Fee Review-notes | 8/31/2001 | 8/31/2001 | 7/19/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 4/22/2002 | | DONE |
|
|
|
Letter of Compliance #22342 issued 4-22-02.
|
BLD-Final | 4/16/2002 | 4/17/2002 | 4/17/2002 | A | PASS |
Russ Owen
|
|
|
fn pete- ###-####Apears ok ther is a new detail for the masonry wall that is stamped the engineer, dated 4/8/02. The roof structure is complete and attic is insulated. It appears ok with visual inspection of blown attic. Prior inspection history of this permit is not clear. 4/17/2002 11:53:09 AM
|
BLD-Final | 4/16/2002 | 4/16/2002 | 4/16/2002 | P | NR |
Jim Sly
|
|
|
fn pete- ###-#### NR 4/16/2002 4:48:21 PM
|
BLD-Framing/Rough-in | 1/28/2002 | 1/29/2002 | 1/29/2002 | A | NR |
Carl Dependahl
|
|
|
###-#### PETE CALL FIRST PLEASE, complete roof, get other r/i's 1/29/2002 12:04:37 PM
|
BLD-Concrete | 1/7/2002 | 1/7/2002 | 1/7/2002 | P | PART |
Carl Dependahl
|
|
|
###-####, grout pour, pend detail 1/7/2002 2:00:26 PM
|
BLD-Conference | 1/7/2002 | 1/7/2002 | 1/7/2002 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/7/2002 9:13:29 AM ok to grout pending faxed detail...
|
BLD-Concrete | 1/4/2002 | 1/4/2002 | 1/4/2002 | P | PART |
Carl Dependahl
|
|
|
PETE ###-####, block in place, need detail onsite to verify steel. 1/4/2002 5:04:04 PM
|
BLD-Conference | 1/4/2002 | 1/4/2002 | 1/4/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/4/2002 2:27:30 PM w/ pete re masonry; take photos
|
Issue & PRINT to be Invoiced | | | 10/24/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/16/2001 | | 10/22/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2001 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/22/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/22/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2001 | | DONE |
|
|
|
permit ready
|
Plan assigned to (JCB) | 9/5/2001 | | 10/22/2001 | | PASS |
Jason Blais
|
|
|
10/22/2001 13:42:05 JCB - activity updated through activity BLDA022 from case BLD01-02414.
|
Plan resubmittals received | | | 10/18/2001 | | DONE |
|
|
|
Received two copies of resubmittal of sheets A1.1, A3.1, A6.1, and A8.1 with cover letter to include comments calcs. Routed to Jason Blais.
|
Routing - PLAN CHECK | 10/1/2001 | | 10/16/2001 | | FAIL |
|
|
|
Architect and engineer did NOT address all issues in intitial review. Second plan review report sent. Resubmittals and response required for further review.
|
Plan resubmittals requested | | | 10/16/2001 | | |
|
|
|
Plan resubmittals, engineering, and written response required again for further review.
|
Plan resubmittals received | | | 10/12/2001 | | DONE |
|
|
|
Received resubmittals sheets A1.1, A2.1, A3.1, A6.1 and structural notes and forwarded to Jason Blais.
|
Routing - PLAN CHECK | 9/5/2001 | | 10/1/2001 | | FAIL |
|
|
|
Plan review report faxed to architect and engineer. Resubmittal sheets and additional engineering required for further review.
|
Plan resubmittals requested | | | 10/1/2001 | | |
|
|
|
Resubmittal plans and additional engineering required for further review.
|
Plans ACCEPTED BY PLAN TECH | | | 9/4/2001 | | DONE |
|
|
|
site plan not dimensioned
|
Received Certificate of Value | | | 9/4/2001 | | DONE |
|
|
|
|
Application received | | | 8/31/2001 | | |
|
|
|
|