Case Summary (BLD) | | | 2/24/2004 | | |
|
|
|
|
DOC - Permit Finaled | 12/10/2002 | 12/10/2002 | 12/10/2002 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 12/10/2002 1:28:30 PM
|
BLD-Final | 12/6/2002 | 12/9/2002 | 12/9/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/06/2002 at 13:32:18. Contact: ###-####.
|
BLD-Final | 12/3/2002 | 12/4/2002 | 12/4/2002 | P | PART |
Tony Young
|
|
|
###-####
ok to move items into home, need to seal firewall and under stairs, landing out rear door, tempered glass x 3, 12/4/2002 3:28:50 PM
|
BLD-Grading Inspection | 12/4/2002 | 12/4/2002 | 12/4/2002 | | BOND |
Rita DeYoung
|
|
|
Retaining walls behind house and revegetation have not been completed. Engineer recommended a $4,000.00 bond, which has been submitted. Grading and drainage is conditionally approved.
|
BLD-Foundation | 8/22/2002 | 8/22/2002 | 8/22/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/22/2002 at 07:15:40. Contact: ###-####.wip, upper portion of retaining wall 8/22/2002 9:49:38 AM
|
BLD-Foundation | 8/13/2002 | 8/13/2002 | 8/13/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/13/2002 at 09:36:21. Contact: ###-####.wip on retaining wall 8/13/2002 4:56:57 PM
|
BLD-Footing | 7/29/2002 | 7/29/2002 | 7/29/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/29/2002 at 08:51:37. Contact: ###-####.
upper retaining wall ftgs 7/29/2002 4:10:38 PM
|
BLD-Energy code compliance | 7/3/2002 | 7/5/2002 | 7/5/2002 | P | PART |
Tony Young
|
|
|
###-####
pending f/p sign offs 7/5/2002 2:30:42 PM
|
BLD-Framing/Rough-in | 6/25/2002 | 6/26/2002 | 6/26/2002 | P | PART |
Tony Young
|
|
|
fr guy ###-####
c/n, ok to insulate 6/26/2002 4:29:26 PM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/11/2002 | 6/11/2002 | A | CANC |
Tony Young
|
|
|
GUY ###-####
|
BLD-Framing/Rough-in | 6/11/2002 | 6/11/2002 | 6/11/2002 | P | PART |
Tony Young
|
|
|
ext, shear ok 6/12/2002 2:19:48 PM
|
BLD-Conference | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | PART |
Tony Young
|
|
|
guy -###-#### for conf
ok for 25" in front of tub 5/13/2002 1:07:50 PM
|
BLD-Aging Inspection | 12/19/2001 | 12/19/2001 | 12/19/2001 | | PART |
Tony Young
|
|
|
wip 12/19/2001 9:32:29 AM
|
BLD-Foundation | 10/19/2001 | 10/19/2001 | 10/19/2001 | P | PART |
Tony Young
|
|
|
###-#### GUY
the rest of the basment walls 10/19/2001 1:55:58 PM
|
BLD-Foundation | 10/9/2001 | 10/9/2001 | 10/9/2001 | P | PART |
Tony Young
|
|
|
###-####
north and east basment walls wip and extra #5 rebar horizontals ok pending eng. letter on beam pockets ? per verbal w/ owner 10/9/2001 2:18:37 PM
|
BLD-Foundation | 9/28/2001 | 10/1/2001 | 10/1/2001 | P | PART |
Tony Young
|
|
|
###-#### GUI
verified letter from A.HJ. eng. on soils. //south and s.east 1/2 of wall ok, per plan 10/1/2001 2:29:07 PM
|
BLD-Footing | 9/24/2001 | 9/24/2001 | 9/24/2001 | P | PASS |
Dave Hannah
|
|
|
###-#### guy
|
Issue PAID IN FULL permit | | | 9/13/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/12/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/12/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (DJO) | 9/7/2001 | | 9/12/2001 | | PASS |
Dan Overy
|
|
|
|
Plan Reviewer's activity | | | 9/12/2001 | | DONE |
|
|
|
started review on friday september 7. additional information on foundation and meeting with contractor will be needed before issuance of permit. when resolved or clarified, permit will be generated.
|
Plan Review Report | | | 9/12/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 9/12/2001 | | |
|
|
|
|
Routing - PLANNING | 8/28/2001 | 8/28/2001 | 8/29/2001 | | PASS |
|
|
|
As per approval of CFH01-00022. (Record of Survey for lot line adjustment approved 8/27/01 by April Miller)
|
Routing - PUBLIC WORKS | 8/28/2001 | 8/28/2001 | 8/29/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 8/22/2001 | 8/22/2001 | 8/28/2001 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 1 with conditions of approval in letter attached to plans.
|
Application received | | | 8/22/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 8/29/2001 | 8/29/2001 | | | PEND |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | | | PEND |
|
|
|
|
Pending Assignment by DJO | 9/12/2001 | | | | |
Dan Overy
|
|
|
|