Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD01-02222
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMICRON MASK SHOP
Customer NumberPCS3278
ePlanReviewNo
Description
MICRON - MASK SHOP BUILDING (SHELL) (PCS80-20003278) * TO CONSTRUCT A NEW 80,350 SQ. FT., TWO STORY WITH A 26,870 SQ. FT. BASEMENT FABRICATION AND OFFICE USE SHELL BUILDING. THIS BUILDING IS CONSTRUCTED OF CONCRETE FOUNDATION & BASEMENT, STEEL STRUCTURAL FRAME WITH CONCRETE & METAL PAN DECK FLOORS, METAL ROOF DECK, METAL STUD EXTERIOR WALLS AND METAL STUD PARTITIONS. THE 13,725 SQ. FT., ONE STORY OFFICE PORTION OF THIS BUILDING LOCATED AT THE WEST SIDE OF THE BUILDING BETWEEN GRID LINES A&C AND 2&10 IS BEING CONSTRUCTED WITH A PRE-ENGINEERED STEEL BUILDING SUPPLIED BY GEM. THIS OFFICE SECTION OF THE BUILDING AND THE REMAINING TWO STORY PORTION OF THE BUILDING ARE BEING DIVIDED BY A TWO HOUR AREA SEPARATION WALL ALONG GRID LINE C. THE 8,190 SQUARE FOOT, ONE STORY BUILDING SECTION LOCATED AT THE EAST SIDE OF THE BUILDING BETWEEN GRID LINES L&M AND 2&6 IS ALSO BEING CONSTRUCTED WITH A PRE-ENGINEERED STEEL BUILDING BY GEM. THIS BUILDING IS FULLY FIRE SPRINKLED. SPRINKLERS TO BE USED FOR AREA INCREASE. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THIS IS A SHELL PERMIT ONLY. NO OCCUPANCY IS ALLOWED UNDER THIS PERMIT. A SEPARATE TENANT IMPROVEMENT PERMIT IS REQUIRED TO FINISH THIS BUILDING FOR OCCUPANCY. FIRST FLOOR: 59,220 SQ. FT. SECOND FLOOR 21,130 SQ. FT. DRH01-000127 CUP01-00077 PC#741-01 JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  3/26/2003  
Letter of compliance  10/23/2002 DONE
Letter of Compliance #22751 issued 10-23-02.
BLD-Final10/18/200210/18/200210/18/2002PPASS
DetailsJim Storey
FIRE-Final Inspection10/14/200210/14/200210/14/2002PPASS
DetailsRick Jackson
BLD-Conference10/14/200210/14/200210/14/2002PDONE
DetailsWm. Michael Meloy
Code Occupancy Approval10/14/200210/14/200210/14/2002PPASS
DetailsWm. Michael Meloy
Approved 10/14/2002 3:00:01 PM
Inspection Record Card- Bld  6/12/2002 DONE
Print Occupancy Form  6/12/2002 DONE
FIRE-Conference5/8/20025/9/20025/9/2002APART
DetailsRick Jackson
Scheduled by Inspector: 409 On 5/8/2002 3:49:48 PM met with Jim Storey and walked through the project; some dampers appear to have the motor too close to wall to have improper fire stopping where motor hits rated wall 5/9/2002 11:01:54 AM
FIRE-Conference4/26/20024/26/20024/26/2002APART
DetailsRick Jackson
Added by Inspector: 409 On 4/26/2002 11:27:33 AM fire sprinklers installed without approved plans; talked to Mike (GC rep for Shilo) and placed stop work on fire sprinklers
BLD-Concrete4/8/20024/10/20024/10/2002PFAIL
DetailsJim Storey
#5@6pc missing at south end of 2 nd floor runing east west/ blk out and do not place concrete in thi area revise special insp report non compliant. 4/10/2002 4:11:03 PM
BLD-Concrete4/8/20024/9/20024/9/2002ANR
DetailsJim Storey
pour re-sch. for wed. pm. 4/9/2002 8:41:56 AM
BLD-Concrete4/8/20024/9/20024/9/2002PCANC
DetailsJim Storey
re-sch for wed.pm. 4/9/2002 8:43:38 AM
BLD-Concrete4/8/20024/10/20024/8/2002PCANC
DetailsJim Storey
BLD-Conference4/8/20024/10/20024/8/2002PCANC
DetailsJim Storey
BLD-Concrete4/8/20024/8/20024/8/2002PNR
DetailsJim Storey
###-#### BRIAN
BLD-Framing/Rough-in2/13/20022/13/20022/13/2002PPART
DetailsJim Storey
###-#### JEFF (REBAR & CONCRETE) slab on grade ok covered with special insp. pending report. 2/14/2002 9:13:33 AM
BLD-Foundation2/8/20022/11/20022/11/2002APASS
DetailsJim Storey
###-####/ 9a.m. rebar ok retaining wall/ pending special insp. report. 2/11/2002 8:40:05 AM
BLD-Framing/Rough-in2/5/20022/6/20022/6/2002APART
DetailsJim Storey
###-#### concrete wall and slab on grage wip/ struc. steel wip special insp work rfi for engineering repairs on track. 2/6/2002 11:22:11 AM
BLD-Concrete1/29/20022/1/20022/1/2002APART
DetailsJim Storey
###-#### placed wiyh special insp. 2/1/2002 9:39:26 AM
BLD-Footing1/31/20022/1/20022/1/2002PPART
DetailsJim Storey
###-#### placed w/special insp. 2/1/2002 1:40:56 PM
BLD-Concrete1/28/20021/30/20021/30/2002APART
DetailsJim Storey
###-#### or ###-#### Jeff cast in place openings in fab floor bar ok special insp on site pending report. 1/30/2002 10:48:55 AM
BLD-Concrete1/29/20021/30/20021/30/2002PPART
DetailsJim Storey
###-#### retaining wall footing
BLD-Concrete12/12/200112/13/200112/13/2001APART
DetailsJim Storey
###-#### pending special insp. report. 12/13/2001 3:19:59 PM
BLD-Concrete10/31/200111/2/200111/2/2001PPART
DetailsRuss Owen
nate ###-####. Special inspection will be performed for this pour. 11/2/2001 12:24:17 PM
BLD-Concrete10/31/200110/31/200110/31/2001PPART
DetailsDave Hannah
###-#### nate spec inspection by mti crew placing key way 10/31/2001 3:23:45 PM
Issue & PRINT to be Invoiced  10/17/2001 DONE
Telephone call  10/15/2001 DONE
permit ready and need ACHD
Plan assigned to (JCM)9/17/2001 10/15/2001 PASS
DetailsJohn Menard
10/15/01 09:44:31 JCM - activity updated through activity BLDA022 from case BLD01-02222.
Routing - PLAN CHECK10/10/2001 10/12/2001 PASS
Plan Reviewer's activity  10/12/2001 PASS
Shell plans approved as drawn with attached comment list. JCM
Print Occupancy Form  10/12/2001 DONE
Inspection Record Card- Bld  10/12/2001 DONE
Print Occupancy Form  10/12/2001 DONE
Inspection Record Card- Bld  10/12/2001 DONE
Inspection Record Card- Bld  10/12/2001 DONE
CHANGE STATUS TO (R)  10/12/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  10/12/2001 PASS
Routing - FIRE10/9/200110/10/200110/10/2001 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  10/10/2001 DONE
Routing - PLAN CHECK10/2/2001 10/9/2001  
Routing - PLUMBING9/25/2001 10/2/2001 PASS
Routing - PLANNING9/19/2001 9/25/2001 PASS
Approved per conditions of approval of CUP01-00077.
Routing - PUBLIC WORKS9/17/2001 9/19/2001 PASS
Plans ACCEPTED BY PLAN TECH  9/18/2001 DONE
Plan routing begun/NEW & ADDTN  9/17/2001 DONE
CHANGE STATUS TO (PND)  9/17/2001  
brought in complete plans
Plans ACCEPTED BY PLAN TECH  9/17/2001 PEND
Requires 1. Soils report before sending to outside eng.
2. Have Paul check on elect. value.
3. Metal building plans state approved for permit only not for field use.
Received Certificate of Value  9/14/2001 DONE
VOIDED CHANGE STATUS  8/20/2001 DONE
imcomplete plans as per John Menard 8/20/01-mps
First Notice8/14/20018/14/20018/14/2001 DONE
Application received  8/14/2001  
Routing Off Site - STRUCTURAL9/19/2001    
Waiting for soils report. When receive, call pdq to take plans to outside eng. KMM
9/19/01 Contacted pdq to take plans to outside eng. kmm