BLD-Final | 6/5/2002 | 6/6/2002 | 6/6/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/05/2002 at 16:45:54. Contact: ###-####.
|
DOC - Permit Finaled | 6/6/2002 | 6/6/2002 | 6/6/2002 | A | PASS |
Tony Young
|
|
|
Finaled by inspector at 6/6/2002 10:54:43 AM
|
BLD-Grading Inspection | 6/5/2002 | 6/5/2002 | 6/5/2002 | | PASS |
Rita DeYoung
|
|
|
Final grading and drainage complete and approved.
|
BLD-Energy code compliance | 2/26/2002 | 2/27/2002 | 2/27/2002 | A | PART |
Carl Dependahl
|
|
|
###-####; ok to cover, walls ok. 2/27/2002 11:14:08 AM
|
BLD-Framing/Rough-in | 2/21/2002 | 2/21/2002 | 2/21/2002 | P | PASS |
Tom Arcoraci
|
|
|
bryon ###-#### fr
|
BLD-Framing/Rough-in | 2/19/2002 | 2/20/2002 | 2/20/2002 | A | NR |
Dave Hannah
|
|
|
Scheduled by Inspector: 408 On 2/19/2002 4:35:54 PM no plans or truss eng on site talked with framer he will get them and reschedule for tomorrow 2/20/2002 3:21:54 PM
|
BLD-Framing/Rough-in | 2/19/2002 | 2/19/2002 | 2/19/2002 | P | CANC |
Tom Arcoraci
|
|
|
###-#### JOHN no time 2/19/2002 4:41:55 PM
|
BLD-Framing/Rough-in | 1/24/2002 | 1/24/2002 | 1/24/2002 | P | PART |
Tony Young
|
|
|
###-#### shear nailing
ext. shear ok on hackberry house, not tiverton, bp #s and addresses messed up between johns 2 houses 1/24/2002 2:01:58 PM
|
(F) Reprint permit | | | 1/23/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/23/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/23/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/23/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/23/2002 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 1/17/2002 | 1/17/2002 | 1/17/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### shear nailing HD hold downs not bolted down in walls panels not nailed per plans 1/17/2002 2:41:10 PM
|
BLD-Aging Inspection | 1/16/2002 | 1/16/2002 | 1/16/2002 | | PART |
Tony Young
|
|
|
wip 1/16/2002 9:54:15 AM
|
BLD-Concrete | 11/15/2001 | 11/16/2001 | 11/16/2001 | P | PART |
Tony Young
|
|
|
###-#### JOHN
interior ftgs in basement, wip 11/16/2001 2:40:52 PM
|
BLD-Foundation | 10/31/2001 | 10/31/2001 | 10/31/2001 | P | PART |
Tony Young
|
|
|
###-#### STEVE
ok for walls 10/31/2001 2:40:00 PM
|
BLD-Foundation | 10/24/2001 | 10/25/2001 | 10/25/2001 | A | PART |
Tony Young
|
|
|
###-#### steve
basement wall steel, ok so far, starting to stand panels 10/25/2001 10:32:31 AM
|
BLD-Grading Inspection | 10/19/2001 | 10/19/2001 | 10/19/2001 | | PASS |
Rita DeYoung
|
|
|
Geotechnical engineer has approved foundation subgrade.
|
BLD-Footing | 10/17/2001 | 10/19/2001 | 10/19/2001 | A | PART |
Tony Young
|
|
|
###-#### STEVE
|
BLD-Conference | 10/17/2001 | 10/18/2001 | 10/18/2001 | A | PART |
Tony Young
|
|
|
steve ###-####
conf. on ftgs, engineering, soils, etc. ///need clarification from structural eng. on which drawing to use for basment wall 10/18/2001 10:15:48 AM
|
Inspection Record Card- Bld | | | 10/11/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/8/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/3/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/3/2001 | | DONE |
|
|
|
permit ready
|
Plan assigned to (DJO) | 10/2/2001 | 10/2/2001 | 10/2/2001 | | PEND |
Dan Overy
|
|
|
10/2/2001 16:39:55 DJO - activity updated through activity BLDA022 from case BLD01-02470.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/2/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 10/2/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 10/2/2001 | | DONE |
|
|
|
AFTER FURTHUR CONVERSATION WITH ERIC FROM PINNACLE AND DAVE RAUSCHER FROM RAUSCHER DESIGN, ALL FOOTINGS, BEAMS, ETC. WERE MARKED ON PLANS. DUE TO THE EXCESSIVE AMOUNT OF RED-LINING AND NUMBERING OF SELECT ITEMS, ONLY ONE APPROVED SET IS BEING ISSUED.,
|
Routing - PLANNING | 9/24/2001 | | 10/2/2001 | | PASS |
|
|
|
Staff level approval needed per Terry Records. Sev Jones is working on this project with Planning and Zoning and he WILL have to sign off on the approved plans.
|
Plans ACCEPTED BY PLAN CHECK | | | 9/28/2001 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 9/28/2001 | | PEND |
|
|
|
ALL BEAMS AND FOOTINGS WERE NOT CROSS REFERENCED TO PLAN SETS. WILL ISSUE WHEN CLEARLY INDICATED.
|
Routing - FIRE | 9/25/2001 | | 9/25/2001 | | DONE |
|
|
|
Sprinklers required per Dave Miller. Memo on file with Dan Overy: Sam Rogers 9/25/01 13:40
|
Routing - PUBLIC WORKS | 9/20/2001 | | 9/24/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 9/10/2001 | | 9/20/2001 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 1 with conditions of approval in letter attached to plan,
|
Application received | | | 9/10/2001 | | |
|
|
|
|
Pending Assignment by DJO | 9/10/2001 | | | | PEND |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 9/25/2001 | | | | PEND |
|
|
|
|