | 1/7/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4700 issued 1-7-02 to Syringa/PMT.
|
BLD-Framing/Rough-in | 12/18/2001 | 12/18/2001 | 12/18/2001 | P | PASS |
Jim Storey
|
|
|
HAROLD ###-#### CELING GRID ceilling ok for cover. 12/18/2001 3:40:21 PM
|
BLD-Framing/Rough-in | 11/14/2001 | 11/14/2001 | 11/14/2001 | P | PASS |
Jim Storey
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 10/18/2001 | | DONE |
|
|
|
|
Routing - FIRE | 9/14/2001 | | 9/17/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/17/2001 | | 9/17/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 9/17/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/17/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/14/2001 | | 9/17/2001 | | PASS |
Carl Westfall
|
|
|
9/17/01 13:27:04 CJW - activity updated through activity BLDA022 from case BLD01-02151.
|
Routing - PLAN CHECK | 9/7/2001 | | 9/14/2001 | | |
|
|
|
|
Plan resubmittals received | | | 9/13/2001 | | DONE |
|
|
|
Received one copy ofresponse letter & batter (ups) information from Martin Group on review comments. Routed to Richard D. KMM
|
Routing - PLUMBING | 9/5/2001 | | 9/7/2001 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - FIRE | 8/31/2001 | | 9/5/2001 | | |
|
|
|
Failed first UFC review. BATTERY ROOM INFO
|
Plan Review Completed(1st rev) | | | 9/5/2001 | | |
|
|
|
Failed first UFC review.
|
Routing - PLAN CHECK | 8/16/2001 | | 8/31/2001 | | PASS |
|
|
|
Drawings approved.
|
Plan Reviewer's activity | | | 8/30/2001 | | PASS |
|
|
|
UBC plan review started August 30, 2001 and finished the next day. The drawings were approved with conditions and "red lines". The the conditions list.
|
Routing - PUBLIC WORKS | 8/14/2001 | | 8/16/2001 | | PASS |
|
|
|
|
Application received | | | 8/6/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/6/2001 | | DONE |
|
|
|
|