Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-02240
StatusFinaled
Name WALGREENS #6971
Site Address 2285 S APPLE ST
Project NameWALGREENS
Customer Number 
ePlanReviewNo
Description
WALGREENS STORE #6971 - To construct a new 14,420 sq. ft., single story, Type VN, fully fire sprinklered retail bldg. with drive-up pharmacy per approved plans and attachments. DRH01-00080 CUP01-00032 PC#673-01 Grading under own permit bld01-02251. Fire sprinklers used for area
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes7/10/20037/10/20037/10/2003 DONE
Fee Review-notes8/16/20018/16/20017/5/2002 DONE
7/5/02 left mesg at number on inspections w/Jon
9/26-called GC (jeff)
Permanent Occupancy 7/2/20027/2/2002 DONE
Details
BLD-Final7/1/20027/2/20027/2/2002APASS
DetailsJim Storey
###-#### JON c/n made ok in pharmacy.final ok 7/2/2002 10:09:29 AM
Permanent occupancy  7/2/2002 DONE
Perm. Occ. Cert. #9235 issued 7-2-02 to Walgreen's.
   7/1/2002 DONE
DetailsAnnett Moore
Parcel Tag Notes: When the sprinkler contractor calls in for his backflow permit DOUBLE FEE. per Bill V. aml Reason for OverRide:
Plan resubmittals received  6/7/2002 DONE
Received one copy of Final Affidavit for Walgreens. Put copy in file and routed a copy to Jim Storey
BLD-Final5/28/20025/29/20025/29/2002PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/28/2002 at 14:23:35. Contact: ###-####. temp ok need mti and engineer to sign off on low prism breaks / state pharmcy law need justafacation to locking hardware on egrees doors out of pharmcy 5/29/2002 3:47:45 PM
FIRE-Final Inspection5/28/20025/29/20025/29/2002APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 05/28/2002 at 09:12:39. Contact: ###-####.
Code Occupancy Approval5/28/20025/28/20025/28/2002APASS
DetailsWm. Michael Meloy
FIRE-Final Inspection5/21/20025/22/20025/22/2002AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 05/21/2002 at 07:29:09. Contact: ###-####. key locks at main exit; fire alarm phone line problems 5/22/2002 9:14:11 AM
FIRE-Hydro test above ground4/30/20025/1/20025/1/2002AFAIL
DetailsTroy Cobbley
unable to perform hydro test due to faulty valve, unerground flush ok 5/1/2002 2:47:22 PM
BLD-Other4/29/20024/30/20024/30/2002APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 04/29/2002 at 14:15:07. Contact: ###-####. c/n made ok ok to drop ceilling pending fire insp. 4/30/2002 10:06:43 AM
FIRE-Hydro test above ground4/29/20024/30/20024/30/2002PPART
DetailsTroy Cobbley
Hydro test not done. I did a rough-in inspection on the 1 hour photo, pharmacy and the drive thru canopy. Sprinkler contractor to add one hanger in canopy and change out one pendant in 1 hour photo and pharmacy to ECOH type 4/30/2002 11:33:15 AM
BLD-Framing/Rough-in4/25/20024/26/20024/26/2002APART
DetailsSteven Webb
###-#### Suspended ceiling--ok to drop tiles in main area--verify spacer bars are installed prior to final. 4/26/2002 10:27:55 AM
FIRE-Conference4/23/20024/24/20024/24/2002ANH
DetailsRick Jackson
Scheduled by a contractor via Hello! on 04/23/2002 at 10:33:35. Contact: ###-####. GC not here 4/24/2002 9:03:29 AM
FIRE-Conference4/24/20024/24/20024/24/2002PPART
DetailsRick Jackson
Scheduled by Inspector: 409 On 4/24/2002 9:03:08 AM requirements for final with GC; sprinklers required at areas above ceiling in sales areas for combustible catwalk 4/24/2002 3:46:38 PM
BLD-Framing/Rough-in3/28/20023/29/20023/29/2002APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/28/2002 at 11:54:22. Contact: ###-####. c/n made ok. 3/29/2002 9:26:07 AM
BLD-Framing/Rough-in3/27/20023/28/20023/28/2002AFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 03/27/2002 at 15:32:09. Contact: ###-####. Interior non-bearing walls--studs need screws on both sides not just one. 3/28/2002 11:42:55 AM
BLD-Other3/4/20023/5/20023/5/2002APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 03/04/2002 at 09:09:34. Contact: ###-####. roof decking welding left note for special inspector to check several areas no respection as long as sp insp signs off 3/5/2002 1:22:28 PM
BLD-Footing12/26/200112/27/200112/27/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/26/2001 at 15:10:28. Contact: ###-####. rfi from engineer for rebar configuration changed from approved plan verbal ok from hinsman and jones pending hard copy. special insp. on site ok. 12/27/2001 9:16:32 AM
BLD-Footing12/18/200112/19/200112/19/2001APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/18/2001 at 13:08:57. Contact: ###-####. ok inspection by mti 12/19/2001 12:00:06 PM
BLD-Footing12/14/200112/17/200112/17/2001APASS
DetailsJim Storey
###-#### ft ok mti report pending. 12/17/2001 9:27:10 AM
(F) Reprint permit  12/14/2001  
Override - Parcel Holds  12/13/2001  
Override - Parcel Holds  12/13/2001  
Issue PAID IN FULL permit  12/13/2001 DONE
Routing - PLANNING10/31/2001 11/1/2001 PASS
Approved per DRH01-80.
Override - Parcel Holds  11/1/2001  
verifed with Karen Gallagher that plans were ok to go to front desk. MLO
PLANS/APPL TAKEN TO FRONT DESK  11/1/2001 DONE
Print Occupancy Form  11/1/2001 DONE
Override - Parcel Holds  11/1/2001  
Inspection Record Card- Bld  11/1/2001 DONE
Telephone call  11/1/2001 DONE
permit ready and need ACHD
Plan assigned to (MLO)8/20/2001 11/1/2001 PASS
DetailsMike Otto
11/1/2001 14:02:27 MLO - activity updated through activity BLDA022 from case BLD01-02240.
Routing Off Site - STRUCTURAL10/19/2001 10/26/2001 PASS
contacted PDQ to take resubmitted plans dated 10/18/01 to Stapley Eng.dkl
Routing - PLUMBING10/25/2001 10/26/2001 PASS
roof drainage to terminate 12" above grade per P1.1
Routing - PLAN CHECK10/24/2001 10/25/2001 PASS
passed with condition on Door A to office area
Plan resubmittals received  10/24/2001 DONE
Received three copies of revised sheet A1.1 Routed to Mike O. kmm
Plan resubmittals received  10/23/2001 DONE
Received three copies of revised sheets S6.0, ,P1.1, and P2.1. One copy of cover letter. Routed to Mike P. KMM
Plan resubmittals received  10/18/2001  
Received two sets of sheet S6.0 with cover letter and one set of structural calculations. Routed to mike otto. This submittal is incomplete per written notice to architect. Contacted architect to provide additional plan sheet S6.0. The additional copy of the letter from the engineer and the calcs as requested will be copied by City Staff for the architect. MLO
Routing - PUBLIC WORKS10/15/2001 10/15/2001 PASS
Routing - FIRE10/9/2001 10/12/2001 PASS
Plan Review Completed(1st rev)  10/12/2001 FAIL
Plan resubmittals requested  10/10/2001 FAIL
additional structural corrections
Routing Off Site - STRUCTURAL10/1/2001 10/10/2001 FAIL
Contacted PDQ to take comments to structural plan check. KMM corrections sent to architect MLO
Routing - PLAN CHECK10/3/2001 10/9/2001 FAIL
9/25/01 Mike, after your first review, Public works ready to re-review. Corrections faxed and mailed to architect
Plan resubmittals requested  10/9/2001 FAIL
UBC corrections
Plan resubmittals received  10/8/2001 DONE
Received one copy of comment numbers that correspond with the original comments. Routed to Mike O. kmm
Routing Off Site - STRUCTURAL10/8/2001 10/8/2001 DONE
contacted pdq to take response to outside eng. kmm
Routing - PLUMBING9/28/2001 10/3/2001 FAIL
Plan resubmittals received  10/2/2001 DONE
received 3 revised copies of A2.2, E0.1A, A2.1, E1.1 and routed to Mike Otto
Plan resubmittals requested  10/1/2001 FAIL
structural written response for previous corrections required
Routing Off Site - STRUCTURAL9/28/2001 9/28/2001 FAIL
Contacted pdq to take revised struct. calcs. to outside eng. KMM 9-28-2001 Contacted by reviewing engineer that no written response to correction as requested was provided. Correction mailed and faxed to architect. MLO
Routing - PLANNING9/19/2001 9/28/2001 FAIL
Approved as per CUP01-00032 (Dave Abo).

Plans do not comply with Design Review conditions of approval; please note conditions 1b (east parking lot setback), 1h, 1l, 1m, and 10.
Plan resubmittals received  9/27/2001 DONE
Received two copies of revised sheets S1.0, S2.0, S3.0, S4.0, S5.0, S6.0. Routed to Mike O. Have asked Marla for one more copy, so plans can go to outside eng. KMM
Routing Off Site - STRUCTURAL9/27/2001 9/27/2001 DONE
Contacted PDQ to take one of the two received revised plans of 2.27.01 to outside eng. Then contaced Tamura about an additional copy of revised plans for inhouse routing. KMM THIS SUBMITTAL WAS INCOMPLETE STRUCTURAL CALCS NOT INCLUDED
Plan resubmittals received  9/27/2001 DONE
received 1 revised copy of S1.0, S2.0, S3.0, S4.0, S5.0, S6.0 and 3 copies of Supplemental: Structural calculations and routed to Mike Otto
Routing - PUBLIC WORKS8/21/2001 9/19/2001 FAIL
Requires new access road. New drawings required. Per Brian M. KMM
Routing Off Site - STRUCTURAL8/20/2001 9/11/2001 FAIL
Contacted pdq to take plans to outside eng. KMM
Plan resubmittals requested  9/11/2001 FAIL
structural corrections mailed and faxed to architect.
Routing Off Site - C.D.H8/20/2001 8/21/2001 PASS
Marla picked up plans to take to CDH. KMM
Plans ACCEPTED BY PLAN TECH  8/21/2001 DONE
Plan routing begun/NEW & ADDTN  8/21/2001 DONE
Plan routing begun/NEW & ADDTN  8/20/2001 FAIL
Needs to route to CDH first.
Plans ACCEPTED BY PLAN TECH  8/20/2001 FAIL
Plans need to be signed off by CDH. Contacted Marla of Tamura to come and take plans out to CDH. KMM Plans in hold box waiting to be picked up. KMM
Override - Parcel Holds  8/17/2001  
Recd Pcfee & Taken To Pln CK  8/17/2001  
Received Certificate of Value  8/16/2001 DONE
Application received  8/16/2001