Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/15/2003 | 4/26/2005 | | DONE |
|
|
|
|
BLD-Aging Inspection | 12/15/2003 | 12/15/2003 | 12/15/2003 | | PASS |
Tony Young
|
|
|
|
BLD-Conference | 12/15/2003 | 12/15/2003 | 12/15/2003 | P | PASS |
Tony Young
|
|
|
find out status of project
|
DOC - Permit Finaled | 12/15/2003 | 12/15/2003 | 12/15/2003 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 12/15/2003 3:48:12 PM
|
Fee Review-notes | 7/10/2003 | 7/10/2003 | 7/10/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent Occupancy | | 1/7/2003 | 1/7/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/7/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9521 issued 1-7-03 to Carl's Cycle Bldg. #1.
|
Conference | 8/14/2002 | 8/14/2002 | 8/14/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4817 extended thru 10-31-02 per Tim Hogland.
|
Fee Review-notes | 8/24/2001 | 8/24/2001 | 7/12/2002 | | DONE |
|
|
|
|
Fee Review-notes | 8/24/2001 | 8/24/2001 | 6/20/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/23/2002 | 5/24/2002 | 5/24/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/23/2002 at 14:04:53. Contact: ###-####.
|
BLD-Final | 5/23/2002 | 5/24/2002 | 5/24/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/23/2002 at 14:36:31. Contact: ###-####. temp occ ok perm occ ok after plz perm sing off or posted bond 5/24/2002 11:38:36 AM
|
Temporary occupancy | | | 5/24/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4817 issued 5-24-02 to Carl's Cycle (storage bldg.)
|
BLD-Final | 5/23/2002 | 5/23/2002 | 5/23/2002 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/23/2002 at 10:44:50. Contact: ###-####.
|
BLD-Final | 5/16/2002 | 5/17/2002 | 5/17/2002 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/16/2002 at 16:44:31. Contact: ###-####. This needs all signatures on job card. They are looking for an ok to occupy prior to this. 5/17/2002 10:58:11 AM 5/17/2002 10:59:38 AM
|
BLD-Framing/Rough-in | 4/23/2002 | 4/23/2002 | 4/23/2002 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/23/2002 at 08:36:01. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/4/2002 | 4/4/2002 | 4/4/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/04/2002 at 07:50:44. Contact: ###-####.////ext shear ok on building #1 4/5/2002 9:15:10 AM
|
BLD-Footing | 3/13/2002 | 3/14/2002 | 3/14/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/13/2002 at 15:54:00. Contact: ###-####.
|
BLD-Footing | 3/12/2002 | 3/13/2002 | 3/13/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/12/2002 at 15:12:12. Contact: ###-####. conf on footing pour informed tony 415 3/13/2002 1:04:43 PM
|
(F) Reprint permit | | | 3/11/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/8/2002 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/7/2002 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/7/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2002 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 2/27/2002 | | 3/6/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/6/2002 | | 3/6/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2002 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 8/27/2001 | | 3/6/2002 | | PASS |
John Menard
|
|
|
3/6/2002 16:15:27 JCM - activity updated through activity BLDA022 from case BLD01-02338.
|
Routing - PLAN CHECK | 11/6/2001 | | 2/27/2002 | | |
|
|
|
|
Plan resubmittals received | | | 2/27/2002 | | DONE |
|
|
|
Received five copies of resubmittal Sheet "1 of 1 Grading & Drainage Plan". Routed to John Menard.
|
Routing - PLANNING Land Div | 2/19/2002 | | 2/26/2002 | | PASS |
|
|
|
Land division ok. Returned to Plan Review. (blc)
|
Override - Parcel Holds | | | 2/19/2002 | | |
|
|
|
|
Routing - PLANNING Land Div | 11/5/2001 | | 11/6/2001 | | FAIL |
|
|
|
11/6/01 Per Karen Gallagher, they still need to do a record of survey. blc
|
Plan resubmittals received | | | 10/25/2001 | | DONE |
|
|
|
Received two copies of revised sheets SD1.0, A3.0 and one copy of cover letter. Routed to John M. kmm
|
Routing - PUBLIC WORKS | 9/26/2001 | | 9/28/2001 | | FAIL |
|
|
|
Requires proof of legal land division. Per April Miller
|
Routing - PLAN CHECK | 9/18/2001 | | 9/26/2001 | | |
|
|
|
|
Routing - FIRE | 9/14/2001 | 9/17/2001 | 9/17/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 9/17/2001 | | 9/17/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 9/17/2001 | | 9/17/2001 | | FAIL |
|
|
|
Proof of legal land division per April Miller
|
Routing - FIRE | 9/10/2001 | 9/13/2001 | 9/14/2001 | | FAIL |
Bill Alexander
|
|
|
Lack hydrant flow.
|
Routing - PLAN CHECK | 9/14/2001 | | 9/14/2001 | | |
|
|
|
|
Plan resubmittals received | | | 9/14/2001 | | DONE |
|
|
|
Received 2 revised copies of SD-.0 & SD1.2 and routed to Bill Alexander.
|
Plan Reviewer's activity | | | 9/12/2001 | | PASS |
|
|
|
Resubmitted plans sheets reviewed and approved as submitted. JCM
|
Routing - FIRE | 9/4/2001 | 9/7/2001 | 9/10/2001 | | FAIL |
Bill Alexander
|
|
|
Lack hydrant flow.
|
Plan resubmittals received | | | 9/10/2001 | | DONE |
|
|
|
Received four copies of revised sheetSD1.0. One copy of response letter to John M. and one copy of United Water letter. Routed to John M. KMM
|
Plan resubmittals received | | | 9/10/2001 | | DONE |
|
|
|
Received two copies of revised sheets SD1.0, A1.2, A3.0, A3.1, A4.0, A5.0, A5.1, one copy of response letter and review comment list. Routed to John M
|
Plan Review Completed(1st rev) | | | 9/10/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/10/2001 | | 9/10/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 8/30/2001 | | 9/4/2001 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/4/2001 | | |
|
|
|
Mailed the architect of record a copy of the comment list requesting revisions. JCM
|
Routing - PLANNING | 8/28/2001 | | 8/30/2001 | | PASS |
|
|
|
Approved per DRH01-75 and CUP01-16.
|
Application received | | | 8/30/2001 | | PASS |
|
|
|
Approved per CUP01-16
|
Application received | | | 8/30/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/27/2001 | | 8/28/2001 | | FAIL |
|
|
|
proof of legal land division.
|
Plan routing begun/NEW & ADDTN | | | 8/27/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2001 | | PEND |
|
|
|
Requires struct. calcs. Contacted Rick of this need. kmm
|
Received Certificate of Value | | | 8/24/2001 | | DONE |
|
|
|
|
Application received | | | 8/24/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/24/2001 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/24/2001 | | DONE |
|
|
|
|